PLAT-363 — Scheduled runs lost to pauses and to Pulse, and Pulse did not act

Coordination Value
State Pushed to main; local restart and RTS deploy pending
Date 2026-09-28
Owner scheduler-runs
Related subsystem pulse-governance

Problem

Locally, 21 scheduled runs were missed on Sep 25–28. The scheduler was alive and fired every one of them on time (a heartbeat every minute, no gaps). None of them ran:

  • 18 were skipped by a global "Pause all".
    • Sep 26, 12:07–~15:30 IST.
    • Sep 27, 00:20–20:09 IST.
    • Global pauses have been switched on more than 50 times since late July.
    • Resuming cleared paused_by, and the server logs had rotated, so nobody could tell who paused.
  • 3 were refused because a Pulse fix run held the workflow's schedule lock. With the default skip policy, each was dropped:
    • upwork "Daily Toptal Find + Bid", Sep 26 18:00;
    • social-media "Build-in-Public Post", Sep 26 18:00;
    • social-media weekly "Strategy Discovery", Sep 28 08:00. The fix run ended a minute later.

Pulse saw part of this. social-media's Technical Review noted "four days lost to skipped schedules" and concluded nothing needed fixing. The reasons:

  • the evidence framed every non-run as "the scheduler working as designed";
  • changing collision_policy was reserved for Architecture;
  • the reviewer could not tell that the blocker was Pulse itself;
  • a skipped run triggers no review.

What changed

  1. Fix runs share the Pulse lock (9fccab474). pulse-fix-run shares the one-Pulse-per-workflow lock with scheduled Pulse, instead of the workflow's schedule lock, so Pulse no longer blocks the workflow's schedules.
  2. Pulse sees lost runs (get_schedule_runs). Non-started occurrences are grouped as Lost runs, Deferred runs and Deliberately not run (schedule_fire_decision_kind.go). A busy skip is lost work and names the schedule's current policy; a pause is not a defect.
  3. Technical Review may repair lost runs. When a schedule that does real work loses a run to a busy workflow, it may set collision_policy=queue_latest with a fitting max_start_delay_minutes itself, using update_schedule. The Gate makes Technical Review due for such lost runs. Parallel mode, dependencies and reordering stay with Architecture and the user.
  4. The missed badge says why. The missed status uses the scheduler's recorded decision (paused, busy, expired, failed to start) instead of a bare "no run", and the UI shows it in plain words.
  5. Pause history. Every pause and resume is appended to config/scheduler-pause-log.jsonl and logged, with the user, the client label and the User-Agent (browser vs. agent or script). The paused banner shows who paused and from where.
  6. Resume catch-up. A resume returns the runs the pause skipped, filtered to workflows the caller can access. The Schedule Runs overview offers them for a manual catch-up, one run per chosen schedule. Paused runs never run on their own, since a burst of late sends can be wrong.
  7. No double-running a step. Pulse holds off a step the workflow is running at that moment. A process-wide registry of running steps plus full-workflow CurrentStepID backs a StepBusyForPulse check on Pulse workshops only. execute_step then says to wait for that run's result instead of launching a duplicate.
  8. Local config. 16 local schedules that do real work moved from skip to queue_latest, each with a start window that fits its purpose (bids, posts, engagement, drafts, growth, weekly strategy, the Hetzner audit). Pure checks and reminders stay on skip.

Verification

  • Unit tests:
    • the fix-run lock key;
    • lost/deferred/deliberate grouping;
    • pause and resume recording through the handler, with no event on an unchanged save;
    • the Pulse step hold (own run and other steps free; the workflow's run holds);
    • Pulse session detection;
    • the catch-up panel.
  • Full cmd/server/..., step package and scheduler UI suites pass, except the four failures that already fail on main without these changes.

Left

  • Live check after a restart: a busy skip shows under Lost runs; the next Pulse repairs a real-work schedule; pause and resume leave history; the catch-up panel appears after a resume.
  • Find out who paused on Sep 26–27. From now on the pause log answers it.