Plan grok compat and mermaid viz

Rick Hightower edited this page Jul 22, 2026 · 4 revisions

Current — the latest status report. Reports freeze once published; corrections appear in later reports.

Grok Build compat + Mermaid roadmap visualization

Part 1 — Grok Build compatibility (docs-only, small)

Per the xAI docs (Skills, Plugins & Marketplaces): "Grok is fully compatible with Claude Code with zero configuration needed. Grok automatically reads Claude Code marketplaces, plugins, skills, MCPs, agents, hooks, and instruction files (CLAUDE.md, Claude.md, CLAUDE.local.md, and .claude/rules/) alongside .grok/."

Consequence: our plugin (manifest, commands, skills, hooks) and the /worklog:init scaffold work in Grok Build natively — the AGENTS.md-symlink + config-only-settings design (spec §4.1) plus the shared plugin format means there is nothing to port.

Tasks:

  • Update plugin/PORTS.md: Grok Build moves from "reads the same format" to full native compatibility, zero configuration, quoting the xAI doc; matrix row updated (skills/hooks/commands/marketplaces all native).
  • README "Other harnesses" + docs/user_guide/plugin-guide.md harness notes: same claim, one sentence each, cite the doc.
  • Verification task: run /worklog:init + one /worklog:* command under Grok Build once available to us; record result in PORTS.md (claim is sourced from docs until then — say so).

Part 2 — Mermaid visualization in the roadmap

Goal: docs/roadmap.md gains native Mermaid diagrams (GitHub/GitLab/Obsidian render them; zero dependencies; still generated, deterministic, hash-gated).

Corrected date model (the load-bearing fix to the draft)

The item schema has no start/due/duration — a gantt over invented dates was rejected once before for exactly that reason. But the event log has real timestamps: created (create ev), started (first in_progress ev), closed (close ev), all ULID-derived and deterministic. So:

  • Gantt bars are historical fact, not plans: bar = started→closed (or →max-ev "now" for in-flight). Items never started render as milestones-dots at creation date or are omitted (flag). No fabricated durations, ever.
  • Wall clock never used — "now" = max ev timestamp (same rule as generated-at), keeping the CI hash check stable.

Diagrams (new ## Visual roadmap section)

  1. Dependency graph (graph TD) — the previously-recommended one, fully derivable today: nodes = open items (kind emoji: 📦 feature 🐛 bug 🔧 ops ❓ triage), solid edges = parent, dashed = depends_on, node class by status. Cap at N=40 nodes with a "+K more" note (no silent truncation).
  2. Hierarchy (graph TD, epic→story→task/subtask) for open items.
  3. Gantt (per milestone section, event-derived dates as above; done=done tag, in_progress=active, blocked=crit; unplanned items suffixed ⚡).

CLI

worklog roadmap-render --viz=deps,hierarchy,gantt|all|nonedefault: deps,hierarchy (cheap, always renderable); gantt opt-in until we've lived with it. --no-viz alias for none. Implementation: bin/viz_mermaid.py (pure functions over the fold, imported by render_roadmap), canon + CANON + init.sh list, deterministic-output tests (shuffle test extended), renderer tests for each diagram, coverage sandbox convention respected. /worklog:viz plugin command = run roadmap-render --viz=all and show it.

Out of scope

  • --html interactive dashboard (Mermaid.js standalone) — separate plan if wanted.
  • Status pie/quadrant — the kind-mix line already carries those numbers.

Verification

  • Roadmap renders on GitHub with diagrams; hash gate stays green across regenerations; shuffle-determinism test covers viz output; all suites + coverage gate pass; wiki republish picks it up via existing ledger.