Every process-engineering project in this hub follows the same milestone structure:
| # | Milestone |
|---|---|
| 1 | Stakeholder Alignment & Framing |
| 2 | Design Ideation |
| 3 | Final Design Selection & Endorsement |
| 4 | Create PFD for Selected Design |
| 5 | Software Selection & Management of Change Process |
| 6 | Flowsheet Model Setup |
| 7 | Model Development |
| 8 | Model Validation |
| 9 | Economic Analysis & Optimization |
| 10 | Closeout & Handoff |
To see the structure in use, including each milestone's checklist and discussion, see the MogasDebenz milestones.
License: © 2026 William Docter and Second-Hand Tigers. This work is licensed under a [Creative Commons Attribution 4.0 International License (CC BY 4.0)](https://creativecommons.org/licenses/by/4.0/). You may copy, redistribute, remix, and build upon this material, including for commercial purposes, provided you give appropriate credit to William Docter and Second-Hand Tigers and indicate if changes were made. The Second-Hand Tigers logo is not covered by this license. All rights in it are reserved.