This page collects information that will be useful for the implementation of the new control system on ZOOM.

Background & Timeline

The ZOOM web page describes the background to the instrument. Additional material is also available on the ZOOM sharepoint. ZOOM is expected to have 36 motion axes.

The ZOOM shutter is due to open in February 2017 (see Zoom plan 28th May 2016).

Control System

ZOOM will use the IBEX control system.

ZOOM Equipment

The equipment listed below is to be used on ZOOM. Please add new information (e.g. new items of equipment, new notes, information about drivers, etc. to this table).

Manufacturer Model Type Connection Driver Notes
ISIS Fast Shutter OMRON see Fast Shutter note
ISIS Double Disc Chopper CHOPPER Ethernet/.NET #170 see ISIS Double Disk Chopper note
JAWS #179, #180 see Jaws note
Polariser, guide & collimation unit (PGC) #1233 see Polariser, Guide & Collimator note
JAWS #179, #180
ISIS Spin Flipper #1234 see SpinFlipper note
JAWS #179, #180
Alignment Laser see Alignment Laser note
JAWS #179, #180
JJ XRAY 7-axis Sample Stack Manual Sample Stack #304, #1238 see JJ X-Ray note
Translation (across beam) Sample Stack #1238 see SampleStack note
ISIS Translation (along beam) Sample Stack #1238 Driven by Beckhoff
ISIS Two Tier - possibly Sample Changer see SampleChanger note
Pneumatic Shutter OMRON see Pneumatic Shutter note
ISIS Tank Translation see Tank Translation note
Driven by Beckhoff
In/Out Monitor #267 see Monitor note
JAWS #179, #180
Detector Motion System (DMS) #1236 see Detector Motion System (DMS) note
ISIS DAE (2 or 3?) Detector Electronics Ethernet #219 see DAE note
CAEN HT Detector HV Control Ethernet #214 see CAEN HT note
OMRON PLC Ethernet FINS, #217 see OMRON PLC note
Galil DMC2280 Motion Controller Ethernet EPICS see Galil note
Beckhoff Motion Controller TBC see Beckhoff note
Pfeiffer TPG300 ISIS VACUUM SYSTEM RS232 #218 see Pfeiffer note
Julabo TBC Water Bath RS232 #187, #188 see Julabo note
PSU TBC see Power Supply Unit note
Oxford Instruments ITC503 Temp Controller RS232 see Oxford Instruments Temperature Controller note
Oxford Instruments ILM200 series Helium Level Meter RS232 EPICS see Oxford Instruments Helium Level Meter note
Eurotherm All models at ISIS Temp Controller RS232 EPICS see Eurotherm note
Eurotherm Nanodac Temp Controller Ethernet see Eurotherm note
Thurlby EX355P DC Power Supply RS232 #156 see Thurlby note
KEPCO TBC Bi-Polar Power Supply RS232 #189 see KEPCO note
Tektronix MSO 4104B Oscilloscope Ethernet #234 see Tektronix note
Tektronix AFG 3022B Function Generator Ethernet #237 see Tektronix note
PI Rotation Stage Nano-positioning Rotation Stage RS232 see Physik Instrument note
Bio-Logic Stopped Flow Cell RS232 see BioLogic note
17T Cryomag Super conducting magnet RS232
Oxford Instruments 7.5T Magnet Super conducting magnet RS232 see 7.5T Magnet note
Scientific Magnetics 3 Axis Super conducting magnet & VTI RS232 see Scientific Magnetics note
Lakeshore All models at ISIS TBC see Lakeshore note
Syringe Pumps RS232 see Syringe Pumps note
Hitachi L-7100 HPLC Pump RS232 see Hitachi note
TS-Haake Water Bath RS232 see Thermo Scientific (Haake) note
Huber Sample Stack RS232 see Huber note
Thar Pressure Cell TBC see Thar note
Goudsmit 1T Magnet Magnet TBC see Goudsmit note
Anton Paar Rheometer see Pfeiffer note
ISIS Couette Cell see ISIS Couette Cell note
McLennan Motion Controller RS232 see McLennan note
T-Jump Cell RS232 see T-JumpCell note
Dynamic Light Scattering DLS TBC see Dynamic Light Scattering (DLS) note
Raman Spectroscopy TBC see Raman Spectroscopy note
Linkam RS232 see Linkam note
Keithley All models in use at ISIS RS232, USB see Keithley note
Closed Cycle Refrigerator via Eurotherm? see CCR note

