Meeting 2022 05 13

Anusha Ranganathan edited this page May 14, 2022 · 9 revisions

Google meet: [https://meet.google.com/uvu-eete-cyf)

Date: 2022-05-13 (Friday)

Time UK: 10:00

Agenda

  1. Review actions from previous meeting

  2. Review kanban

  3. Created a Gantt chart for the project, which I would like to share and discuss - AR

Update

Any updates in the two weeks following this meeting?

Record of the meeting

Present: Neil, Miranda, John, Hrafn, Anusha

The project as it stands, is estimated to take 114 days, which is a little over the mid point estimated (87 to 127 days) and finish in mid November.

As it stands, as the Gantt shows, each of the tasks have been very tightly estimated with not much room for getting it done any quicker in terms of time allocated or the deadline. If we do need to aim to finish at the lower end of the estimate, we would need to start looking at reducing the scope of the edit interface.

Actions