How This Project Is Planned
Prerequisites: Git, GitHub and pull requests and the Roadmap. This page is about how the work is organised, not what the stages are.
The work is planned the way a small team plans software: a written backlog, a size on every item, two-week sprints, a review at the end of each, and a definition of done. The plan lives in GitHub, next to the code, so a change to the plan is as visible as a change to the code.
- The board: the Clouds Against Humanity project (Sprint board, Sprint plan, Roadmap, Backlog and Agents at work views).
- The backlog: the repository's issues, grouped into epics and milestones.
-
The board as code:
board.yamlin the repository root. It names every field, option, iteration and view, and Scrum Around and Find Out (SAFO) creates and checks the board from it.
| Level | What it is | Where |
|---|---|---|
| Epic | One theme, such as stage 2 telemetry. Labelled epic, with sub-issues. Has a start and a target date that draw its bar on the Roadmap view |
Issue |
| Milestone | The same theme as a release gate, with a due date | Milestone |
| Issue | One piece of work with a reason, a "done when" list and, where it applies, a gate | Issue, sub-issue of an epic |
| Sprint | A two-week slice, Tuesday to Monday | Board field |
The eight epics are operations and gates, stage 1 hardening, stage 2 telemetry, stage 3 workloads, the edge and DMZ, multi-cloud, learning and wiki, and process.
Sprints run two weeks from a Tuesday. Sprint 1 starts on 2026-10-20; eight are defined, through 2027-02-08. Anything with a sprint is scheduled. Anything without one is backlog: wanted, ordered by priority, not promised.
Dates beyond the sprint calendar are indicative. A milestone for stage 3 or the edge carries a date so the Roadmap view has a shape, but those stages wait on a cost decision and on earlier stages, and the date moves at the sprint review when the facts do. A moved date is not a failure; a date nobody revisits is.
The maintainer has a day job and works on this in the evenings and at weekends, and has other projects. The plan is built so he can also rest:
- The sprint load counts the maintainer's own hours: the items whose Agent is You. About 10 to 12 hours is the ceiling for one sprint, less around holidays.
- Items worked by agents are limited by the agents' budgets and by review time, not by his hours. At most three agent items are in flight at once, each with its own branch and worktree.
- Sizes convert to hours so a sprint can be added up: S is about 2 hours, M about 5, L about 12 and XL about 30. An XL is split into smaller issues before it is scheduled; none sits in a sprint.
| Status | Meaning |
|---|---|
| Backlog | Not scheduled |
| Next | Scheduled for a sprint |
| In progress | Being worked, or a draft pull request is open |
| In review | A pull request is open and checks and reviews are running |
| Blocked | Needs the maintainer or an answer from outside |
| Done | Closed or merged, with the date in Done on |
SAFO moves a card as GitHub events happen: an opened issue is Backlog, a ready pull request is In review, a merged one is Done. The sprint, size, area, priority and agent are set by hand when an issue is planned.
An issue goes into a sprint when it has a reason, a "done when" checklist, a size, an owner (the maintainer or an agent), and its gate named: the decision, approval or earlier issue it waits on. An issue that cannot say what done looks like is a question, not a task.
A pull request closes its issue when all of these are true:
- The checks are green, including the
CI greengate and the secret scan. - Tests exist for what changed, and a test that should fail without the change was shown to fail.
- The docs and the wiki say what is now true, including the Roadmap status line.
- A change that touches live infrastructure shows its plan, and the maintainer read it. A plan that replaces a droplet is discarded unless that was the point.
- Risky changes had a second review: an adversarial pass by an agent that did not write the code.
- The maintainer merged it. Agents open pull requests; they do not decide what ships.
Work is routed by what it is, from measurements recorded in SAFO:
| Kind of work | Goes to |
|---|---|
| Decisions, approvals, anything that changes a live account or a credential | The maintainer |
| Implementation from a written description, wiki pages, tests | A Sonnet agent |
| Security-sensitive changes | Built by one agent, attacked by another before merge |
| Text in, text out (summaries, triage, drafts) | The local model first, checked before anything is applied |
The Agent field on the board names the intended owner. The maintainer-only steps carry the needs-maintainer label so they are easy to filter.
- Planning (the first day of a sprint): pull the next ready items from the top of the backlog until the load is full. Check the maintainer's hours first.
- During: one branch per issue, one pull request per change, small enough to review.
-
Review (the last day): post a project status update (
safo status --postbuilds it from the board, counted in code), note what slipped and why, and re-order the next sprint. The first review is scheduled as an issue so the habit exists from day one. -
Keeping the board current: a user-owned GitHub Project cannot be written by an App, so the maintainer runs
safo --board board.yaml reconcilefrom his own login on a timer. It adds new issues, marks closed ones Done and fills the area. No token is stored in CI.
Plans change in the open. To add work, open an issue with a reason and a "done when" list. To change the sequence or the board's shape, open a pull request: board.yaml is reviewed like code, and safo --board board.yaml audit reports where the live board differs from the file. A few settings (the Roadmap view's date fields, view grouping and the project's built-in workflows) cannot be set through GitHub's API; board.yaml lists them under ui_only so they are checked by eye.
Next: Roadmap.
Source for these pages lives in docs/wiki/ and is published by the Wiki workflow on every merge to main. Corrections are welcome as pull requests; edits made in the wiki editor are overwritten on the next publish. Apache-2.0 licensed, see LICENSE and NOTICE in the repository.
Support this project: support.chiefgyk3d.com, or see Home.
Core path: read in this order
- Start here if you are new
- What is the cloud
- Networking basics
- Identity, secrets, zero trust
- Infrastructure as code
- Git and pull requests
- Containers and Docker (optional)
- How money works
- Enterprise habits
- Architecture overview
- Why ZTNA and not a VPN
- Twingate
- DigitalOcean network and firewalls
- Droplet hardening
- OpenTofu, stacks and modules
- Spacelift
- Doppler and secrets
- CI, tests and the cost gate
- Threat model
- Lessons learned
- Roadmap
Track: build it yourself
Track: understand the design
The rest of this track is on the core path; see Reading order.
Track: security and threat modelling
- Threat model exercise
- Threat Dragon exercise
- Threat frameworks: STRIDE, ATT&CK, ATLAS
- Troubleshooting index
The Threat model is core step 19.
Track: detection and monitoring
- A small example: the enterprise landscape
- Detection, Wazuh and the landscape
- Cloud telemetry: what and why (unverified draft)
- Multiple sites and identity (unverified draft)
- Telemetry crosses the trust boundary (unverified draft)
- Reading a dashboard as an operator (unverified draft)
- Build your own mini SOC (unverified draft)
- Stage 2 home-side runbook (unverified draft)
- Grafana dashboards (unverified draft)