Project Roadmap

This roadmap provides a high-level overview of the project's development from the initial concept to the final submission.


Phase 1 — Project Setup & Planning (May)

Milestone: Development Environment Ready

Main Activities

  • Brainstorming and project planning
  • Flutter familiarization
  • Analysis of the previous team's implementation
  • Repository setup (GitHub, Wiki, Pull Request template, CI)
  • Research on GPS integration in Flutter

Phase 2 — Initial Development (June)

Milestone: First Functional Prototype

Main Activities

  • GUI mockups and click dummy
  • Initial GPS implementation in Flutter
  • Research on Health Connect and Apple Health APIs

Phase 3 — Core Application Development (July – Early August)

Milestone: End-to-End Walk Test Execution

Main Activities

  • Knowledge transfer with the previous development team
  • GPS-based distance estimation
  • Software architecture (feature-first structure, layered architecture, sensor abstraction)
  • Sensor sample persistence
  • Fitness assessment implementation
  • Pedometer integration
  • Patient profile persistence
  • Logging infrastructure
  • Walk session persistence

Phase 4 — Core Feature Completion (August)

Milestone: GUI Development

Main Activities

  • Test instructions screen
  • Home Screen
  • Walk Test Screen
  • Background execution and locked-screen support
  • CI/CD setup

Phase 5 — Feature Completion (September)

Milestone: Feature Complete

Main Activities

  • Completion of remaining application screens
  • Session management
  • Test abort handling
  • Data export (CSV / JSON)
  • GPS outlier detection
  • Robust distance estimation

Phase 6 — Finalization (October)

Milestone: Finalization

Main Activities

  • Continuous testing
  • Outlier detection tuning
  • Performance optimization
  • Bug fixing and application stabilization
  • Documentation and Wiki completion
  • Final project review

Note

This roadmap provides a high-level overview of the project's evolution. Detailed implementation tasks and day-to-day progress are managed separately using GitHub Issues.