Phase 0 Execution
Status: Phase 0 approved; global AC mock-oracle gate passed at 99/100; Phase 1A in progress
Requirements baseline: word_association_game_requirements.md v2.6
Execution date: 26 October 2026
Target: sharpninja/wordpairs
The user approved Phase 0 on 26 October 2026. Planning artifacts and the v2.6 baseline are approved. The global test-only AC/TR suite passes 316 tests: 67 primary AC scenarios, 27 supplemental scenarios, four separate TR-19 reaction contract cases, and 112 named AC semantic controls. The exact-commit hostile review at b9e7dee8b93a9639c56fe3348595bfa7e38f4d86 scored 99% accuracy and 100% completeness. Phase 1A adds five skeleton checks; the current combined suite passes 321 tests. Typecheck, lint, and local Next.js build pass. Only the app shell and empty DDD module roots exist; gameplay behavior remains unimplemented.
The requirements contain 22 functional requirements, 31 technical requirements, and 45 active acceptance criteria. The six retired IDs AC-34, AC-35, AC-36, AC-40, AC-48, and AC-49 remain reserved and are verified only through their mapped technical requirements. ac_test_inventory.md maps all 45 active ACs to 67 test oracles. The oracle suite proves assertion sensitivity, not product conformance. The user approved the v2.6 baseline, architecture, interface contracts, and Phase 0 exit. All product choices affecting active AC expected results are resolved.
| Gate | Current evidence | Status | Remaining work |
|---|---|---|---|
| Requirements baseline | Requirements v2.6; 45 active ACs (51 numbered IDs including six retired TR-only IDs); all FR/TR IDs mapped in architecture_design.md
|
Approved by user | Record approval in the Phase 0 receipt; any later behavior change requires a formal requirements and test change. |
| DDD and concurrency direction | Modular monolith, context split, ports/adapters, aggregate transactions, idempotency, outbox and SVG diagrams in architecture_patterns.md and architecture_design.md
|
Approved for implementation | ADR and interface contracts are recorded; evolve only through reviewed requirements/design changes. |
| Test traceability | 45 active ACs map to 67 primary case IDs plus 27 supplemental scenarios; deployment-only IDs are TR-only | Global mock-oracle gate passed exact-commit review at 99/100; 112 semantic controls are included | Run the same reusable assertions against real behavior as each increment is implemented; keep product-conformance evidence distinct. TR and deployment checks never count as AC coverage. |
| Test-harness bootstrap | Test tooling and licenses are documented in ATTRIBUTIONS.md; package-lock.json records installed dependencies |
316 global mock-oracle tests and five Phase 1A tests pass; Next build, typecheck, and Biome lint pass locally | Candidate includes full-schema/source/archive/notices validation, snapshotted driver requests, concrete supplemental AC scenarios, separate TR-19 tests, and module-boundary tests. Gameplay behavior remains unimplemented. |
| Deployment topology | Vercel Hobby + Supabase Free, no GitHub Actions, manual provisioning, SWBOM/release gates documented | Constraints accepted; deployment follows coding | Do not provision or deploy during coding Phases 1–6. Finalize branch/project mapping and verify account capacity at Phase 7 entry. These TR checks do not change AC expectations. |
| Data/security design | DDD ownership, projection boundaries, and candidate persistence/security contracts are documented | Approved design baseline | Implement and validate the schema/security contract through tests before the Phase 1 persistence adapter. |
| Public interfaces and data contracts | Approved commands, queries, typed failures, event audiences, logical relations, RLS and transaction invariants are documented in phase0_interface_and_data_contracts.md
|
Approved design baseline | Translate the approved contracts into executable test names/paths; any technical change requires corresponding test updates. |
| Delivery order | Coding Phases 1–6 and post-coding deployment Phase 7 are in implementation_plan.md
|
Documented | Confirm AC-to-increment allocation, test IDs/owners, and evidence tiers; perform deployment only after coding Phase 6 is complete. |
This is the selected v2.6 stack recorded in the approved architecture ADR. Requirements specify Vercel, Supabase, the Free/Hobby tiers, Git-based Vercel deployment, no GitHub Actions, and GPL-2.0-only; the draft resolves the framework and package manager as Next.js/TypeScript/npm.
