Sprint 4

github-actions[bot] edited this page Oct 2, 2026 · 2 revisions

Generated from docs/planning/sprints/sprint-04.md. Edit that file in the repository: changes made in the wiki are overwritten.

The planning record of Sprint 4, kept as the Work Management and Delivery Specification requires (§7, §14). Reconstructed on 2026-10-02 from the items' close dates (#339), when the owner split release 1. No sprint was planned in advance: the goal summarizes what was done, and no capacity was recorded at the time. These one-day sprints adapt past work to the specification; they don't change its rules.

Field Value
Sprint Sprint 4 (Project iteration Sprint 4)
State Ended
Start 2026-10-02 00:00 Europe/Brussels, inclusive
End 2026-10-03 00:00 Europe/Brussels, exclusive
Duration One day (history, owner decision on #339)
Release v0.2, its final sprint by owner exception: it wasn't a stabilization sprint

Sprint Goal

Adopt the Work Management and Delivery Specification and split release 1 into releases and sprints.

Capacity assumptions

None recorded at the time. The sprint is reconstructed from completed work.

Selected scope

No sprint backlog was selected in advance (see above). The scope is every item whose Sprint is Sprint 4 on the Project: 11 outcome items and 26 tasks, all in release v0.2. #203 and #350 also have tasks finished in earlier sprints, shown in brackets.

Outcome

Reviewed on 2026-10-03, after the sprint ended at 00:00, from a read-back of the Project (#400, #401).

Goal achievement

Achieved. The specification was adopted (#323, closed at 15:24) and release 1 was split into releases and sprints (#339, 16:20). The same day also planned Sprint 5 and approved release v0.3 (#360), and brought the OVH test deployment into v0.3 (#367, #378).

Completed work

Every item and task in the sprint closed as completed before the sprint ended. The Story Points are the retrospective estimates of #346, set after the work; they aren't velocity (see Sprint 5).

User stories, 18 points:

Item Story Points Closed (2 October) Tasks in Sprint 4 (earlier)
#308 create RaidManager roles with chosen permissions 5 10:27 #310, #312, #313, #314
#350 Link a community and enforce officer permissions (part delivered in v0.2) 13 16:50 #290, #296 (#286, #287, #288, #289, #294, #297, #300)

Improvements, 38 points, counted separately from stories (specification §9):

Item Story Points Closed (2 October) Tasks in Sprint 4 (earlier)
#203 Re-theme the website to the design system 8 06:20 #305, #306 (#263, #265, #275)
#158 Enforce the Epic, Feature, Story and Task hierarchy 3 15:06 #318, #321
#323 Adopt the Work Management and Delivery Specification 13 15:24 #324, #325, #326, #327, #328, #329, #330, #337
#339 Split release 1 into releases and sprints 3 16:20 #340, #341
#343 Show releases and sprints clearly on the Project 2 16:46 #344
#346 Keep each sprint on one release and complete estimates and stages 3 17:16 #347, #348
#360 Plan Sprint 5 and approve release v0.3 2 20:14 #361
#367 Apply the release decisions of 2 October and add the OVH test deployment to v0.3 3 22:44 #368
#378 Bring the OVH deployment spike into Sprint 5 1 23:31 #379

No bugs, spikes or stabilization work were in the sprint.

Unfinished work

None. No item in Sprint 4 is open or canceled.

Replanning decisions

None needed: nothing is carried over. Release v0.2, whose final sprint this was, stays open until the first deployment (owner decision 3 on #367).

Assignment history

Date Change
2026-10-02 Created as Sprint 1 (2 to 16 October) for the adoption work (#323).
2026-10-02 Owner decision on #339: renumbered Sprint 4 and shortened to 2 October, keeping its items; the two-week sprint moved to start on 3 October as Sprint 5.
2026-10-03 Reviewed after its end (#401). The reconstruction of 2 October had listed #164, #168, #172 and #198 by their close date; their tasks finished in Sprint 2, where the Project places them, and the items closed later on 2 October are added.