Release Process

Source of truth: RELEASE.md, kept in the repository and copied here.

The order below is not advisory. Each rule exists because violating it has already cost a release cycle or nearly shipped a defect.

Order of operations

  1. Freeze the code. No fixes land after this point without restarting at step 2.

  2. Adversarial review of the complete diff — independent reviewers per dimension (delivery paths, protocol handling, UI truthfulness vs. code, docs claims vs. code), each finding verified by skeptics instructed to refute it. This happens before version stamping, not before tagging: the 6.2.15 review ran after the installer was built and both blockers it found (a BDAT truncation defect and a fix that converted transient file locks into permanent mail loss) forced rebuilds and a re-run of the full suite. Same review, an hour cheaper, if run first.

  3. Fix what survives review; each defect fix gets a negative-control test. Build the pre-fix binary and confirm the new test fails against it. A test that passes on both builds proves nothing — one of the 6.2.15 abort tests did exactly that until it was strengthened with session-count assertions.

  4. Pre-flight the bench: build\preflight-tests.ps1 (add -Clean to remove a stale ERROR log). Never skip this after an aborted run — an aborted run leaves a deliberate scanner error in the ERROR log and the next run fails 100% of tests in fixture setup, and it also leaves the TLS fixtures' twelve extra ports behind, which the pre-flight checks.

  5. Check the roadmap against itself: build\check-roadmap.ps1. It reconciles every tick box in Roadmap.md against the per-section counts and the contents table, because three hand-edited restatements of the same 750 numbers drift — nine sections had drifted when the check was written.

  6. Check the database scripts build a database: build\check-db-scripts.ps1. It creates a throwaway SQL CE database from CreateTablesMSSQL.sql using the same splitting rules the server uses, because nothing else here does - the regression bench's database is upgraded out of band, so no local test takes the CREATE path a fresh install takes. 6.2.22-pre4 shipped an installer whose database could not be created at all, and the only symptom was a service that started and did not listen.

    Run build\check-schema-versions.ps1 beside it (pwsh 7, not Windows PowerShell 5.1, where it dies in Measure-Object -Property To). It walks the registered upgrade chain and proves it is contiguous and forward-only, and that every step is present for every backend. That matters most on exactly the kind of release this checklist keeps being used for - one that moves the schema several steps past the last stable - and it was missing from this step until 6.2.23.

  7. Version stamp: Version.h (version, numeric, build), section_setup_64.iss, all seven .csproj <Version> values. Verify nothing else still carries the old version: git grep <old-version>. In section_setup_64.iss the VersionInfoVersion fourth component stays 0: the build number lives in Version.h and the tag, and a build-only re-cut (the common case) must not have to touch the installer script or the seven .csproj files, whose versions are also <version>.0.

  8. Build everything at the stamped version: build.ps1 -Configuration Release, build-tools.ps1 -Configuration Release, ControlPanel dotnet publish to its publish\ folder (build-tools does not cover it), build-tests.ps1. Confirm the stamped FileVersion on hMailServer.exe and publish\hMailCP.dll.

    If hMailServer.idl changed in this range, regenerate the checked-in COM wrapper after the server build and before the tools build: build\regenerate-interop.ps1. It runs TlbImp AND rewrites the wrapper's SHA-256 and size in hmailserver\docs\third-party-binaries.json - the binary-provenance workflow fails when those disagree, and regenerating by hand without the manifest did exactly that twice in one day. A stale wrapper still compiles, which is why this is easy to skip: the tools use a small stable subset of the API, so nothing fails, and the members added this release are simply invisible to them. Regenerate AFTER any interface-ordering fix, never before, or the old vtable layout is baked into the shipped wrapper permanently.

    Then prove the build is still reproducible: build Release a second time from clean (build\build.ps1 -Configuration Release -Clean) and compare the SHA-256 of hMailServer.exe with the first. They must be identical - /Brepro, /d1trimfile, /pdbaltpath and OPENSSL_NO_FILENAMES in the project make the executable a pure function of the source and the toolchain, and a mismatch means something has started embedding a timestamp or a path again. Put the hash in the release notes' verification section so anyone with the same toolchain (v145, Windows SDK 10.0.26100) and library layout can check the published binary came from the published source. Both builds restart the service, so do this before step 9, never after.

8b. Full regression suite on the assertion build, first. Build with build\build.ps1 -Configuration Release -Asserts - the same source, with every HM_ASSERT kept and a violated one reported as HM6364 in the ERROR log instead of compiled out - and run the whole suite on it. The ERROR log is checked before each test, so a violation fails the test that provoked it and names the expression, file and line. Expect none. Then rebuild plain Release (step 8) before step 9: the assertion build is the dynamic-analysis build and is never the binary that ships or is hashed.

