Planning and Scheduling Overview
English | 中文
Applies to DecisioWorks v1.4.0
Master planning and detailed scheduling solve different problems. Planning decides what to produce, how much, and when work may be released. Scheduling assigns released, executable work to resources, sequence, and time. Combining everything in one model often makes the plan too detailed and pushes material or management conflicts into the scheduler.
Master planning brings together demand, capacity, material availability, inventory, delivery commitments, and execution feedback. It does not seek second-by-second precision for every operation. It identifies underproduction, overload, kitting risk, inventory pressure, and commitment risk, then decides what may be released and what needs to wait, be adjusted, or be escalated.
DecisioWorks can represent these changes as PlanBias records. A bias preserves source, affected object, direction, and impact before anyone overwrites the active plan.
Scheduling receives released, confirmed work packages that meet the material conditions required for that release. Within a local production unit it handles resource assignment, sequence, waiting, idle time, and changeovers. Upstream planning confirms material readiness; if a scheduling capability also supports time-phased material constraints, enable them explicitly. Precise scheduling depends on stable input, while long-term forecasting, procurement commitments, and cross-department coordination belong to the corresponding planning processes.
demand, capacity, material, and execution changes
-> PlanBias -> PlanSignal
-> objective/rule candidates or release policy
-> scheduling work package
-> workload, waiting, changeover, and execution feedback
-> next planning cycle
A PlanSignal routes a planning impact to a receiving action, which may propose an objective change, a local rule, or a release candidate, or retain an alert. Configuration and approval determine whether the proposal enters a later run. Creating a signal does not itself change the plan.
Disturbance response should not default to global rescheduling. Near-term prepared work may be frozen, still-valid work continued, and only the affected scope reconstructed. Compare solution gain with change scope, shop-floor switching cost, and commitment impact.
These steps use an installed DecisioWorks Web Cockpit with the required license configuration. This website provides documentation and historical case records; its sandbox illustrates the workflow.
- Inspect demand, capacity, kitting, and time units.
- Run a baseline and review satisfaction, workload, waiting, and shortage.
- Change an objective or solver parameter supported by the page and rerun. For rule or resource changes, update the corresponding data or recipe and reload it first.
- Compare what remained stable, what changed, and why.
- Record cross-cycle issues as inputs to the next planning round.
- Treating MPS as a coarse Gantt chart.
- Leaving material shortages and procurement conflicts entirely to the scheduler.
- Overwriting the original plan after an exception without explaining the change.
- Comparing only objective scores rather than plan stability and execution costs.
Continue with the Stamping Planning Case and Results, Evidence, and Feedback.
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制