Release 6
Release 6
Description
This release includes a major expansion in system reporting and logging with the introduction of Touch Point Logging, Forecasting Stats, and enhancements to the Status Page. It also addresses several important bugs identified in earlier sprints. The Retention Metric Stat was deferred to a future release.
Features Delivered in This Release
-
Add Timeless Event Potential Walk-ins
#301
Logged events from users attending timeless events to better track walk-in participation. -
Create Touch Point Logic
#313
Introduced logic to capture and store user interactions at key areas across the site. -
Add Table for Touch Point Logging
#314
Backend support to log and store interaction events via a dedicated database table. -
Touch Point Log Script
#315
Script automates the collection and submission of touch point data into the system. -
Add Forecasting Stat
#194
Added statistical model to project estimated demand based on historical site usage. -
Notify Users of LOTO
#186
Implemented a notification system to alert users when equipment is locked/tagged out. -
Admin View of Tables
#305
Added a new administrative view to improve visibility and management of table data within the system.
Bug Fixes
-
Bug with Checkout System
#306
Resolved an issue that caused intermittent failures in the tool checkout process. -
Checkable Tools Bug
#302
Fixed a bug where certain tools were not appearing as checkable due to a permission mismatch.
Significance of Completed Work
With the introduction of touch point tracking, system administrators now gain deeper insight into user behavior, allowing for more informed operational decisions. The forecasting tools provide critical data for future planning. Bug fixes help ensure the platform remains stable and reliable for users.
Statistics
- Commits: 158
- Story Points Completed: 30
- Lines of Code Added: 3,200
- Lines of Code Removed: 239
- Tests Added: 0
- Issues Closed: 7 issues
Resources
Release 5
Description:
This release represents sprint 10 which was a 3-week long sprint. This release had one big feature delivered with Single Sign On (SSO) while the team progressed work on stories for Status Page and Upgrade Lockout Features while fixing known bugs within the system.
Features Delivered in This Release:
Single Sign On (SSO)
- SHIB Return #176
- SHIB redirects back to Garage
- CAS Correlation #177
- Take CAS output and correlate existing user
- Update IDM with Login Status #283
- Update IDM
- Check for Orientation Attendance #285
- Redirect users to a page for new member orientations if they have attened one
*Hide Username Login and Logout #284 - Only allow users to login via SSO except for kiosk account. Also move location of username logout button to https://engineering-garage.unl.edu/me/
- Redirect users to a page for new member orientations if they have attened one
- Handle Unknown User #178
- Handle SSO login from a use that doesn't exist in the Garage Database
Features progressed
Status Page
- Create Status Page #188
- Create the initial page for the Status Page
- Compile Machine List #187
- Compile list of locked out/ tagged out machines
- Number of Down Machines Stat #195
- Retrieve the number of LOTO's Machines
- Template Status Element #190
- Create a template element that can store relevant machine information, as well as easily be (repeatedly) added onto the website
Upgrade Lockout Feature
- INOP to Lockout #183
- Change INOP to Lockout
- Add Mandatory Description #184
- Add Mandatory Description
- Expected Date Range #185
- Add optional expected date range
Bug Fixes
Significance of Completed Work:
Release 5 incorporates the university standard of login with SSO which integrates the Kiewit Garage Manager with the UNL system and reduces the the need for users to create separate accounts. The progress on Status Page and Upgrade Lockout Feature ensures their timely development and deployment for the upcoming release 6. Bug fixes ensure over all smooth and fluid interaction with the system.
Statistics:
Number of commits: 64 commits
Story points completed: 32
Lines of code added/changed:
957 lines added
180 lines deleted
Tests added: 0
Issue closed: Closes 18 issues
Resources:
GarageStudioManager-Meeting-Release-5.zip
What's Changed
Full Changelog: https://github.com/cseseniordesign/GarageStudioManager/commits/V5.0.0
Release 4
Description:
This release represents spirnts 7, 8 & 9 for the Kiewit Garage Studio Manager Project. This release contains the Tool Checkout, Tour and Training, as well as the Bulk Permissions features. Though not included in this release, significant progress on the SSO feature.
