Updating progress

Nozzit edited this page Oct 21, 2026 · 1 revision

Updating progress

Goal: put the actual state of the work into the schedule and recalculate the schedule: which tasks are finished, which are running and how much is still to do.

When you need this

You update progress at fixed moments, for example every Friday when the site manager reports the state. That way the schedule sees what has actually happened and calculates the remaining work from the status date. Why the app does it this way is explained in Progress, status date and baseline.

Steps

1. Set the status date

The status date is the day on which you take stock. Set it before you enter progress.

  1. Go to Planning › Baselines & progress › Status date.
  2. Type the date in the three boxes for day, month and year (in the order of your date notation), for example 28, 06 and 2027, and press Enter. The app jumps to the next box by itself.
  3. Does the project calendar have working-time blocks (the Working times block in the Calendars window)? Then the app calculates in hours and a time field shows on the right, for example 17:00. Type another time, for example 12:00, and press Enter. If you empty the time field, only the date remains. If you change only the date, the time stays. The time follows your time notation (24 or 12 hours). Without working-time blocks the app calculates in whole days: then there is no time field and the status date line sits at the start of the day.
  4. With the small cross next to the field you empty the status date again.

If you take stock on Friday after working hours, set the status date to the next working day, Monday. The app plans the remaining work from the start of the status date.

If you enter progress while there is no status date yet, the app sets it to today and reports: Status date set to today (…). So rather do this yourself first.

2. Enter the progress

Choose the way that suits your situation. They give the same result.

One task in the Properties panel. Useful when you update a single task.

  1. Click the task. If you do not see the Properties panel, turn it on with View › Panels › Properties.
  2. Drag the slider Progress (%) to the percentage that is done.
  3. If needed, fill in Actual start and Actual finish, in the same way as the status date. The app calculates the field Remaining itself; you cannot change it here.

A milestone has one field, Actual date.

Choosing a percentage in the menu. Useful for a quick state.

  1. Right-click the task bar in the Gantt.
  2. Choose Progress and then 0%, 25%, 50%, 75% or 100%.

Several tasks in the table. Useful when you update a whole list.

  1. Click the + at the right of the task list header (Add column) and open the category Progress. Add the columns Actual start, Actual finish, Remaining and Status. The column Progress is already on the Table tab.
  2. Double-click a cell, type the value and press Enter. You type a percentage as 50 or 50%, a date as 25-06-2027, a remaining duration as 1.
  3. For Status, after a double-click press Enter and choose Not started, In progress or Completed.

If you type a remaining duration, the app works back to the percentage: for a task of 2 work days a remainder of 1 gives a percentage of 50. A remainder of 0 completes the task. The Actual duration column (also in the category Progress) works the other way round: type how much work is already done and the app calculates the percentage. For a task of 4 work days, an actual duration of 1 gives 25%. If you choose Not started at Status, the percentage goes to 0 and the actual dates disappear.

Everything of one task in the Edit task window. Right-click the task and choose Edit.... The progress fields are there too. They only apply once you click Save.

Many tasks at once from a spreadsheet. See Importing progress from a spreadsheet.

3. Recalculate the schedule

Every change to progress or the status date makes the schedule out of date: the status bar reports Out of date — recalculate (F5). Press Calculate (F5), for example through Planning › Schedule › Calculate. If Calculate automatically is on (under Settings › Project › App settings, tab Planning), the app does this itself.

Checking the result

  • On the status date the Gantt shows a dashed line with the date in the header. At running tasks the line bulges out to the percentage in the bar. You turn these on or off with View › Baselines & progress › Progress line and Status date line.
  • The completed part of a bar turns grey; the rest keeps its colour. A task that is fully done is fully grey, with a tick before the name and without a float band. The bar of a phase also turns grey up to its derived percentage, so you see per phase how far the work is. If you show the predecessors or successors of a task, those bars keep their highlight colour, also when they are done.
  • Completed tasks are never red: with a status date a completed task is not critical.
  • Phases show a derived percentage and the finish of the schedule may have moved.
  • If you saved a baseline, the original schedule is under each bar and the report type Variance shows the variance.

Pitfalls and what the app does

A date after the status date. The app refuses an actual start or an actual finish after the status date. In the panel it says under the fields Actuals cannot be after the status date; in the table the cell reports The actual date lies after the status date. First set the status date later, or correct the date.

A task that would only start after the status date. If you enter progress for a task that according to the schedule would not have started yet, the window Enter the actual start opens. It asks when the task actually started; the suggestion is the status date. With Apply progress you record it, with Cancel nothing changes.

100% without dates. If you set a task to 100% without an actual finish, the actual finish becomes the status date, even if the task was finished earlier. Then fill in the actual finish yourself.

A percentage below 100%. If you set a completed task back below 100%, the actual finish is dropped. If you clear only the actual finish, the percentage goes to 0 and the task stays In progress. If you want the task to count as not started again, also clear the actual start, or choose Not started at Status in the table.

Changing the duration of a running task. The work done stays done and the percentage adjusts. A task of 5 work days at 60% that you set to 10 work days ends up at 30%. The app refuses a duration shorter than the work already done: ‘Build inner cavity leaf’ is already 60% done: a duration shorter than the work already done isn't possible. The duration was not changed. In the table the cell reports This duration is shorter than the work already done.

The remaining duration is rounded. The app rounds the remaining duration to whole work days. For a task of 2 work days, 50% and 75% both give a remainder of 1 work day.

A phase. A phase has no progress of its own. In the panel it says Derived from the subtasks: change progress there. The summary task follows after calculating (F5). In the table the cell reports The progress of a summary task is derived from its subtasks and cannot be changed here.

Moving the status date later. The remaining work of running tasks starts on the new status date, and work that has not started yet cannot lie before that date. So move it only together with an update of the progress. If you set a status date without also entering progress, all work that has not started yet moves to that date (except in the Microsoft Project profile).

A mistake. Every progress change is one step for Ctrl+Z.

See also

Open Planner Studio

Tutorials

Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.

How-to guides

Explanation

Reference

Project

Clone this wiki locally