Learning D1 Read a Stamping Plan
A stamping plan must align demand by period with work-center capacity and material availability at each operation. This case uses StampingWorkshop/data.db and the production_planning orchestration recipe to examine those relationships through inputs, configuration and results.
The recorded run took place on 2026-08-31 using DecisioWorks v1.4.0 with commercial Enterprise authorization. The tables retain that run's parameters and measurements.
| Object | Recorded size | Role |
|---|---|---|
| Order details | 1,920 rows | Products, due times and quantities |
| Capacity | 50 rows | Resource availability by time |
| Operation-material relationships (ingredient) | 38 rows | Materials required at each operation |
| Material availability | 500 rows | Available quantities and timing |
| Time units | 25 | Shared input and output coordinate |
| Work centers | 3 | Resource scope |
Trace one order through its product, route, operations and eligible resources, then inspect material conditions. Use row counts to check import completeness, then verify references to confirm that orders connect to the intended resources and materials.
The record enables capacity, demand and material-availability constraints. Capacity is soft and inventory constraints are disabled. Baseline weights are job_bias=-0.001 and waittime=1.0. The request uses 16 threads and a 120-second limit. These describe the recorded run; current use follows the installed release and authorization.
Actions acquire data, parse constraints, generate and select a solution, evaluate it and optionally output results. Persistence uses a separate result file rather than overwriting the standard business database.
| Item | Baseline | Adjusted |
|---|---|---|
| job_bias weight | -0.001 | -0.003 |
| waittime weight | 1.0 | 2.0 |
| API status | ok | ok |
| API elapsed seconds | 14.41 | 14.29 |
| Result rows | 66 | 66 |
| Total demand/output | 680500/680500 | 680500/680500 |
| Final shortage | 0 | 0 |
| Weighted job_bias contribution | -7854.678 | -23564.034 |
The baseline reports available capacity of 1188000, processing load of 371588.48 and planned load including setup and waiting of 377080.42, with reported utilization around 31.74%. These retain the report's measurement basis and are not converted to minutes here.
Both runs selected candidates that passed the recorded validity checks. Here, “best” means the selected candidate from that run, without a claim of proven global optimality. The listed aggregates are unchanged. Match rows by business identifiers to compare quantities and completion times, then check those times against due dates. As two weights changed together, this record describes their combined adjustment.
The reference includes actual input, baseline and comparison screenshots. Those page runs used two threads and 60 seconds and form a separate execution group. Keep each group's configuration and results together rather than inserting screenshot values into the API table.
Reading exercise: check two values using only the figures above.
| Check | Hand calculation | Interpretation |
|---|---|---|
| Overall utilization | 377080.42 ÷ 1188000 × 100 ≈ 31.74% | Matches the reported aggregate; period-level detail is still needed to identify local overload |
| Planned minus processing load | 377080.42 − 371588.48 = 5491.94 | Under the report's definitions, the difference involves setup and waiting; it does not separate their individual values |
These calculations use the published record and retain its original load units. The table supplies no conversion to minutes.
A suitable conclusion is: “Both runs report total output of 680500 and zero final shortage. Those two quantity measures agree. On-time completion, local overload and task-timing changes require detailed records.”
Runtime exercise: obtain the detailed results first. Within one run group, choose a work center and period. Record demand, capacity, materials, output and open questions. If only aggregates are available, mark this step as awaiting detail rather than inferring missing rows.
For a follow-up comparison, change only waittime. Hold data, constraints, other objectives and computing conditions constant, and check the effective objective configuration. Save the new run's status, results and detailed differences before assessing the effect.
Stamping Planning Case · Injection-Molding Scheduling Case · End-to-End Scenario · Scenarios and Pain Points
Worksheets: Worksheet: Baseline and Adjusted Plan Comparison
Topic D · Previous: Turn Shop-Floor Experience into Checkable Rules · Next: Injection Molding: Explain Attributes and Changeovers
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制