Learning E2 Deviations to Planning Signals
“Material is late” describes an event. A planner also needs the affected orders, operations, quantities and periods. Link the event to business objects before selecting a response.
The teaching periods T1, T2 and T3 are in chronological order. Consider this event: material M was expected in T2 and is now confirmed for T3. Operation OP-1 needs it in T2. First inspect its task quantities and possible alternatives, then describe the planning impact.
| Record | Purpose | Information in this example |
|---|---|---|
| Business change | Updated fact | M's arrival time and source |
| PlanBias | Impact relative to the plan | Objects, periods, direction and quantities |
| PlanSignal | Route impact to a recipient | Receiving capability, priority and proposed direction |
| Follow-up measure | Execution or pending confirmation | Release adjustment, proposed objective change, rule or coordination |
The table explains the business meaning of each record. When calling an interface, use its documented types and fields for the selected version.
The planning_system_linkage orchestration recipe performs planning and analysis before the impact_analysis action. Follow the planning analysis in production_analysis.planning, the linkage report in planning_system.linkage_report, and the plan_biases and plan_signals records to trace how the same business change is handled.
PlanBias is produced during execution and is managed separately from the standard input tables in data.db. For long-term storage, save it in the application's result records with the source-data version and run identifier.
A deviation may lead to monitoring, reduced near-term release, a proposed objective change or a purchasing check. Record the proposal, approval and actual handling separately so participants know who acts next.
Review the analysis output, recipient, adoption status and processing result in order. After an objective change is adopted, check the actual configuration and rerun. Until then, retain it as a proposal awaiting confirmation.
One delay may affect several orders. Aggregation supports prioritization, but preserve the path from order to operation, material and period. If availability later recovers, distinguish updated records so the impact is not counted twice.
For the teaching event, identify affected objects, information sources, two possible measures and their approvers. Write an accurate statement when no measure has yet been executed.
For example: material risk has been identified for operation OP-1 in T2, and a proposed release-time change awaits the planning owner's confirmation. After execution, record the actual released tasks, timing and planning results to evaluate the measure.
Planning and Scheduling · Results and Feedback · Component Responsibilities
Worksheets: Worksheet: Operational Rule and Verification · Worksheet: Review and Change Record
Topic E · Previous: From the Master Plan to Work Release and Scheduling · Next: Define the Scope of a Disruption Response
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制