Meeting Date: 22.05.17 Author: Elia Traore

Accomplishments

  • Alex - hiatus.
  • Inbal - Continued the cloud migration and implementing the שינויוסי.
  • Ron - Researched about event system, and tested his ideas on a separate branch.
  • Elia - hiatus. (locally tested ARP implementation, continued working on the sensors simulator house design.)
  • Roy - Continued the sensors simulator implementation, added marking sensors by label. Currently at 40% progress.
  • Yarden - Learnt the dashboard demo code and how to use it.

Plans for the future

  • Alex - work on the shutter application: finish the application and the tests. If finishes ahead of time, will join the dashboard team.
  • Inbal - continue working on the aforementioned goals. Time estimation: a week and a half.
  • Ron -
    • Apologizes.
    • Implements API for applications allowing cloudDB access and listening on messages paths. If enough time remains, will start implementing the listeners the system need to set on system loading.
  • Elia - Join the dashboard team and work on the goals discussed in the weekly meeting, and continue working on the GUI house design.
  • Roy - Continue working on the simulator. Specifically - add a sensor adding GUI.
  • Yarden - Implement the dashboard. Specific goals in the weekly meeting.