Skip to content
idelatorre edited this page Feb 26, 2014 · 73 revisions

Project BackLog to complete the QA Plan

Pendings tasks

ID Chapter of the QAP Description Responsible for implementation Status of implementation Deadline for Implementation Contributors/ Reviewers Priority
2 All Propose Technologies/tools to be used for: Change/Problem Management process, Configuration Management process, Implement Traceability Matrix Izaskun de la Torre (SQS) In process - All
14 Annexes C and D (to Chapters 4.2 and 4.3) Roles: Elaborate RCM Software and Tool Chain, according to CENELEC Jan Welte. Addressed 11/06/2013 In progress (RCM Software done, Tool chain in progress) 31.07.2013 Open Medium
16 Annex E (to Chapter 5) Methods and Tools: Requirements & Architecture (Preliminary and Maintain) Marielle Petit-Doche. Addressed 11/06/2013 Accepted In Progress 21.06.2013 First Contributions 11.07.2013 Update Open Medium
17 Annex E (to Chapter 5) Methods and Tools: Testing, Verification and Validation (Preliminary and Maintain) Merlin Pokam. Addressed 11/06/2013 Medium
18 Annex E (to Chapter 5) Methods and Tools: Safety, Maintainability (Preliminary and Maintain) Jan Welte. Addressed 11/06/2013 Accepted Medium
23 Chapter 8.2 and 8.5 Prepare SCMP Jürgen Weiss - Peer Jacobsen In progress 31.07.2013 High
29 Procedures Code Review Process Bernd Hekele 20.09.2013 (descripcion on QA Plan), External description XX.XX.XXXX Medium
31 Procedure How to make a dissemination Stefan Rieger Medium
33 Template Expert Database Template ?? Medium
34 Guidelines Expert Selection Guidelines SQS Medium

Done tasks

ID Chapter of the QAP Description Responsible for implementation Deadline for Implementation Contributors/ Reviewers
0 All Include the updated version of the FPP in Github under Governance Bernd Hekele 16.05.2013 None
1 All Agree on the technologies/tools to be used for: Review Process Bernd Hekele 17.05.2013 SQS, IT, All
3 Chapter 1.2 Include the scope and goals of the project as agreed in the meeting in Paris Bernd Hekele 31.07.2013 SQS
4 Chapters 1.3, 1.4 and 1.5 Complete and implement comments made by reviewers Izaskun de la Torre (SQS) 16.05.2013 Bern Hekele
5 Chapters 2.1 and 2.2 Project organisation Chapter: review and complete Izaskun de la Torre (SQS) 17.05.2013 Bernd Hakele
6 Chapter 2.3 Project QA Management: complete Izaskun de la Torre (SQS) 17.05.2013 Bernd Hekele
7 Chapter 3 Life Cycle: Prepare short Introduction Izaskun de la Torre (SQS) 10.07.2013 Bernd Hekele
8 Chapter 3.1 and 3.2 Project and Product Life-cycle Izaskun de la Torre (SQS) 01.07.2013
9 Chapters 3.2.1 and 3.2.2 OpenETCS Software and Tool Chain life-cycle Jan Welte 31.07.2013 All
10 Chapters 3.3 QA Management Izaskun de la Torre (SQS) 21.11.2013 All
11 Chapter 4 Roles: include overview and explanations for each sub-chapter Izaskun de la Torre (SQS) 17.05.2013 Bernd Hekele
12 Annex A (to Chapter 4.1) Roles: Elaborate Required Competence Matrix (RCM) Open ETCS project Roles Bernd Hekele 17.09.2013
13 Annex B (to Chapter 4.1) Roles: Elaborate Required SCRUM Roles and Competence Matrix (RCM) Bernd Hekele 17.09.2013
15 Chapter 4.4 Elaborate Monitoring and Control Activities to be performed Izaskun de la Torre (SQS) 17.05.2013
16 Chapter 5 Methods and Tools: Overview chapter and explanations for each subchapter Izaskun de la Torre (SQS) 22.05.2013
19 Chapter 6 & 6.1 Introduction to the section and 6.1 Izaskun de la Torre (SQS) 12.07.2013 Bernd Hekele - Jan Welte
20 Chapter 6.2 & 6.3 Documentation Structure (tool chain) - Quality Control and Monitoring Izaskun de la Torre (SQS) 21.11.2013 Bernd Hekele - Jan Welte
21 Chapter 7 Documentation Control, including the Review Process Ainhoa Gracia (SQS) 28.08.2013
22 Chapter 8.1 Prepare Traceability Matrix. Identify traceability requirements. Izaskun de la Torre (SQS) 14.11.2013
24 Chapter 8.3 Fault Management Process: review, complete and prepare. Izaskun de la Torre (SQS) 19.06.2013 Bernd Hekele
25 Chapter 8.4 Prepare a grieving handling process Bernd Hekele 18.07.2013
26 Chapter 9 Supplier control Izaskun de la Torre (SQS) 22.07.2013 All
27 Chapter 10 Publishing guidelines Stefan Rieger 22.07.2013 All
28 All, Chapter 1 Abbreviations and Naming Conventions Jan Welte 11.09.2013
30 Procedures Training Process Izaskun de la Torre (SQS) 28.08.2013 All
32 Template Competence Matrix Template Jan Welte 20.09.2013 All
35 Procedure Nomenclature definition Izaskun de la Torre (SQS) 12.07.2013 All
36 Chapter 7.1 Quality Control and Monitoring Activities Izaskun de la Torre (SQS) 14.11.2013
37 Chapters 5.3 Quality Control and Monitoring Activities SQS 20.11.2013

QA Plan Deliveries

Nr Date Back log IDs Implemented Responsible Contributors/Reviewers
1 20.05.2013 4, 5, 6, 11, 15 and 16 Izaskun de la Torre (SQS) Bernd Hekele
2 28.06.2013 7, 19 y 24 Izaskun de la Torre (SQS) Bernd Hekele
3 31.07.2013 16 Marielle Petit-Doche; Izaskun de la Torre (SQS) Bernd Hekele
4 31.07.2013 3, 21, 23, 25 Izaskun de la Torre (SQS), Bernd Hekele, Jürgen Weiss

Clone this wiki locally