8c. Timed fuzz run on the release source — required for every minor release. On the build from step 8: fuzz\run-fuzz.ps1 -Target mime_message_fuzzer -Minutes 30, and the same for each other harness listed in hmailserver/docs/Fuzzing.md. A crash, a hang or a violated assertion is a release blocker: minimise it, fix it, add the input to fuzz\regression, restart at step 1. Record the harnesses, the duration and the execution count in the release notes' verification line. A patch release may cite the previous minor's run when none of the fuzzed parsers changed; anything else runs again.

  1. Full regression suite on the stamped binary — every test, nothing skipped. If anything changes after this run, the run is void: rebuild and re-run. Never abort a run; if one must be stopped, expect step 4 to fail and clean up before trusting any result.

  2. README release notes — every claim checked against the diff. "Fixed" means reproduced-then-fixed or negative-control-tested; anything else is described as hardening or diagnostics. Unfixed known issues are named as unfixed.

  3. Installer: ISCC on hMailServer64.iss. Never run the installer on the dev machine — validation is the CI smoke-test workflow (installer-smoke.yml), which installs it on a throwaway runner.

  4. Commit (as chrisholloway5, no co-author trailers - history has been rewritten once to remove them, and will be again). master is protected: changes arrive by pull request, force-pushes and deletions are refused, and the maintainer's bypass exists for emergencies, not for the release flow. So push the working branch, open the PR and merge it with a rebase so the history stays linear and the commits keep their own messages:

    git push origin server-fixes-wave
    gh pr create --base master --head server-fixes-wave --fill
    gh pr merge --rebase            # self-merge is allowed; no reviewer is required
    git pull --ff-only origin master
    

    Then tag vX.Y.Z on master as an annotated, signed tag and push it (tags matching v* are protected too: no deletion, no rewrite - a tag is spent once):

    git tag -s vX.Y.Z -m "hMailServer X.Y.Z"
    git -c gpg.ssh.allowedSignersFile=.github/allowed_signers verify-tag vX.Y.Z
    git push origin vX.Y.Z
    

    Signing is SSH-based (git config gpg.format ssh and user.signingkey pointing at the public key, set once in the repository's config), and the key must be listed in .github/allowed_signers - the signing workflow below refuses to sign anything for a tag that is lightweight or that does not verify against that file, so an unsigned tag stops the release before it has any assets. Every tag up to v6.2.23-alpha1 was lightweight; there was nothing to verify and nothing stopped a v* ref being moved.

    Then publish as a draft first - this repository has immutable releases enabled, so a published release refuses every further asset upload and would be stuck with whatever it was created with:

    gh release create vX.Y.Z <installer> --draft --prerelease \
       --title "..." --notes-file <notes>
    gh workflow run "SBOM" -f release_tag=vX.Y.Z          # SPDX + CycloneDX
    gh workflow run "Sign release artefacts" -f tag=vX.Y.Z  # LAST: signs what is attached
    gh release view vX.Y.Z --json assets                   # expect installer + 2 SBOMs + bundle
    gh release edit vX.Y.Z --draft=false                   # publish, now complete
    

    The installer's name is not cosmetic. It must be exactly hMailServer-<tag without the leading v>-x64.exe, with its .cosign.bundle beside it. The update checker in every running server builds that name from the tag and matches an asset on exact equality; a release named anything else reports "a new version is available" and then "there is nothing to download" to every installation in the field. This was broken once already, at v6.2.22-pre3, whose installer was hMailServer-6.2.22-x64.exe. The signing workflow now refuses a release that does not carry the expected name, so the check happens before publication rather than after somebody notices.

    Order matters twice over: the SBOMs have to be on before signing, because cosign signs whatever is attached when it runs; and everything has to be on before publication, because nothing can be added afterwards. 6.2.22-pre4 was published straight away and ended up with an installer and no SBOM at all.

    The two gh workflow run lines are required, not belt-and-braces. Saving a draft does not start a workflow: GitHub does not deliver release events for draft releases, which was measured here rather than assumed - creating the pre5 draft produced no run at all. The release: created trigger on both workflows therefore only covers a release published without a draft, which is the path that can no longer attach anything. Dispatching them by hand is the path that works.

    And a tag is spent once: a tag that has backed an immutable release cannot back another, even after that release is deleted. There is no re-cutting a broken release under the same version - it needs the next number.

  5. Close the loop: answer every issue the release resolves (and close them), update the ones it does not resolve saying so plainly.

Standing rules

  • Prefer two small releases over one large one. 6.2.15 carried IMAP semantics, delivery changes, a connection-layer rewrite and a UI expansion in one tag; its worst defect lived in the interaction between two of those themes.
  • A fix to a shared layer needs a dependents audit. Before changing behaviour in something like TCPConnection, enumerate who depends on the old behaviour (the BDAT reads depended on "any error ends the session").
  • The public record never overstates. If it is not reproduced and negative-control-tested, it is not "fixed" — say "hardened", "instrumented" or "still open". Credibility with reporters is the project's scarcest resource.