Mid Sprint 0 Status

Date: Sept 25, 2026

Completed so far

  • #15, #16 — Frontend scaffold + API client/auth interceptors
  • #17, #18 — Backend FastAPI setup + JWT authentication
  • #20 — CI pipeline running lint + tests on every PR

In progress

  • #21 — LLM Client Factory
  • #22, #23 — Market data fetching + indicator math

Blockers / risks

  • No blockers at this point — core infrastructure (auth, database, CI) landed on schedule
  • #19, #24, #25 (Alpaca credential/broker integration) not yet started; at risk of slipping past Sprint 0's end date