This week we made a lot of progress finalizing the design for the payload software. This was mostly a result of writing the design document. There was much communication with the electrical team.
Next week is finals week. We will be writing our progress report and recording our presentation.
One problem we are encountered is the slow response to questions that arise about the RockSat-X program. I have several questions about the format and delivery of telemetry data that won't be answered until mid- to late-next week. That information was not able to be included in the design document.