Iteration 3
Nguyen Le edited this page Oct 5, 2026
·
5 revisions
Due: Nov 3, 2026
| Item | Description |
|---|---|
| Security (#22) | Baseline security setup. See Security. |
| Configuration file | Central configuration for environments and settings. |
| Presentation to stakeholder | Present progress and the design to the stakeholder. |
| Data import (#24) | Import companies and people from CSV and JSON files. |
| Unified Data Model v0 (#25) | Design and implement the first version of the Unified Data Model. |
| Identifier normalization (#26) | Normalize identifiers so the same entity can be matched across sources. |
| Entity browsing (#27) | Browse imported entities with their source provenance. |
| Legal and privacy (#34) | Review legal, licensing and privacy aspects. See Legal and Ethical Issues. |
| Societal impact and ethics (#35) | Societal impact, ethics and diversity statements. See Diversity Statement. |
| Business model and cost (#36) | Business model and project cost estimate. See Budget and Economic. |
| Rollout and user study (#40) | Rollout strategy and user study plan. |
| Ticket | Title | Type | Status |
|---|---|---|---|
| #22 | Establish security baseline | Task | Open |
| #24 | Import companies and people from CSV and JSON files | User story | Open |
| #25 | Design and implement the Unified Data Model v0 | User story | Open |
| #26 | Identifier normalization module | User story | Open |
| #27 | Browse imported entities with their source provenance | User story | Open |
| #34 | Review legal, licensing and privacy aspects | Documentation | Open |
| #35 | Write societal impact, ethics and diversity statements | Documentation | Open |
| #36 | Define the business model and estimate project cost | Documentation | Open |
| #40 | Define the rollout strategy and user study plan | Documentation | Open |
- Planned vs. done:
- What slipped:
- Done early:
- Contractor estimate for this iteration:
- What went well:
- What went wrong:
- Improvements:
| Member | Contributions (issues / PRs / commits) |
|---|---|
PULSE Wiki
- Home
- Team Structure
- Product Roadmap
- Meeting Minutes
- Risks
- User Consent and EULA
- Legal and Ethical Issues
- Economic
- Budget
- Personas
- Diversity Statement
- Overall Architecture and Class Diagrams
- Infrastructure and Tools
- Naming Conventions
- Testing Plan and Continuous Integration
- Security
- Performance
- Deployment Plan and Infrastructure
- Missing Knowledge and Independent Learning
-
Iteration and Release Notes
- Iteration 1 (Oct 6, 2026)
- Iteration 2 (Oct 20, 2026)
- Iteration 3 (Nov 3, 2026)
- Iteration 4 (Nov 17, 2026)
- Iteration 5 (Dec 1, 2026)
- Iteration 6 (Dec 15, 2026)
- Iteration 7 (Jan 19, 2027)
- Iteration 8 (Feb 5, 2027)
- Iteration 9 (Feb 16, 2027)
- Iteration 10 (Mar 2, 2027)
- Iteration 11 (Mar 16, 2027)
- Iteration 12 (Mar 30, 2027)
- Iteration 13 (Apr 13, 2027)