06 Resources and Assignments
| Type | Typical use |
|---|---|
| Staff | Have capacity (e.g. part-time 50%), efficiency, availability period |
| Equipment | Same as above, but usually without a notion of "effort" |
| Material | Consumables, usually priced by quantity |
| Group | Used only to categorize within the resource tree; doesn't take part in scheduling itself |
Groups can be nested; the resource panel collapses by group.
| Attribute | Meaning |
|---|---|
| Availability | The fraction of each day this resource contributes. 50% = part-time. Default 100% |
| Efficiency | The output coefficient per unit of time |
| Available period (availableFrom / availableUntil) | Start date / rental period. The resource can only be scheduled within this interval |
| Cost | One-time usage cost (per use) + hourly rate |
Cost is entered on the resource, not on the task—a task's cost and total cost are aggregates derived by the engine from assignments, so the three cost columns in the outline are read-only for that reason.
The "who does what" between a task and a resource is one record (an Assignment), editable from two directions:
- Task → who does it: inspector "Task" tab → "Assigned resources" → pick a resource
- Resource → which tasks it does: inspector "Resource" tab → "Assignments" → pick a task
Both directions go through the same command and change the same record; there's no "it's different depending on which side you add it from".
Each assignment carries a units value: the fraction this resource contributes on that task, in the range (0, 1].
Select multiple tasks in the outline or Gantt (Ctrl/Cmd + click, or Shift for a range), and the Assign resources dropdown in the top bar can check resources onto all selected tasks at once:
- Checking a resource → each selected task gets one assignment with
units = 1.0; existing ones aren't added twice - Tri-state: shows indeterminate when some tasks already have that resource
- Unchecking → removes that resource from all selected tasks
- Clear assignments at the bottom → clears all assignments on all selected tasks
The dropdown collapses resources by group and has a search box at the top; when no task is selected, or all selected ones are summary tasks, the button is disabled with a visible reason (it won't "do nothing when clicked").
A bulk action leaves only one undo record: checking, clearing, or bulk-deleting tasks—a single
Ctrl+Zrestores it all.One intentional exception: "Assign resources" is a shortcut (fixed
units = 1.0); to changeunitsprecisely or delete a single assignment, still go to the inspector.
Set in the task's inspector:
| Model | What happens when you add people |
|---|---|
| Fixed duration | Duration stays the same, effort increases |
| Fixed effort | Effort stays the same, duration shrinks (5 person-days / 2 people = 3 workdays) |
Under Fixed effort, "Effort" is an input; under Fixed duration, "Effort" is a derived quantity, so that column doesn't enter edit mode under fixed duration in the outline.
Next: Leveling.