Time: 13:30 - 15:00 Place: Online
Coordination:
- Arnaud Poncet-Montanges (Technical Group Secretary) (APM)
Present:
- Urs Kaufmann (Holinger Thun) (UK),
- Stefan Burckhardt (SB),
- Lukas Wiss (geowerkstatt) (LW),
- Sandro Gassmann (geopoint lütolf AG) (SG),
- Timothée Produit (Alpnetsystem SA (ig-group)) (TP),
- Jean-Pierre Dupuy (Morges) (JD),
- Marion Nappez (GeoConseils SA) (MN)
Excused :
- https://conference.qgis.org/presenting/ call for papers and workshops: TP will prepare a paper and hand in with the support of SB and APM. Deadline mid April!
- TEKSI General Assembly 2026, March 27th, 2025 in Zermatt
- Webinar : 31st TMMT Presentation
- Next meeting April 21st, 2026 13:30 - 15:00
- Issue #541, (duplicate #805): TWW plugin does not update service file when switching between projects - why not solved, how can they be solved? (UK)
- #908 : we can not work with hydr_geometry if this problem exists (UK).
- Integration of measuring_point and measuring_series / results - use case biol_ecol_assessment. SB shows some pre-studies and asks to implement the relations between these classe in the qgs project. Maybe also a new vw_tww_ to link discharge_points with biol_ecological_assessement and then the related measuring_points with its measuring_series and _results.
and lower part
- UK and TP are interested to follow-up on that with SB.
- Re-integration of length profile #344 - results of some more testing by SB show, that the new length profile integrate in QGIS can be used. The group is interested that this will be re-integrated in TWW.
- Please add additional requirement in the issue, so that SB can compile a requirements document until the April meeting
- Detailed geometry for wastewater structures - inner and outer border - open feature issue with short description how the digitizing tool could be improved to automatically create a geometry with inner borders also (based on a give average wall thickness)
- TMMT - current status of testing phase (AP / TP): Many bugs are already fixed - please use the latest version for additional testing till end of this week.
- Another short presentation will be done at the General Assembly in Zermatt (for desicion makers) and with all details at the Webinar (see Agenda).
Configuring of layer sia405cc* and sia405pt*