| Decision | Proposal | Reason / constraint |
|---|---|---|
| Application | Next.js with TypeScript, deployed as one modular monolith on Vercel | Matches Vercel target; supports server-owned use cases and public/server projections without splitting the domain into services. |
| Package manager | npm with committed package-lock.json
|
TR-27 and SWBOM workflow already specify the exact npm lockfile as inventory input. |
| Test stack | Vitest for domain/use-case tests; MSW and explicit fakes for network/port boundaries; Testing Library for UI behavior; Playwright for browser acceptance | Keeps domain tests independent of production services while permitting component and multi-client acceptance tests. No dependency may be installed until the compatible version/license review is recorded. |
| Persistence | Supabase Postgres with versioned SQL migrations and server-only privileged adapter | Required by TR-22; Postgres transactions are the room serialization boundary. |
| Realtime | Supabase Realtime transports committed, audience-filtered outbox events; clients refetch authorized projections after reconnect | Keeps Postgres authoritative and delivery retry-safe. |
| Environments | Proposed post-coding layout: local Development; isolated Supabase Staging project targeted by a protected staging Vercel Preview branch; Production on main and a separate Supabase project |
The proposal fits the stated free-tier limit and keeps Preview away from Production. It is not a Phase 0 approval gate; confirm account availability and finalize branch/project mapping at Phase 7 entry after coding. |
| Runtime behavior | Domain/app modules use ports for DB, identity, clock, random source, scheduler, quota and event delivery | Enables mock-first tests and prevents framework/services from owning game rules. |
ADR approval is complete: the selected Next.js/TypeScript/npm stack, DDD boundaries, dependency/license baseline, application interfaces, schema/RLS, transaction model, and deadline scheduler contract are approved for test authoring. If test design reveals a semantic gap, revise the relevant requirement/contract and traceability before implementation. Deployment tooling remains post-coding Phase 7 work.
All product decisions affecting active AC expected results are resolved in Requirements v2.6. Phase 0 was closed by the user approval recorded in phase0_approval_receipt.jsonl. The approved requirements, ADR, technical interfaces and schema/security contracts are the baseline for the global test gate. Any later change must update affected expected results and traceability before implementation.
The user approved the Phase 0 baseline and exit on 26 October 2026. The implementation owner records test/mock evidence, implementation increments and review receipts. Any change affecting requirements or expected results returns through requirements and test review before code changes.
Phase 0 approval is complete; the global mock-oracle gate is awaiting independent re-review after correction. The candidate contains 67 primary AC scenarios plus 27 supplemental scenarios, checked against independent expectations and semantic controls. Four additional TR-19 reaction cases remain separate from AC coverage. This is mock assertion sensitivity evidence, not product conformance. The next steps are:
-
Record the exact gate evidence: keep test IDs, commands, results, hashes, and boundary limits in
test_execution_receipt.jsonl. - Hostile review: independently review the exact remote commit and iterate until accuracy and completeness both score at least 98%.
- Phase 1A entry: after that review passes, begin production implementation with BDP v4 Red/Green/Refactor. Run the unchanged oracles against real behavior incrementally and record product conformance separately.
The v2.6 decision register resolves all product outcomes. Phase 0 approval and the global mock-oracle gate are complete; Phase 1A is in progress. Deployment topology and account eligibility remain post-coding Phase 7 work.
The v2.6 requirements decision register records resolved defaults. Future changes that affect expected behavior require a baseline update and corresponding test-specification revision before implementation.
After coding Phases 1–6 and before deployment execution for TR-20–TR-29, finalize the protected staging branch and Vercel Preview mapping, separate Staging/Production Supabase project allocation, account capacity, and Preview/Production variable scopes. This operational mapping does not change active AC contract expectations and is not required for Phase 0 exit. Mockable TR tests can validate branch/environment separation and fail-closed behavior using abstract identifiers; actual account eligibility and deployed settings are TR-only integration/operational evidence, never AC coverage.
Phase 7 deployment-entry checklist:
- Confirm current Vercel Hobby eligibility and Supabase Free account capacity after coding is complete.
- Approve the branch-to-environment mapping and separate Staging/Production project allocation.
- Verify Preview and Production variable scopes before provisioning or deployment.
