Bracket P-1 is stamped and then assembled. Create route 101 for product 1, with code ROUTE-P1 and priority 0. The route references the product through product; operations reference it through route.
| process.id | route | name | code | operation_number | seqno |
|---|---|---|---|---|---|
| 1001 | 101 | Stamping | STAMP | 10 | 1 |
| 1002 | 101 | Assembly | ASSEMBLE | 20 | 2 |
Numbers 10 and 20 identify operations; sequence values 1 and 2 express precedence. Separating identity and order lets precedence change without renaming the operations.
The base configuration uses two mappings, with durations in seconds:
| id | process | workcenter | productivity | batch_size | processing_time | setup_time |
|---|---|---|---|---|---|---|
| 1 | 1001 | 11 | 4 | 20 | 600 | 0 |
| 2 | 1002 | 12 | 1 | 20 | 120 | 0 |
Both records use priority=0, wip_buffer_size=120, OEE=100, and binding=NULL. Buffer capacity is measured in operation-output units here; check the relevant capability configuration to establish whether it becomes a model restriction.
Trace the order using the actual foreign-key relationships below. Some steps follow references in reverse, from a product to its candidate routes:
order_item.product -> product.id
process_route.product -> product.id
process.route -> process_route.id
process_adaptor.process -> process.id
process_adaptor.workcenter-> workcenter.id
Each referenced identifier needs an actual record.
If stamping can also run on work center 13, add an adaptor with the same process=1001 and the new resource, using that machine's real output and duration. Keep one operation identity for alternative execution resources.
If the manufacturing method changes the operation chain, such as outsourced forming followed by assembly, create a different route and its operations. Distinguish resource choice for an operation from manufacturing-path choice for a product. Confirm route and resource selection policies separately; alternative resources do not multiply product demand.
For two independent inspection steps in another exercise, use distinct operation_number values and equal seqno values. This removes precedence between the checks. A common inspector, instrument, or material condition may still prevent simultaneous execution. Match this semantic relationship to the selected model's support for parallel operations.
Check route ownership, operation numbering, sequence values, references, and parameters for each resource option. Add surface treatment between stamping and assembly: retain numbers 10 and 20, introduce number 15, and use sequence values 1, 2, and 3. Add a resource mapping and material requirements for the new step. A node in a diagram without an adaptor still lacks an executable resource.
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制