Sprint 1

github-actions[bot] edited this page Oct 2, 2026 · 3 revisions

Generated from docs/planning/sprints/sprint-01.md. Edit that file in the repository: changes made in the wiki are overwritten.

The planning record of Sprint 1, kept as the Work Management and Delivery Specification requires (§7, §14). Reconstructed on 2026-10-02 from the items' close dates (#339), when the owner split release 1. No sprint was planned in advance: the goal summarizes what was done, and no capacity was recorded at the time. These one-day sprints adapt past work to the specification; they don't change its rules.

Field Value
Sprint Sprint 1 (Project iteration Sprint 1)
State Ended
Start 2026-09-29 00:00 Europe/Brussels, inclusive
End 2026-09-30 00:00 Europe/Brussels, exclusive
Duration One day (history, owner decision on #339)
Release v0.1

Sprint Goal

Lay the delivery foundation: the domain model, the first tasks and the Warmane lockout research.

Capacity assumptions

None recorded at the time. The sprint is reconstructed from completed work.

Selected scope and outcome

Completed outcome items, by close date (their tasks closed with them):

  • #40 (spike) Validate Warmane reset and difficulty rule matrix
  • #148 (improvement) Enforce documentation quality gates
  • #354 (user story) Respond on the website with multiple characters and presets (part delivered in v0.1)
  • #355 (user story) Capture complete and fresh raid-save evidence (part delivered in v0.1)
  • #356 (user story) Evaluate combined raids and block confirmed locks (part delivered in v0.1)

Corrected on 2026-10-03 to match the Project (#401): the list now follows each item's Sprint field, including the parts split from mixed-release items (#347).

Unfinished work: items worked on during this day but not finished stay open on their planned release, with their finished tasks recorded in this sprint. No Story Points were recorded for these days.