Workflow Variants

The backend contains two process-flow configurations.

Without SOW

Seq. Phase Baseline minutes
1 Intake 28.75
2 Planning 280
3 Fielding 240
4 Design Handoff 10
5 Scoping/Pre-Design 120
6 Additional Fielding Conditional / not fixed
7 Design 900
8 Design QC 180
9 O-Calc 465
10 Delivery 45

Known-duration total: 2,268.75 minutes (37.81 hours), excluding conditional additional fielding.

With SOW

Seq. Phase Baseline minutes
1 Intake 28.75
5 Scoping with SOW 120
6 Fielding 240
7 Design 900
8 Design QC 180
9 O-Calc 465
10 Delivery 45

Known-duration total: 1,978.75 minutes (32.98 hours).

Interpretation

The raw difference is approximately 290 minutes (4.83 hours), but the sequences are not directly equivalent and the first variant includes steps omitted or consolidated in the second. Do not treat this as proven savings without controlled operational measurement.

Calibration

For each phase, track:

  • queue time and touch time separately;
  • rework and return rate;
  • number of systems accessed;
  • number of handoffs;
  • exception frequency;
  • staff role and loaded cost;
  • completion quality;
  • With-SOW/Without-SOW comparability.