Plan a task in hours
Goal: plan tasks in working hours alongside tasks in days.
A crane is hired by the hour, a pour takes six hours and a night crew works outside the day shift. Duration in hours is always available. The calendar determines when those hours fit.
- Select the task and open Properties › Time › Duration.
- Type, for example,
12hor1h 30mand press Enter.uis also accepted for hours. - Press Calculate (F5).
- Choose View › Time Scale › Hour to see hours in the timeline header.
At the Day scale, a bar moves in whole days. At hour zoom it moves by the hour; with Quarter-hour zoom and sufficient zoom, by quarter-hours.
- Open App settings › Appearance.
- Under Duration display, enable Allow mixed day/hour planning.
This shows the Duration unit selector. Without the selector, you can still type a duration with a unit.
- Open Project settings.
- Choose Hour measure under Default measure for new tasks and click Apply.
New tasks get the chosen measure. The same choice is available when creating a project, alongside the shift preset. In the P6 and MSP profiles the choice is fixed on Hour measure. The text below the list then says so.
Derived duration. You cannot type the duration of a summary, hammock or zero-duration milestone.
Fixed work. A task with the task type Fixed work always uses the hour measure. If you set a task of 3 d to Fixed work, it becomes 24 h: 3 × the working time per day. The finish can therefore move, as with a duration change. In the table you cannot set such a task back to days.
Duration display in OPS. This setting is disabled: each task shows its own unit. In the P6 and MSP profiles the choice remains available.
- Days and hours: the two units.
- Set working times: the calendar.
- App settings: display and quarter-hour zoom.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Plan a task in hours
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an MCP client
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the MCP link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- MCP tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project