This is a real-time tracking of our program's progress in long-baseline observations. For each target, we requested 2 execution blocks (EB). These were nominally going to be done in one of two configurations (with half the targets done in one, and the other half in another), but the late arrival in the long-baseline configurations means its more haphazard. The C40-8 and C40-9 configurations were done in September at the end of Cycle 4. The C43-10 configuration is ongoing in Cycle 5; it will shift back to C43-9 around October 21, then to C43-8 in November.
The quick-look images are presented as a courtesy of the NAASC. They are often from a single EB, and have not been self-calibrated or optimized in any way. What we come up with should eventually be somewhat better. The images here have been stretched by eye (by Sean) to accentuate some features. If you want to play around with the .FITS files directly, they are available on the internal team webpages (see the main p484 github page). Of course, these images are not to be used or shown elsewhere without permission of the PIs, as stated in the Guiding Principles document.
| Source | EB1 | EB2 | Quick-look Image | Delivery |
|---|---|---|---|---|
| IM Lup | C40-9 | . | (none) | . |
| AS 205 | C40-9 | . | (none) | . |
| HT Lup | C40-9 | C40-9 | (none) | . |
| RU Lup | C40-9 | . | (none) | . |
| Elias 27 | C40-8 | C43-10 | elias27 | . |
| Elias 24 | C40-9 | C43-10 | (none) | . |
| HD 142666 | C40-9 | . | hd142666 | . |
| Wa Oph 6 | C40-8 | C40-9 | waoph6 | . |
| DoAr 25 | C40-9 | . | doar25 | . |
| AS 209 | C40-8 | C40-9 | as209 | . |
| WSB 52 | C40-8 | . | wsb52 | . |
| HD 143006 | C40-9 | . | (none) | . |
| Elias 20 | C40-9 | . | (none) | . |
| MY Lup | C40-9 | . | (none) | . |
| HD 163296 | C40-8 | C40-8 | hd163296 | . |
| GW Lup | C40-9 | . | (none) | . |
| Sz 129 | C40-9 | . | (none) | . |