A* algorithm together with Pruning was used to find the optimal schedule in the NP-Hard problem. This algorithm used Heuristics to exhaust the search space until an optimal schedule was found. Each new partial schedule created by the algorithm was iteratively extended and then ordered according to the heuristic. A fully optimal schedule is found when the head of the queue contains a schedule that includes all tasks. see pseudocode for details
PsuedoCode
OPEN is a priority queue where ordered by Heuristic
OPEN ← initialise -> Put first node in partial schedule and add to OPEN
while OPEN not empty
s - > Take the first element in OPEN
if s complete schedule then
return s (optimal)
else
Extend s to new states NEW
for all schedules s in NEW
Calculate Heuristic for each schedule s
Check for duplicates and then insert into OPEN
Insert s into CLOSED and remove s from OPEN