Skip to content

Sprint 11 November 15th 2017

Aileen Devine edited this page Dec 27, 2017 · 1 revision

On November 15th, the TalentMAP team met to perform a retrospective of the sprint. The team reviewed I Liked..., I Wish... and What If... items, and moved on to dot voting. Each team was dot-voted on using the process of every participant having 6 votes, where the first vote is 3 dots, second vote is 2 dots, and third vote is 1 dot. The themes are ordered based on the number of votes they received.

I liked...

  • Profile Page Dashboard - 13
  • DOS Deployment Process & Relationship - 12
  • Usability Testing - 10
  • Sprint Handoff Meetings - 5
  • Productivity of team with PTO - 2

I wish...

  • Legacy DIN workstations - 15
  • Structure of usability tests - 10
  • Kristian being stretched - 9
  • People were sick and on PTO - 4
  • Transparency on DOS integration - 3
  • Limited focus on DOS integration - 1

What if...

  • See TalentMAP within DOS environment - 17
  • Engagement/Education for usability testing - 14
  • Style guide - 5
  • See TalentMAP with dynamic data from Web Services - 4
  • User research with Bureau representatives - 4