This is the Phase 1 test-authoring and implementation plan. Its planned cases must be replaced with executable test names/paths, exact expected outcomes, mock behavior, and separate non-mock evidence. All active-AC tests must be executable and mock-validated before the first project implementation code.
| ACs | Planned cases | Mock-backed test responsibilities before implementation |
|---|---|---|
| TR-22–23 |
TR-23-T01–TR-23-T03
|
Mock persistence/use-case contracts and migration fixtures support application coding. Provisioning CLI behavior is specified for Phase 7 and implemented only after coding. Disposable database checks remain TR-only integration evidence. |
| AC-37, AC-39 | AC-37-T01, AC-39-T01 | Mock quota port and fixture manifest/lockfile validate recoverable service limits and attribution records without any deployment dependency. |
| AC-51 | AC-51-T01–AC-51-T04 plus separate TR-30-T01–TR-30-T02 and TR-31-T01–TR-31-T06 checks | Active-AC mock contracts cover domain boundaries/conflict policy/idempotency/outbox intent; distinct later local/disposable DB integration tests verify actual capacity, uniqueness and atomic durability. |
Specify these now, but implement/run them only after coding Phases 1–6 are complete. Validate each mockable TR contract before its Phase 7 tooling is written. None contributes to AC coverage.
| TR | Planned cases | Mock-backed contract |
|---|---|---|
| TR-20, TR-24 |
TR-20-T01, TR-24-T01
|
Fake Vercel metadata/config verifies repository and branch mapping and no GitHub Actions dependency. |
| TR-21 | TR-21-T01 |
Fake configuration evaluator rejects paid tiers/add-ons; account eligibility is checked in Phase 7. |
| TR-23 provisioning |
TR-23-T02–TR-23-T03
|
Fake CLI/temp filesystem verifies safe reruns, secret redaction and environment separation. |
| TR-26–27 |
TR-26-T01, TR-27-T01
|
Fake test runner/build metadata and temporary output verify fail-closed ordering and fixture SWBOM generation. |
| TR-28–29 |
TR-28-T01, TR-29-T01
|
Temporary source archive and fixture SWBOM/license verify required paths/notices without deployment. |
The 67 active-AC IDs have reusable scenario assertions. The exact-commit 99/100 hostile review confirmed archive, driver, AC-38 and evidence fixes. The 316-test mock suite passes. The global gate has passed; during Phase 1A, retain the reusable assertions and begin recording real product conformance separately. During implementation, run those unchanged assertions against the real system and record actual product conformance separately.
- Approve the ADR recording the selected stack and architecture.
- Assign every active AC (45 total) to an increment, test IDs, expected outcome, evidence type, owner and blocked decision; keep retired deployment IDs in TR-only verification records.
- Approve Phase 0 application interfaces, schema, RLS, transaction/idempotency/outbox, quota and deadline contracts. Provisioning, build-gate, and artifact-verification interfaces belong to the post-coding Phase 7 deployment plan.
- Approve
phase0_interface_and_data_contracts.md, including logical schema, idempotency, transaction/locking, outbox, RLS and secret boundaries for the foundation slice. - Review current direct dependency versions/licenses and update
ATTRIBUTIONS.md; test tooling and the Phase 1A Next.js/React runtime dependencies are locked and attributed. Other planned runtime integrations remain for later increments. - Complete all planning/design/decision work; keep this checklist free of executable test or implementation tasks.
Current gate: Phase 0 was approved by the user on 26 October 2026; see phase0_approval_receipt.jsonl. The global AC mock-oracle gate passed exact-commit review at b9e7dee8b93a9639c56fe3348595bfa7e38f4d86 with 99% accuracy and 100% completeness; see repo_review_receipt.jsonl. Phase 1A is authorized. The passing suite validates mock assertions only and does not establish product behavior. Deployment remains Phase 7 after coding Phases 1–6; database/platform checks remain TR evidence separate from AC coverage.
Generated from MCP requirements wiki export.
