Interface 09 Results
中文 · Learning guide · Semantic guide
This is a manually constructed candidate for calculation, not solver output. The base database keeps planning_result empty; candidate rows are stored separately in CSV.
| workcenter | time_unit | process | number |
|---|---|---|---|
| 11 | 1 | 1001 | 80 |
| 12 | 1 | 1002 | 80 |
| 11 | 2 | 1001 | 40 |
| 12 | 2 | 1002 | 40 |
Resolve each operation to its route and product. Assembly is the final operation, so deliveries correspond to 80 and 40. The four rows total 240 operation-output units, not 240 finished deliveries.
| Period and resource | Output | Units/cycle | Cycles | Seconds/cycle | Processing minutes |
|---|---|---|---|---|---|
| Day-one stamping | 80 | 4 | 20 | 600 | 200 |
| Day-one assembly | 80 | 1 | 80 | 120 | 160 |
| Day-two stamping | 40 | 4 | 10 | 600 | 100 |
| Day-two assembly | 40 | 1 | 40 | 120 | 80 |
Consumption is 80 blanks and 160 fasteners on day one, then another 40 and 80. Check cumulative consumption against cumulative supply. With opening finished stock 20 and issues 80 then 40, ending finished inventory is 20 on both days.
These calculations assume no initial setup, changeovers, scrap, or additional OEE adjustment. Add applicable time from the adopted records and rules when checking real results. Read value_1/2/3 using the scenario's definition; cycle number and sequence position are scenario-specific interpretations.
Extending day-one stamping maintenance from two to three hours reduces available time from 360 to 300 minutes. The 200-minute stamping load still fits in aggregate. If maintenance occurs at the start of the shift and all 80 units needed on day one must finish stamping before any assembly starts, with no overlap between operations, continuous execution needs 180+200+160=540 minutes, exceeding eight hours. The two-hour-maintenance version needs 480 minutes.
Transferring all 80 units together is an additional assumption, not a consequence of batch_size=20. Confirm the processing batch and transfer batch separately. If each completed batch of 20 can move to assembly, with no transport or setup losses and both machines able to operate concurrently, the four batches finish at minutes 270, 320, 370, and 420. The 420-minute and 540-minute calculations use different transfer rules; neither is a solver run.
A resource-load check therefore does not establish that the entire operation chain fits within the shift. Transfer batches, overlapping production, or changed windows need explicit scenario rules and model support. Result review needs both aggregate quantities and operation-level detail.
- Separate executed, committed, and adjustable work; retain the original plan.
- Update remaining demand using actual deliveries, rather than planned completion.
- Update available materials using actual consumption, receipts, and blocked quantities.
- Carry forward necessary resource commitments without counting maintenance twice.
- When the planning origin moves, rebuild every time reference, not just result numbering.
- Record configuration differences before starting the next capability run.
Day one promised 80 but delivered only 60. If the cumulative commitment is unchanged, day-two remaining delivery is 60: the original 40 plus backlog 20. This does not automatically mean 60 new units must be produced. Review finished stock, work in process, completed but undelivered quantities, and inventory policy. Treating delivery backlog as new production can duplicate output.
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制