Note: Fast Shutter

Location: Front End
Due: Day 1
As used on: SANS2D

Note: ISIS Double Disk Chopper

ISIS Mk3 Chopper
Location: Front End
Due: Day 1
As used on: SANS2D

Note: Jaws

Location: Front End Vacuum Tank
Due: Day 1
As used on: Many instruments
Testing Summer 2015

Note: Polariser, Guide & Collimator

Location: Front End Vacuum Tank
Due: Day 1
1 horizontal motion axis controlling four 4m evacuated tubes

Note: SpinFlipper

Location: Fixed Collimation
Due: Day 1
4m evacuated tube & Spin-flipper unit Spin-flipper will be controlled by 2 Kepco Power Supplies

Note: Alignment Laser

Location: Blockhouse
Due: Day 1
Single in/out axis
No control of the alignment laser is required, other than the ability to move it in/out of the beam. It can treated like a monitor.

Note: JJ X-Ray 7-axis Sample Stack

Location: Blockhouse
Due: Day 1
7-axis Sample Stack Manual
See also LARMOR

Note: SampleStack

Location: Blockhouse
Due: Day 1
The JJ X-Ray sample stack will sit on rails to allow the entire sample stack to be translated back & forth along the beam. The rails are not perfectly straight, so there needs to be an axis allowing motion perpendicular to the rails to correct for any slight misalignment in the rails. In other words, there are two axes for wholesale motion of the sample stack (in addition to the 7 internal axes of the sample stack itself).

  1. Across beam (i.e. perpendicular to the rails): Alignment stage for reproducibility.
  2. Along beam (i.e. along the rails): Monitoring only, no control required.
    See ZOOM_Sample_Stack_Schematic
  3. The axis setup is described here

Note: Pneumatic Shutter

Location: Blockhouse
Due: Day 1
As used on: SANS2D

Note: Tank Translation

Location: Blockhouse
Due: Day 1
The tank will be moved by a motor connected to a Beckhoff controller.
Monitoring only, no control required.

Note: Monitor

Location: Tank
Due: Day 1
In/Out positioning - c.f. LARMOR, IMAT,others

Note: Detector Motion System (DMS)

Location: Tank
Due: Day 1

7 axes consisting of:

  1. Baffle
  2. Detector translation
  3. Strip Beam Stop
  4. 2x Disk Beam stop - x and y movement (total: 4 axes)

Note: DAE

Location: Screened Room
Due: Day 1
As used on: Many instruments

Note: CAEN HT

Location: Screened Room
As used on: LARMOR

Note: OMRON PLC

Location: TBC
As used on: LARMOR, IMAT
A full memory map is available
There are up to three functions for the PLC(s) - exactly which are to be included in the computing control is TBC. Current expectation is that the PLC will control:

  1. "Fast Shutter" (located at the front end of the beamline). SANS2D has a similar shutter.
  2. "Pneumatic Shutter" (located in the blockhouse). SANS2D has a similar shutter.
  3. Pfeiffer TPG 300 pressure gauges

Note: Galil

Location: Blockhouse x 1, Mezzanine x 4
Due: Day 1
As used on: Many instruments
There are at present 39 axes to be controlled via Galil

Note: Beckhoff

Location: TBC
As used on: IMAT
The Beckhoff controller will control two axes:

  1. the motion of the JJ X-ray sample stack along the rails see SampleStack
  2. the motion of the tank (enclosing the detectors & detector motion system).

