Project BackLog to complete the QA Plan

Pendings tasks

ID Chapter of the QAP Description Responsible for implementation Status of implementation Deadline for Implementation Contributors/ Reviewers Priority
2 All Propose Technologies/tools to be used for: Change/Problem Management process, Configuration Management process, Implement Traceability Matrix Izaskun de la Torre (SQS) In process - All
10 Chapters 3.3 QA Management Izaskun de la Torre (SQS) ToDo - Open Medium
12 Annex A (to Chapter 4.1) Roles: Elaborate Required Competence Matrix (RCM) Open ETCS project Roles Bernd Hekele ToDo - Open Medium
13 Annex B (to Chapter 4.1) Roles: Elaborate Required SCRUM Roles and Competence Matrix (RCM) Merlin Pokam. Addressed 11/06/2013 In process 31.07.2013 Open Medium
14 Annexes C and D (to Chapters 4.2 and 4.3) Roles: Elaborate RCM Software and Tool Chain, according to CENELEC Jan Welte. Addressed 11/06/2013 In progress (RCM Software done, Tool chain in progress) 31.07.2013 Open Medium
16 Annex E (to Chapter 5) Methods and Tools: Requirements & Architecture (Preliminary and Maintain) Marielle Petit-Doche. Addressed 11/06/2013 Accepted In Progress 21.06.2013 First Contributions 11.07.2013 Update Open Medium
17 Annex E (to Chapter 5) Methods and Tools: Testing, Verification and Validation (Preliminary and Maintain) Merlin Pokam. Addressed 11/06/2013 Medium
18 Annex E (to Chapter 5) Methods and Tools: Safety, Maintainability (Preliminary and Maintain) Jan Welte. Addressed 11/06/2013 Accepted Medium
20 Chapter 6.2 & 6.3 Documentation Structure (tool chain) - Quality Control and Monitoring Izaskun de la Torre (SQS) - Jan Welte In process - Bernd Hekele - Jan Welte Medium
22 Chapter 8.1 Prepare Traceability Matrix. Identify traceability requirements. First draft (Izaskun de la Torre (SQS)), ?? Medium
23 Chapter 8.2 and 8.5 Prepare SCMP Jürgen Weiss In progress 31.07.2013 Open High
28 All, Chapter 1 Abbreviations and Naming Conventions Bernd Hekele, Jan Welte 23.08.2013 Medium
29 Procedures Code Review Process Bernd Hekele Medium
30 Procedures Training Process Izaskun de la Torre (SQS) Medium
31 Procedure How to make a dissemination Stefan Rieger Medium
32 Template Competence Matrix Template Jan Welte 23.08.2013 Medium
33 Template Expert Database Template ?? Medium
34 Guidelines Expert Selection Guidelines SQS Medium

Done tasks

ID Chapter of the QAP Description Responsible for implementation Deadline for Implementation Contributors/ Reviewers
0 All Include the updated version of the FPP in Github under Governance Bernd Hekele 16.05.2013 None
1 All Agree on the technologies/tools to be used for: Review Process Bernd Hekele 17.05.2013 SQS, IT, All
3 Chapter 1.2 Include the scope and goals of the project as agreed in the meeting in Paris Bernd Hekele 31.07.2013 SQS
4 Chapters 1.3, 1.4 and 1.5 Complete and implement comments made by reviewers Izaskun de la Torre (SQS) 16.05.2013 Bern Hekele
5 Chapters 2.1 and 2.2 Project organisation Chapter: review and complete Izaskun de la Torre (SQS) 17.05.2013 Bernd Hakele
6 Chapter 2.3 Project QA Management: complete Izaskun de la Torre (SQS) 17.05.2013 Bernd Hekele
7 Chapter 3 Life Cycle: Prepare short Introduction Izaskun de la Torre (SQS) 10.07.2013 Bernd Hekele
8 Chapter 3.1 and 3.2 Project and Product Life-cycle Izaskun de la Torre (SQS) 01.07.2013
9 Chapters 3.2.1 and 3.2.2 OpenETCS Software and Tool Chain life-cycle Jan Welte 31.07.2013 All
11 Chapter 4 Roles: include overview and explanations for each sub-chapter Izaskun de la Torre (SQS) 17.05.2013 Bernd Hekele
15 Chapter 4.4 Elaborate Monitoring and Control Activities to be performed Izaskun de la Torre (SQS) 17.05.2013
16 Chapter 5 Methods and Tools: Overview chapter and explanations for each subchapter Izaskun de la Torre (SQS) 22.05.2013
19 Chapter 6 & 6.1 Introduction to the section and 6.1 Izaskun de la Torre (SQS) 12.07.2013 Bernd Hekele - Jan Welte
21 Chapter 7 Documentation Control, including the Review Process Ainhoa Gracia (SQS) 28.08.2013
24 Chapter 8.3 Fault Management Process: review, complete and prepare. Izaskun de la Torre (SQS) 19.06.2013 Bernd Hekele
25 Chapter 8.4 Prepare a grieving handling process Bernd Hekele 18.07.2013
26 Chapter 9 Supplier control Izaskun de la Torre (SQS) 22.07.2013 All
27 Chapter 10 Publishing guidelines Stefan Rieger 22.07.2013 All
35 Procedure Nomenclature definition Izaskun de la Torre (SQS) 12.07.2013 All

QA Plan Deliveries

Nr Date Back log IDs Implemented Responsible Contributors/Reviewers
1 20.05.2013 4, 5, 6, 11, 15 and 16 SQS, IT Bernd Hekele
2 28.06.2013 7, 19 y 24 SQS, IT Bernd Hekele
3 31.07.2013 16 Marielle Petit-Doche; SQS, IT Bernd Hekele
4 31.07.2013 3, 21, 23, 25 SQS, IT, Bernd Hekele, Jürgen Weiss