Splitting a task
Goal: interrupt a task, so that the work stops and carries on later, without turning it into two tasks.
Laying the reinforcement takes eight work days, but after four days the crane has to go to another job and the work carries on two days later. Making two separate tasks means keeping your relations and assignments twice. With a break it stays one task, with one bar that has a gap. The app also calls the break a pause.
The work stays the same length, but the task now lasts longer on the calendar. An example: a task of 8 work days that starts on Tuesday 29 September 2026 finishes on Thursday 8 October. If you put a break of 2 work days after 4 work days, it finishes on Monday 12 October. The duration stays 8 work days, only the finish moves two work days.
- Choose Home › Tasks › Split task (or Planning › Relations › Split task). Above the schedule the notice Click a bar on the day the break starts and drag right for its length. Press Esc to stop. appears. The button is also on the Table tab (Table › Tasks › Split task), but it is disabled there.
- Move the mouse over the bar. A dashed line and a label with the date show where the break would start. Press on the bar, on the day the break starts.
- Drag to the right. The label shows the length, for example 2 workdays break: the distance in work days to the day under your mouse. Release.
If you just click, without dragging, the pause becomes one work day. Dragging back to the left makes the pause shorter again, down to a minimum of one work day. For a task in hours, it works in hours.
The mode stays on, so you can split more tasks. You stop with Esc or with the Stop button in the notice. If you press Esc while dragging, the app reverses the pause and the mode stops. Each gesture is one step for Undo.
After a split the schedule is out of date. Press Calculate (F5) for the final dates.
This works without split mode, directly on a bar that has a break.
- Drag the piece after the pause to the right or left. The pause becomes longer or shorter, with the label 3 workdays break. If you drag it back until the pause is 0, the label shows Merge and the two pieces are one again.
- Drag the right edge of the piece before the pause. That piece becomes longer or shorter, with the label Piece: 5 workdays. The duration of the task changes with it.
- If you drag the first piece, you move the whole task, as with any bar.
Select the task. In the Properties panel the Breaks block is under Dependencies and above Assignments. Scroll to it if needed.
- Add break puts a pause of one work day halfway through the longest piece.
- Each pause has two boxes: after (how many work days of work come before the pause) and pause (the length of the pause). Next to them are the dates of the piece after the pause. For an hour task they show hours.
- If you set pause to 0, the break disappears. The small bin (Remove break) does the same.
Be careful with after: that box lengthens or shortens the piece of work before the pause, and with it the duration of the whole task. With pause only the finish changes.
Right-click the break in the Gantt, or the piece after it, and choose Remove break. Remove all breaks is in the right-click menu of every bar that has a break. Or use the Breaks block in the Properties panel, as above.
A connected AI assistant sets breaks with the tool planner_set_task_splits, in the same form as the panel: after how many work days (or work hours) of work, and how many work days (or work hours) of pause. It always gives the whole list; an empty list removes all breaks. It reads them back with planner_get_task. The same rules apply as below: a task you cannot split, the assistant cannot split either. Unlike a split you make yourself, the app recalculates the schedule afterwards by itself. How to connect an assistant is in Connecting an AI assistant (MCP).
Not every task can be split. You cannot split a milestone, a summary task, a task with Hammock (derived duration) on (see Creating a hammock), a task with duration type Elapsed time, a task that is Manually scheduled, or a task shorter than two work days. In split mode the mouse shows a not-allowed cursor and nothing happens. For such a task the Breaks block is also missing in Properties.
On the Table tab the button does not work. Split task is disabled there, with the tooltip Only available when the Gantt chart is visible. The gesture needs a bar. Split mode and link mode switch each other off.
A click with no effect. A break cannot start on the first day of the task and not inside an existing pause. Each piece of work must also stay at least one work day long. If you click such a place, nothing happens, without a message.
A task with progress. If the task has progress, a break can only start after the work that is already done. At 50% of 8 work days that is the fifth work day at the earliest. A click in the done part does nothing, and a task that is 100% complete can no longer be split. In the panel Add break is then disabled: that also applies if the middle of the longest piece falls in done work, for example at 75% of 8 work days.
Leveling also creates breaks. They show in the Breaks block with the label leveling. Resources › Leveling › Clear leveling removes them again. If you edit the breaks of such a task yourself, all its leveling pauses become yours and Clear leveling no longer removes them.
Breaks do not travel to MS Project or Primavera. If you export to MS Project XML or Primavera P6 XML, that program knows a break only as a work distribution of an assignment. Without such a distribution the task arrives without a break, and the app reports how many tasks that is: 1 task with breaks was exported without its breaks: MS Project/P6 only know breaks as a work distribution. In the app's IFC file they are kept.
A file with breaks the app cannot edit. Breaks from a source file that do not fit the app's form show the message These breaks come from the source file in a form that cannot be edited here in the panel, with only Remove all breaks.
- Critical path and float: how the schedule counts in work days and why the finish moves.
- Adding relations: another mode in the Gantt, which you use with a bar drag.
- Task dialog and properties panel: the Breaks section in the properties panel.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project