Progress Tracker

Zlatko Lakisic edited this page Aug 4, 2026 · 3 revisions

Progress Tracker

Single place to track Phase 1 progress. Source: docs/IMPLEMENTATION_TRACKER.md (update that file in-repo; mirror here when status changes).

Last mirrored: 2026-08-04

Progress dashboard


Current position

Field Value
Active milestone M4 / M7 / M8 hardware gates (software path largely wired)
Overall Phase 1 ~75%
Board Pi 4B 4GB — SSH Host comstar
Vision CodeProject.AI 10.0.10.16:32168 GPU
AO Reach 10.0.10.16:8765 v1.27.4 — greeter + voice live PASS
Speech Prefer Reach; on-Pi STT/TTS as fallback
Admin Always-on :8781/admin (status, logs SSE, restart, sleep, LAN token); see Admin Console
Tests Dart + Python unit green on Mac; live STT gate needs more bridge fixtures

Remaining before Phase 1 exit

  • Wake-word ONNX train + ROC (M4)
  • TalkingHead GLB lip-sync (M7) — HTMLAudio path VERIFIED
  • Face enrollment with person in frame + walk-up (M8)
  • 24 h soak + failure matrix (M9)

Open blockers / gaps

ID Item Blocks
B6 Faces / walk-up UAT M8 greet-by-name
B8 Wake ONNX not trained M4 ROC exit
B9 TalkingHead GLB missing M7 lip-sync UAT
B11 Live STT fixture set thin M6 voice UAT gate (≥10 source=bridge)

Milestone rollup

# Name Status Progress
M0 Ground truth done 100%
M1 Skeleton & config done 100%
M2 Vision client done 100%
M3 Attention state machine done 100%
M4 Audio pipeline in_progress ~70%
M5 AO Reach session in_progress ~80%
M6 Voice round trip in_progress ~85%
M7 Avatar & kiosk in_progress ~50%
M8 First contact in_progress ~40%
M9 Hardening & soak not_started 0%