Features Included in This Release:
Tool Checkout
- Tool View Page #163
- Added a new page to view checkable tools from the Admin point of view
- Tool Checkout Page #160
- Added a new page to view checkable tools from Warehouse point of view
- Track Tool Barcode #159
- Configured the site database to track the barcodes of tools
- Correlate User Profile #162
- Configured the site database to correlate users with tools they have checked out
- Tool Checkout Functionality #273
- Created the feature to allow users to check in and out tools
- Tool Checkout Table #275
- Created table in database to store checkable tools
- Modify Tool Creation to Allow Checkout Tool Creation #252
- Modified the process by which tools are created on the site to allow for Checkable to also be created
Tour and Training
- Tour/Training Completion page #236
- Modified the Checkout page to display information relevant to Tours and Training, and added the other necessary relevant UI elements
- Fetch User & User's events #237
- Developed the backend logic to fetch user events, as well as the logic necessary to mark those events as attended
Bulk Permissions
- Add an option to perform bulk permissions #167
- Modified the admin Tools page to give the option to perform bulk permissions
- Allow for Bulk Permissions #168
- Created backend logic to perform bulk permissions
- Create Front-End Page for Bulk Permissions Update #274
- Created a page from which bulk permissions can be performed
Significance of Completed Work:
With the addition of this release, the Tour and Training feature as well as the Tool Checkout feature enhance the Checkout system delivered last release, giving technicians the ability to perform more tasks with the website system. The Bulk Permissions feature increases the usability of the website tool system, making creating new permissions easier for site admins.
Statistics:
Number of commits: 84 commits
Story points completed: 29
Lines of code added/changed:
839 lines added
95 lines deleted
Tests added: 1
Issue closed: Closes 13 issues
Resources:
Release 3
Description:
This release represents sprints 5 & 6 for the Kiewit Garage Studio Manager project. The majority of this time was spent on developing and implementing the Warehouse Storage feature. Much of the time was also spent on developing bug fixes for the Kiewit Garage website, many of which are not a part of this release, but some are.
Features Included in This Release:
Warehouse Storage
Work Completed:
- Scan Ncard (#153)
- Added a new page that allows permitted users to input a NUID to access a given student's project portfolio
- User Correlation (#154)'
- Updated the database to allow users to be associated with projects
- Check In/Out Page (#155)
- Added a page to allow users to access the projects associated with their profile
- Bin Form Checkout (#156)
- Added a method by which new projects can be made and old projects can be edited
- Link Other Users (#157)
- Updated the database to allow users to be associated with projects they are not the owner of
- Test Warehouse Storage (#158)
- Added a unit test to assure the quality of the Warehouse Storage feature
Significance of Completed Work:
Completing the Warehouse Storage feature permits the Kiewit Garage to now have an automated process to track the status of projects within the garage. Importantly, the completion of this feature also lays important groundwork for the completion of the Tool Checkout feature.
Bug Fixes
Work Completed:
- Timeless Events bug ((#249)
- Fixed bug where events other than New Member Orientation would not work
- User Expiration Removal
- Removed User Expiration from the homepage of the Kiewit Garage website
Significance of Completed Work:
With the completion of the Timeless Event bug fix, admins of the site will now be able to create timeless events for users to access without needing to set a date. The completion of User Expiration Removal removes a unnecessary element from the homepage, which may have led to confusion amongst users.
Statistics:
Number of commits: 71 commits
Story points completed: 42
Lines of code added/changed:
4843 lines added
32 lines deleted
Tests added: 1
Issue closed: Closes 8 issues
Resources:
Release 2
Description:
This release represents sprints 3 & 4 for the Kiewit Garage Studio Manager project. The majority of this time was spent on developing and implementing all user stories from the Initial Config feature and the User Creation Overhaul feature along with integrating TravisCI for CI/CD. Below, you'll find detailed information about each feature.
Features Included in This Release:
Initial Config
Work Completed:
- 24-hour Reservation
- Changed reservable times for certain pieces of equipment and resolved logic conflicts
- Show 24-hour Reservations
- Revised the reservation page to reflect reservation time
- Addition of NUID to users
- Altered existing user database table to add NUID
- Developed code logic to automatically retrieve NUID of a user if applicable
- Addition of new categories for events and alerts
Significance of Completed Work:
This initial config setup the basis for usage of the engineering garage in which students and faculty could use site specific features. This initial config also helped us analyze the code base to get a better understanding of the logic and connections between pieces of code.