- Home
- Guest Game and GitHub Admin PWA
- Functional Requirements
- Technical Requirements
- Testing Requirements
- TR per FR Mapping
- Requirements Matrix
- Wordpairs
- Local Development
- Testing and Evidence
- Administration and Access Control
- Requirements Baseline v2.8
- Architecture Decision Record
- Architecture Design
- Architecture Patterns
- Content Moderation
- Deployment and Release Plan
- Acceptance Criteria Gap Analysis
- Acceptance Criteria Test Inventory
- Implementation Plan
- Phase 0 Execution
- Phase 0 Interface and Data Contracts
- Phase 1A Execution
- Phase 1 Execution
- Phase 2 Execution
- Phase 3 Execution
- Phase 4 Execution
- Phase 5 Execution
- Phase 6 Execution
- Optional Phase 6 Human Feedback
- Historical Chromium Crash Diagnosis
- Completed Coding Goal and Review Agreement
- Third Party Attributions
- Software Bill of Materials Contract
- Phone Installation and PWA
- Live Multiplayer Runtime and UI Integration
- UI Test Case Index
- UI Design Coverage
- UI Criterion Gaps
- UI Design Questions
- UI Test Persistence
- TEST-ACCESSIBLEGAMECONTROLS-044 UI Case
- TEST-ACLAUTHORIZATION-132 UI Case
- TEST-ADMINUI-136 UI Case
- TEST-AUTHORITATIVEANSWERHANDLING-045 UI Case
- TEST-BROWSEOPENLOBBIES-022 UI Case
- TEST-CATALOGVERSIONING-133 UI Case
- TEST-CATEGORYART-005 UI Case
- TEST-CATEGORYCHOICE-011 UI Case
- TEST-CATEGORYSUGGESTIONUNLOCK-019 UI Case
- TEST-CONFIGUREDCAPACITY-024 UI Case
- TEST-CONNECTIONRECOVERY-109 UI Case
- TEST-CONTENTVALIDATION-016 UI Case
- TEST-DEEPLINKJOINANDFULLROOM-026 UI Case
- TEST-FINALSTANDINGS-013 UI Case
- TEST-FIRSTCATEGORY-004 UI Case
- TEST-FREETIERQUOTAHANDLING-037 UI Case
- TEST-FULLROOMOBSERVER-027 UI Case
- TEST-GUESTPLAY-021 UI Case
- TEST-HINTPROGRESSION-009 UI Case
- TEST-HINTSCORING-007 UI Case
- TEST-HOLDOUTWARNINGANDREMOVAL-032 UI Case
- TEST-IDLELOBBYREADINESSPROMPT-033 UI Case
- TEST-INROUNDEMOJIREACTION-029 UI Case
- TEST-LANDINGPAGEPUBLICDATA-050 UI Case
- TEST-LIVESCORECARD-010 UI Case
- TEST-MODERATIONANDCATALOGBOUNDARY-047 UI Case
- TEST-NOHINTSOLVE-006 UI Case
- TEST-NOMINATIONELIGIBILITY-017 UI Case
- TEST-NOMINATIONMODERATION-114 UI Case
- TEST-NOMINATIONTHRESHOLDANDMODERATION-018 UI Case
- TEST-OBSERVERPERSPECTIVEANDPERMISSIONS-028 UI Case
- TEST-OIDCTOKENVALIDATION-046 UI Case
- TEST-OPENAIOIDCPROFILE-020 UI Case
- TEST-ORIENTATION-015 UI Case
- TEST-PLAYERLIMIT-002 UI Case
- TEST-PRECOUNTDOWNOBSERVERPROMOTION-030 UI Case
- TEST-PROFILEICON-003 UI Case
- TEST-PUBLICGAMELANDINGPAGE-043 UI Case
- TEST-PWAINSTALL-137 UI Case
- TEST-PWAPRIVACY-138 UI Case
- TEST-QUICKMATCH-023 UI Case
- TEST-READYCOUNTDOWNANDROSTERLOCK-031 UI Case
- TEST-ROOMINVITATIONS-025 UI Case
- TEST-ROOMJOINING-001 UI Case
- TEST-ROOMSYNC-139 UI Case
- TEST-ROUNDSUMMARY-012 UI Case
- TEST-SUGGESTIONREVIEW-115 UI Case
- TEST-TIMETIEBREAK-014 UI Case
- TEST-UNSOLVEDRESULT-008 UI Case
- UI Gap Decisions and Synchronization
- TEST-ACCESSIBILITYDETAILS-144 UI Case
- TEST-CANDIDATEHOLD-141 UI Case
- TEST-LOBBYMATCHING-117 UI Case
- TEST-NAVIGATIONDRAFTS-142 UI Case
- TEST-NOSOLVERFALLBACK-146 UI Case
- TEST-REQUESTFEEDBACK-143 UI Case
- TEST-RESPONSIVEMATRIX-145 UI Case
- TEST-REVIEWCHANGES-140 UI Case
- TEST-ROOMCODES-110 UI Case
- UI Gap Implementation Plan
- UI Gap Implementation and Evidence
- Contest Readiness
- Hostile Validation Evidence
- Category Artwork
- 10-Player Release Completion Plan
- Deadline Report and Token Accounting
- Deadline Report Supporting Evidence
- Deadline Timeline and Review Finding Analysis
- Stopped Wordpairs Release Handoff