A shop contains stamping machines A and B and an assembly station. Both machines depend on one fixture. Express organizational ownership, machine availability, and fixture capacity separately.
| workcenter.id | name | code | parent_id | type | station_count | parallelism | equipping_time |
|---|---|---|---|---|---|---|---|
| 10 | Shop | SHOP | NULL | 1 | 1 | 1 | 0 |
| 11 | Stamping A | PRESS-A | 10 | 0 | 1 | 1 | 0 |
| 12 | Assembly | ASSEMBLY | 10 | 0 | 1 | 1 | 0 |
| 13 | Stamping B | PRESS-B | 10 | 0 | 1 | 1 | 0 |
| 20 | Shared fixture | FIXTURE | 10 | 0 | 1 | 1 | 0 |
These are extension records for this lesson. The end-to-end base database uses the shop, stamping A, and assembly; the other records extend it. The shop is an organizational node. Its scalar defaults do not create another set of executable capacity.
Hierarchy also supports common-attribute inheritance, rules at different levels, and aggregate analysis. A shop may define a shared calendar convention while each machine adds its own maintenance. Configuration applies shop-level rules to the participating resources, and analysis aggregates machine-level loads. The teaching table establishes parent relationships; automatic inheritance and rule expansion require the relevant capability. A shop's aggregate load does not create another machine's capacity.
shared_resource stores the relationships:
| id | binding | to |
|---|---|---|
| 1 | 20 | 11 |
| 2 | 20 | 13 |
capacity stores the fixture's own availability:
| id | time_unit | workcenter | used |
|---|---|---|---|
| 5 | 1 | 20 | 0 |
| 6 | 2 | 20 | 0.5 |
On day two the fixture has half a shift available. Two links do not create two separate half-shifts. shared_resource has no time_unit or used column; availability is reached through the resource work center.
If A needs the fixture for three hours on day two and B needs it for two, their five-hour total exceeds four available hours by one. Eight available machine-hours on each machine do not make the combined plan feasible. Even after the aggregate fits, actual uses must not overlap.
This lesson defines the data and checks the conflict manually. For an actual solve to exclude the conflict, confirm that the model configuration adopts the shared relationship and inspect its result.
-
parent_id: organizational ownership, or “belongs to.” -
process_adaptor: executable resource compatibility, or “can run on.” -
shared_resource: resource dependence, or “also needs.”
station_count describes stations; parallelism describes parallel units. Solver threads do not represent production resources, and station and parallel counts must not multiply time twice without a valid model interpretation.
For a second independent fixture, create its resource and calendar, then define which machines can use it. If both fixtures still require the same operator, represent that shared person as well; capacity does not automatically double. Every dependency should resolve to a resource and its time-phased availability.
Product Home | DecisioWorks v1.4.0 | English / 中文
- What Is DecisioWorks / DecisioWorks 是什么
- Scenarios and Pain Points / 适用场景与痛点
- Quick Start / 快速开始
- Documentation Map / 文档地图
- Research and Commercial Editions / 研究版与商业版
- Whitepapers / 白皮书
-
Learning Center / 学习中心: 8 topics / 8 个专题
- Design Principles and Differentiation / 设计原则与差异化
- Architecture Overview / 总体架构
- Component Responsibilities / 组件职责
- Standard Actions and Orchestration / 标准动作与能力编排
- Objectives and Rule Control / 目标与规则控制
- Controlled Solving and Engine Adapters / 受控求解与模型适配
- Results, Evidence, and Feedback / 结果、证据与反馈
- Developer Guide Index / 开发手册索引
- Data Objects and Fields / 数据对象与字段
- Actions, Recipes, and Execution / 动作、配方与执行
- Runtime Status, Errors, and Limits / 运行状态、错误与限制