IBEX is NOT required to actually control these two axes (that will be done independently). IBEX is required to monitor the locations reported by the Beckhoff system - a read only driver will be required.

Note: Pfeiffer

Location: TBC - alongside PLCs
Due: Day 1
As used on: LARMOR, IMAT

Note: Julabo

Location: TBC
Due: Day 1
As used on: LARMOR

Note: Power Supply Unit

Location: TBC
Due: Day 1
This is to control a magnet which will be linked to the interlocks, but there are no details at present

Note: Oxford Instruments Temperature Controller

Model: ITC503
Location: TBC
As used on: LARMOR

Note: Oxford Instruments Helium Level Meter

Model: ILM200 series
As used on: LARMOR

Note: Eurotherm

Model: all models at ISIS
Due: Day 1
Location: TBC
As used on: LARMOR
Note: ZOOM may also use a Eurotherm Nanodac to monitor detector temperatures.

Note: Thurlby

Location: TBC
As used on: LARMOR

Note: Pfeiffer

Location: TBC
As used on: LARMOR

Note: KEPCO

Location: TBC
As used on: LARMOR

Note: Tektronix
  1. Model: Oscilloscope
  2. Model: Function Generator

Location: TBC
As used on: LARMOR

Note: SampleChanger

Location: Sample Area
Due: Day 1
Same as used on: SANS2D/LARMOR, translations done via sample stack

Note: Physik Instrument

Model: Nano-positioning Rotation Stage
Location: TBC
PI Software, EPICS driver
As used on: LARMOR

Note: BioLogic

Model: Stopped Flow Cell
Location: TBC
As used on: LARMOR

Note: Scientific Magnetics

Model: 3 Axis Super conducting magnet & VTI
Location: TBC
As used on: LARMOR

Note: Lakeshore

Model: all models at ISIS
Location: TBC
As used on: LARMOR

Note: Pfeiffer

Model: all models at ISIS
Location: TBC
As used on: LARMOR

Note: Hitachi

Hitachi L-7100 HPLC pump (no longer supported at ISIS). Can't find L-7100 on Hitachi web-site (may be obsolete). Check existing SECI VI for logic and manual: both VI and manual are located here: C:\LabVIEW Modules\Drivers\Hitachi L-7100.

  • Update (27-06-2019): Hitachi pumps are no longer used. No longer any need to support them. See #3780.

Note: Thermo Scientific (Haake)

Model: Water bath
Location: TBC
As used on: LARMOR

Note: HUBER

Model: Sample Stack
As used on: SANS2D
Location: TBC

Note: Thar

Model: Pressure Cell
Location: TBC
As used on: SANS2D, LOQ

Note: Goudsmit

Model: 1T Magnet
Location: TBC
As used on: SANS2D, LOQ

Note: Pfeiffer

Model: Rheometer
Location: TBC
As used on: SANS2D
Currently controlled from a separate PC

Note: ISIS Couette Cell

Location: TBC
As used on LOQ

Note: McLennan

Location: TBC
Due: Day 1
As used on: Many instruments

Note: T-JumpCell

Location: TBC
As used on: LOQ

Note: Dynamic Light Scattering (DLS)

Location: TBC
As used on: SANS2D
There is an interaction with a LabVIEW function that ought to be reproduced.

Note: Raman Spectroscopy

Location: TBC
As used on: INTER
This may not have an existing interface, and may not need one

Note: Linkam

Location: TBC
There are VIs for this

Note: Keithley

Model: all models in use at ISIS
Location: TBC
There are VIs for this

Note: CCR

Model: TBC
Location: TBC
Details of Closed-Cycle Refrigerators at ISIS.

Note: 7.5T Magnet

Model: 7.5T Magnet

Clone this wiki locally