Project BackLog to complete the QA Plan

ID

Chapter of the QAP

Description

Responsible for implementation

Status of implementation

Deadline for Implementation

Contributors/Reviewers

Priority

0

All

Include the updated version of the FPP in Github under Governance

Bernd Hekele

Done

16.05.2013

None

High

1

All

Agree on the technologies/tools to be used for:

  • Review Process

Bernd Hekele

Done

17.05.2013

SQS, IT

All

High

2

All

Propose Technologies/tools to be used for:

  • Error Management process
  • Maintain and manage the backlogs
  • Implement Traceability Matrix

SQS, IT

In process

30.05.2013

All

3

Chapter 1.2

Include the scope and goals of the project as agreed in the meeting in Paris

Jan Welte??

High

4

Chapters 1.3, 1.4 and 1.5

Complete and implement comments made by reviewers

SQS, IT

Done

16.05.2013

Bern Hekele

High

5

Chapters 2.1 and 2.2

Project organisation Chapter: review and complete

SQS, IT

Done

17.05.2013

Bernd Hakele

High

6

Chapter 2.3

Project QA Management: complete

SQS, IT

Done

17.05.2013

Bernd Hekele

Medium

7

Chapter 3

Life Cycle: Prepare short Introduction

SQS, IT

In process

14.05.2013

Bernd Hekele

High

8

Chapter 3.1 & 3.2

Project and Product Life-cycle

??

Medium

9

Chapters 3.2.1 and 3.2.2

OpenETCS Software and Tool Chain life-cycle

Jan Welte. Addressed 11/06/2013

Medium

10

Chapter 4

Roles: include overview and explanations for each sub-chapter

SQS, IT

Done

17.05.2013

Bernd Hekele

High

11

Annex to Chapter 4.1

Roles: Elaborate Required Competence Matrix (RCM) Open ETCS project Roles

Merlin Polkam. Addressed 11/06/2013

Medium

12

Annexes to Chapters 4.2 and 4.3

Roles: Elaborate RCM Software and Tool Chain, according to CENELEC

Jan Welte. Addressed 11/06/2013

Medium

13

Chapter 4.4

Elaborate Monitoring and Control Activities to be performed

SQS, IT

Done

17.05.2013

Medium

14

Chapter 5

Methods and Tools: Overview chapter and explanations for each subchapter

SQS, IT

Done

22.05.2013

High

15

Annex to Chapter 5

Methods and Tools: Requirements & Architecture

(Preliminary and Maintain)

Marielle Petit-Doche. Addressed 11/06/2013

Medium

16

Annex to Chapter 5

Methods and Tools: Testing, Verification and Validation

(Preliminary and Maintain)

Merlin Polkam. Addressed 11/06/2013

Medium

17

Annex to Chapter

Methods and Tools: Safety, Maintainability

(Preliminary and Maintain)

Jan Welte. Addressed 11/06/2013

Medium

18

Chapter 6

Documentation Structure

SQS, IT

ToDo

14.06.2013

Bernd Hekele

Jan Welte

High

19

Chapter 7

Documentation Control, including the Review Process

SQS IT

In process

14.06.2013

High

20

Chapter 8.1

Prepare Traceability Matrix. Identify traceability requirements.

??

Medium

21

Chapter 8.2 and 8.5

Prepare SCMP

??

High

22

Chapter 8.3

Error Management Process: review, complete and prepare.

SQS, IT

In process

14.05.2013

Bernd Hekele

High

23

Chapter 8.4

Prepare a grieving handling process

Bernd Hekele

High

24

All

Search for open source tools to compare files of any type

SQS, IT

ToDo

25

All, Chapter 1

Abbreviations and Naming Conventions

            </p>
        </td>
        <td width="124" valign="top">
            <p>
                Bernd Hekele
            </p>
        </td>
        <td width="110" valign="top">
        </td>
        <td width="111" valign="top">
        </td>
        <td width="94" valign="top">
        </td>
        <td width="76" valign="top">
            <p>
                Medium
            </p>
        </td>
    </tr>

26

Procedures

Code Review Process

??

Medium

QA Plan Deliveries

Nr

Date

Back log IDs Implemented

Responsible

Contributors/Reviewerws

1

20.05.2013

4, 5, 6, 10, 13 y 14

SQS, IT

Bernd Hekele

1

14.06.2013

7, 18, 19 y 22

SQS, IT

Bernd Hekele

Clone this wiki locally