Adjusting the structure

Nozzit edited this page Oct 21, 2026 · 1 revision

Adjusting the structure

Goal: arrange tasks into phases and subtasks, change their order and keep the WBS numbers correct.

When you need this

Your schedule is a tree: phases (summary tasks) with subtasks below them, such as Foundation with Groundwork, Reinforcement and Pouring. You adjust that tree when you want to hang tasks under a phase, take a task out of one, or the order is wrong. The WBS code (1, 1.1, 1.2, 2, …) is a task's number in that tree.

Steps

Indenting a task

  1. Select the task. Selecting several tasks is fine.
  2. Choose Planning › Structure › Indent. You can also use Alt+→ (or Alt+Shift+→), or Indent in the right-click menu.

The task becomes the last subtask of the previous task at the same level. That task becomes a summary task as a result. If you select a contiguous block, the block indents as a whole. If the task has no previous task at the same level, nothing happens, and there is no message.

Outdenting a task

Choose Planning › Structure › Outdent, press Alt+← (or Alt+Shift+←) or choose Outdent in the right-click menu.

The task becomes a sibling directly after the phase it hung under. Its own subtasks go with it. The tasks that came after it in that phase stay in it. A task at the top level does not outdent any further.

Moving a task

You have three ways.

  • With the keyboard. Alt+↑ and Alt+↓ swap the task with its neighbour at the same level. A summary task takes its subtasks along. At the top or bottom of the level nothing happens. With several tasks selected, only the task you clicked first moves.
  • Dragging in the task list. Press on a row and drag vertically. The top quarter of a row means before, the bottom quarter after. The middle of a summary task hangs the task under it as its last subtask. The middle of an ordinary task counts as the nearest edge. If you drag a row that is part of a multiple selection, the whole selection moves.
  • Dragging in the Gantt. Drag the bar vertically to another row. That works the same as dragging in the list and changes no dates. If you drag horizontally, you shift the dates instead.

Each move is one step for Undo (Ctrl+Z).

Keeping the WBS numbers up to date

Look at the WBS auto button in Planning › Structure.

  • On (the default in a new project). Also on after you open a file without this setting, if all WBS codes already match the numbering of the tree (1, 1.1, 1.2 …). The codes do not change. An empty file without this setting also gets on, just like a new project. The app renumbers the whole tree with every addition, deletion and move. The WBS code is then read-only: you cannot type it in the list or in the Properties panel. Renumber WBS is disabled.
  • Off. The default in a file with its own codes, such as A1000, or with one code that differs from the tree. The codes stay as they are, also after moving and indenting. You type them yourself, in the WBS column or in the WBS Code field in Properties, or you have them renumbered once with Renumber WBS. That also overwrites codes you typed yourself.

If you turn WBS auto on, the app numbers the tree at once. Both WBS auto and Renumber WBS can be reversed with Undo.

Pitfalls and what the app does

Filtering, grouping or sorting is on. The order you see is then not the order of the schedule, so the app locks the structure. Indent and Outdent are disabled, with the tooltip Not available while filtering/grouping/sorting. Alt+→ and dragging show the same text in a red strip, with the Clear button. That removes filter, grouping and sorting in one go, and Ctrl+Z does not bring them back. The strip stays until you click the cross, use Ctrl+Z or Ctrl+Y, or go to another document. Indent and Outdent are then missing from the right-click menu.

Alt+↑ and Alt+↓ do work in such a view, without a message. With only a filter you see the new order at once. With a sorting the order in the schedule does change, but you only see it after Clear.

WBS auto is off. This happens with a file that has its own codes, or with a file that saves the setting as off. A new task gets the code that fits its place in the tree, even if another task already has that code. That way duplicate numbers can appear. After indenting, too, the codes no longer match the tree. Renumber WBS fixes both.

A milestone gets subtasks. A milestone is a moment and has no subtasks. The app removes the milestone flag and tells you.

A task with resource assignments gets subtasks. A summary task carries no assignments itself. So the app first asks what to do with them, in the window Task becomes a summary task. This happens when you indent, use Add subtask or Add milestone on a task, insert a template, and in Edit task when you choose a new Parent task: for an existing task and for a new task. In Edit task the question comes before saving. If you choose Cancel there, Edit task stays open with your changes. You choose:

  • Cancel: nothing changes, the structure also stays as it was.
  • Remove assignment: the task gets its subtasks and its assignments are removed. The actual work of those assignments is removed too.
  • Move to '…': the assignments go to the first new subtask that can carry them, with their actual work. A milestone or a summary task carries no assignments.

If that subtask already has the same resource, or there is no suitable subtask, Move is disabled. An orange block in the window tells you why.

If an assignment already has actual work, the orange block tells you how many hours per resource, for example The assignment of Metselaar already has 8 hours of actual work. Removing it discards that work. Cancel is then the default button: Enter changes nothing. If you still want to remove the assignment, click Remove assignment yourself.

While the window is open, no shortcut outside the window works, including Undo, Paste, Delete, F5 and Ctrl+S. If one action creates more summary tasks at once, the window shows the resources per task, and your choice applies to all of them. One Undo (Ctrl+Z) reverts the whole action.

A relation would create a cycle. The relations of a summary task also apply to its subtasks. If a move would create a cycle because of that, the app refuses it, with the message This move would create a cycle in the schedule (…). Nothing changes.

A relation between a task and its own phase. If you put a task under a phase it already has a relation with, that relation stays, but no longer counts in the calculation. The app tells you. You can read more about relations on summary tasks in Relations and lag.

The schedule is out of date. A move to another phase can change dates. Press Calculate (F5). Just swapping the order within the same phase does not.

See also

Open Planner Studio

Tutorials

Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.

How-to guides

Explanation

Reference

Project

Clone this wiki locally