User Creation Overhaul
Work Completed:
- Add User Agreement Expiration to Database
- Added a new attribute to the User table to represent User Agreement Expiration Date
- Add User Agreement
- Added a User Agreement section to new member sign up
- Add User Agreement Lockout
- When the User Agreement has expired, the website forces the user to the renewal page and does not allow for any other access to the website
- Add User Agreement Renewal Page
- Add User Agreement Read Only Page
- Added a link within the My Account page to view the User Agreements
Additional Notes:
- There was an additional feature for adding timeless events that is used for new member signup but doesn't fit fully into the User Creation Overhaul feature
Significance of Completed Work:
The User Creation Overhaul allows for Engineering Garage specific sign ups and account attributes with the most significant addition being the User Agreement and all of its sub-stories. This makes it so that Garage Studio users must agree to terms of usage for the garage area and tools and provides general rules.
TravisCI
Work Completed:
- TravisCI runs static code analysis on every push to development
- TravisCI runs unit tests on every push to development
- Developers are notified of a failing build
Significance of Completed Work:
Automated unit testing allows for preliminary checking of coding to ensure quality development. Any builds that fail are not pushed so that there is always a working build available.
Statistics:
Number of commits: 146 commits
Story points completed: 41
Lines of code added/changed:
8,827 lines added
685 lines deleted
Tests added: 3
Issue closed: Closes [Issue #208 , Issue #142, Issue #215, Issue #210, Issue #150, Issue #214, Issue #217, Issue #222, Issue #146, Issue #145]
Resources:
Release 1
Description:
This release represents our first sprint for the Kiewit Garage project. The majority of this sprint was focused on setting up our development environment, which took up a significant portion of our time. Despite this, we successfully implemented three important features that improve functionality and branding consistency for the website. Below, you’ll find detailed information about each feature and how it fits into the overall project.
Features Included in This Release:
Hiding the Material Pricing Tab (Admin-only Access)
Work Completed:
We added a conditional check in the navigation.erb file to ensure that the "Material Pricing" tab is only visible to Admins or Innovation Studio users. This restricts access for non-admin users and improves security, ensuring sensitive information is only available to authorized users.
Significance of Completed Work:
This feature ensures that only authorized users can see the Material Pricing tab, protecting sensitive data while keeping the feature accessible to those who need it.
Additional Note:
This pull request also contains code related to Disable Parking due to shared dependencies.
Statistics:
Number of commits: 4 commits
Story points completed: 1 story point
Lines of code added/changed:
208 lines added
196 lines deleted
Tests added: No automated tests were added in this sprint.
Issue closed: Closes [Issue #144]
Disable Parking Section
Work Completed:
We modified several files (edit_user.erb, users.erb, me.erb, and new_member_signup.erb) to hide vehicle-related information from users who don’t have specific SS IDs. This ensures that only the right users can see and interact with vehicle-related details on the site, such as parking and vehicle registration.
Significance of Completed Work:
By limiting the visibility of parking-related data, we streamline the website for users who don’t need to see this information while adding a layer of security for those who should have access.
Additional Note:
While changes were made to new_member_signup.erb, we were unable to visually verify them due to limited access to that part of the website. The code is in place and will be reviewed when access becomes available.
Statistics:
Number of commits: 2 commits
Story points completed: 2 story points
Lines of code added/changed:
109 lines added
106 lines deleted
Tests added: No automated tests were added.
Issue closed: Closes [Issue #140]
Verify Page Copy Reflects Kiewit Garage
Work Completed:
We manually reviewed the entire Kiewit Garage website to ensure there were no remaining references to “NIU” anywhere in the text. This was a branding cleanup task to replace all instances of "NIU" with "Kiewit Garage."
Significance of Completed Work:
This was an important step to maintain consistent branding across the site, which helps avoid confusion and creates a professional, trustworthy appearance for users.
Statistics:
Number of commits: No code commits (manual task).
Story points completed: 1 story point
Lines of code added/changed: None
Tests added: Manual verification, no automated tests.
Additional Notes/Resources:
As mentioned, much of this sprint was focused on setting up the development environment, which reduced the time available for feature development. Now that the environment is fully configured, we expect to accelerate feature completion and implement automated testing in future sprints.
Release_1.zip
Thank you for your patience as we get everything up and running!