Monte Carlo Simulation

Monte Carlo simulation is a risk analysis tool that models project duration uncertainty through hundreds or thousands of random samples, answering questions like "what is the probability of completing the project before a given date."

Why Simulation is Needed

Traditional deterministic scheduling (CPM) assumes each task's duration is fixed, but in reality:

  • Task durations have uncertainty — optimistic 3 days, most likely 5 days, pessimistic 10 days
  • Uncertainty accumulates and propagates — after stacking 10 tasks, the total duration uncertainty far exceeds that of any single task
  • The critical path may change dynamically — in different sampling outcomes, different task chains may become the bottleneck

Monte Carlo simulation repeatedly runs the entire project (each time sampling from each task's uncertainty distribution) to obtain a probability distribution of project duration, rather than a single point estimate.

How to Use

1. Open the Simulation Dialog

Click menu bar "Project" → "Monte Carlo Simulation", a drawer opens from the right side.

2. Configure Parameters

  • Iterations (default 1000)

    • Number of simulation runs; more iterations = more accuracy, but takes longer
    • Recommended: 100-500 for quick preview, 1000-5000 for formal analysis
  • Confidence Level (default 95%)

    • Probability threshold for calculating confidence intervals
    • 95% means "the true value has a 95% probability of falling within this interval"

3. Run Simulation

Click the "Run Simulation" button:

  • Simulation executes in a Web Worker, won't freeze the interface
  • Button text changes to "Simulation running..." and becomes disabled
  • You can close the drawer at any time to cancel the simulation

4. View Results

When simulation completes, the drawer displays a visualization dashboard with three sections:

Statistical Metrics Cards (6 cards)

  • Mean Duration - Arithmetic average of all simulation runs
  • Median Duration - 50th percentile (P50), half the results are shorter, half are longer
  • Standard Deviation - Measures dispersion; higher values indicate greater uncertainty
  • P10 (Optimistic) - 10th percentile, meaning "only 10% of cases will be shorter"
  • P50 (Median) - Equivalent to the median
  • P90 (Conservative) - 90th percentile, "90% of cases will be shorter, only 10% will be longer"

Distribution Histogram

  • X-axis: Project duration (days)
  • Y-axis: Frequency (number of times this duration occurred)
  • Hover tooltip: Shows precise duration and frequency values
  • The histogram's shape reflects the distribution characteristics of uncertainty (symmetric / right-skewed / bimodal, etc.)

Duration Range Explanations

  • Min-Max Range

    • The shortest and longest durations that appeared across all simulations
    • These are theoretical extreme boundaries with very low actual probability
  • P10-P90 Range

    • 80% of the time, project duration will fall within this interval
    • This is a more practical "reasonable range" estimate

Technical Principles

PERT Beta Distribution

Each task's uncertainty is sampled from a Beta-PERT distribution, with parameters from:

  • Optimistic value (O) - optimisticDuration
  • Most likely value (M) - duration (the value used in CPM scheduling)
  • Pessimistic value (P) - pessimisticDuration

Beta-PERT distribution characteristics:

  • Has upper and lower bounds (O and P)
  • Peak near the most likely value M
  • Asymmetric - allows for realistic situations where "pessimistic value is farther from most likely than optimistic value"
  • Standard deviation σ ≈ (P - O) / 6

Simulation Workflow

  1. Initialize - Obtain task list and dependencies from current project's CPM scheduling results
  2. Sample - For each task, sample a duration value from its Beta-PERT distribution
  3. Re-schedule - Re-run CPM solve with sampled durations to get this iteration's project duration
  4. Repeat N times (iteration count)
  5. Statistics - Calculate mean, percentiles, and histogram from all sampled results

Web Worker Execution

To avoid blocking the UI thread (especially during thousands of iterations), the simulation engine runs in a separate Web Worker:

  • Main thread sends configuration via postMessage
  • Worker executes simulation and returns results via postMessage
  • User can continue operating the interface or close the drawer to cancel simulation while it runs

Usage Recommendations

When to Use Simulation

  • Project has high uncertainty tasks (e.g., R&D, creative work, external dependencies)
  • Need to report risk to stakeholders ("70% probability of completion before June 1")
  • Need to reserve buffer but unsure how much
  • Have a hard deadline and want to know the probability of on-time completion

When Simulation is Not Needed

  • Task durations are very certain (e.g., assembly line, standardized operations)
  • Project scale is small (<10 tasks)
  • Just want a quick look at scheduling, don't care about probabilities

How to Set Task Estimates

  • Most likely value (duration) - The value you're already using in CPM scheduling, keep it unchanged
  • Optimistic value (optimisticDuration) - Shortest duration "when everything goes smoothly," not impossible, but low probability
  • Pessimistic value (pessimisticDuration) - Longest duration "when encountering trouble but not catastrophic," also a low probability event

Common mistakes:

  • ❌ Setting optimistic value to 0 or extremely small ("theoretically could finish in 1 hour")
  • ❌ Setting pessimistic value to infinity or extreme cases ("if we rewrite everything, it'll take 1 year")
  • ✅ All three values should be reasonable estimates at different probabilities, not "worst nightmare"

How to Interpret Results

  • Mean is rarely the most useful, as the distribution may be right-skewed (extreme long tail)
  • Median (P50) is more robust, "half the cases will be shorter, half will be longer"
  • P90 is a good choice for conservative estimates, "only 10% of cases will be longer"
  • Histogram shape tells you the nature of the risk:
    • Narrow and tall → Low uncertainty, high probability within a certain range
    • Wide and flat → High uncertainty, anything can happen
    • Right-skewed (long tail to the right) → A few cases will be extremely delayed

Limitations and Considerations

  1. Resource constraints not considered - Current simulation only samples task durations, doesn't re-run resource leveling; if resources are heavily overloaded, actual duration may be longer
  2. Dependency changes not considered - Dependency relationships remain unchanged across all simulations; in real projects, tasks may be added or removed due to risks
  3. Assumes independence - Each task's uncertainty is sampled independently; in reality, multiple tasks may be affected by the same external factor (e.g., supplier delay)
  4. Requires estimate quality - Simulation accuracy completely depends on your estimates of optimistic/pessimistic values; garbage in → garbage out