Report types

Nozzit edited this page Oct 21, 2026 · 1 revision

Report types

Every report on the Report tab, with the options that belong to it: what they do, the starting value, what changes in the report and where you find them. How to make a report and save it as a PDF is in Making and printing a report.

How the report window works

Open the Report tab (or press Ctrl+P). On the left is the Report column with the drop-down Report type, the block Summary with counts, the block Settings or Report options and at the bottom the button Export PDF. On the right is the preview. What you see in the preview goes into the PDF.

Report type — which report you see. Choose from eleven reports. Default: Gantt chart. Where: Report, at the top of the Report column.

Export PDF — makes the PDF. Effect: the result is only a PDF; the app does not send anything to a printer. If the schedule is out of date, the app calculates first. If the calculation gives an error, for example because of a loop in the relations, the button makes no file and shows the error. Where: Report, at the bottom of the Report column.

Remembered. The app keeps all report options on this device, for all your projects. They do not belong to the project file. Only the Company: field of the Gantt chart is not kept.

Current schedule. The reports use the last calculation. If the schedule has changed since then, the table reports show at the top The schedule changed since the last calculation — press Calculate (F5) for current values. If nothing has ever been calculated it says Not calculated yet — press Calculate (F5) for dates and float. If the project is in the view Dates as recorded, the reports show the dates from the source file and a strip says so.

Abbreviations. wd is work days. TF is total float, FF free float.

Paper and orientation

Paper: — the paper size of the PDF. Choose from A4, A3, A2 and A1. Default: A3. Effect: the pages are laid out for that size. There is one choice for all reports: what you choose for one report also holds for the others. On portrait A4 a wide table gets small, because the table is scaled to the page width. Where: Settings (Gantt chart and Resource diagram) or Report options (the seven table reports). The Milestone overview and the Variance show no choices.

Orientation: — landscape or portrait. Choose from Landscape and Portrait. Default: Landscape. Effect: like Paper:. Where: the same place as Paper:.

Gantt chart

The schedule as a bar chart, with a table on the left and a timeline on the right, over several pages if needed. The preview shows the paper with page header, table, timeline and legend. The block Summary counts Tasks:, Leaf tasks:, Critical: and Relations:. All options are under Settings.

Company: — the company in the page header. Default: the company from the project settings. Effect: only the header of the report; what you type over here is not kept. Change the company in Settings › Project › Project settings, in the field Client/organization, and confirm with Apply.

Author: — the author in the page header. Read-only: the app takes it from the project settings.

Font size: — size of text and table in the report. Choose from 90%, 100%, 110% and 125%. Default: 100%. Effect: with a larger font, text, rows and table grow and the timeline loses width. Independent of Text size in the settings.

Bar colors: — what the colour of a bar depends on. Choose from Critical path, Per task — automatic and By category, with a drop-down Category field for By category. Default: Critical path. Effect: this is the same choice as Bar colors on the View tab: if you change it here, the Gantt on screen changes with it. If the chosen field does not exist in this project, it says This field does not exist in this project. Work category is used temporarily.

Status line: — a line at the status date. Choose from None, Status date line and Progress line. Default: None. Effect: Status date line draws a line at the status date; Progress line draws the zigzag line that bulges to the progress of each task. If the project has no status date, it says Set a status date first and the report draws nothing.

Follow view (filter, grouping, sort) — only for the Gantt chart. Default: off. Effect: off puts the whole task tree on paper. On draws exactly the rows of the screen: with your filter, grouping, sorting and collapsed phases.

Auto-fit to paper — scale the timeline to the page width. Default: on. Effect: on scales the timeline to the width of the page; the number of pages follows from the height. Off uses a fixed scale (Zoom:) and also tiles across the width, which quickly gives many pages.

Zoom: — the fixed scale of the timeline. Only visible when Auto-fit to paper is off. Slider from 1 to 40. Default: 22. Effect: a larger value makes the timeline wider, so more pages across.

Timeline over: — spreads the timeline over more page widths. Choice from 1 through 8 pages. Default: 1 page. Effect: only with Auto-fit to paper; otherwise the choice is disabled and it says Only with auto-fit. Handy for a long schedule that you want to print in readable size.

Repeat header on each page — Default: on. Effect: on puts the page header on every page; off only on the first.

Repeat footer on each page — Default: on. Effect: on puts the footer (project name, print date and legend) on every page; off only on the last. A handout without a legend is unreadable, hence on.

Task names on bars — Default: on. Effect: the name of the task on the bar, where there is room.

Show completion — Default: on. Effect: the completed part of the bar turns grey, as in the Gantt, and the column Compl. appears in the table. A completed task gets no float band.

Truncate task names — Default: on. Effect: on cuts names in the table at the width of Name column:. Off lets the column grow with the longest name; it then says The name column adapts to the longest task name.

Name column: — the width of the name column. Only visible when Truncate task names is on. Slider from 60 to 400. Default: 130.

Show baseline overlay — the active baseline next to the bars. Default: off. Effect: a thin bar in the baseline colour under the task bar, only for tasks that are in the baseline.

Critical path — Default: on. Effect: only controls the red relation lines between two critical tasks and the legend line. The bars themselves follow Bar colors:, regardless of this checkbox.

Show float — Default: on. Effect: the float as a band behind non-critical bars.

Dependencies — the relation lines. Default: on. Effect: draws arrows between the bars.

Show only working days — compresses the timeline axis in this report. Default: off. Effect: weekends and holidays are skipped, and week bands then replace the weekend shading. Independent of the same setting for the Gantt on screen.

Weekends — Default: on. Effect: shades weekends and holidays in the timeline, as long as the scale makes days distinguishable. On the compressed axis (Show only working days) this checkbox has no effect.

Legend — Default: on. Effect: the legend in the footer.

Preview quality — how sharp the preview is. Choose from Standard, High and Maximum. Default: High. Effect: only the sharpness of the preview on screen; the PDF does not change. Where: Report, above the preview.

Resource diagram

The same bars as the Gantt chart, grouped per resource: who does what and when. The block Summary counts Resources:, Assignments: and Without resource: (with a period also Outside the period:). The diagram shares all options of the Gantt chart, except Follow view (filter, grouping, sort), Critical path and Dependencies: the rows do not come from the screen, a task can appear under several resources, and the relations are not drawn there. The checkbox Critical path is hidden and on. This comes with the options of the Gantt chart under Settings, with these four checkboxes and the period:

Each resource on a new page — Default: off. Effect: each resource starts on a new page, so you can hand out a sheet per crew or employee. Off gives one continuous document.

Include tasks without a resource — Default: off. Effect: the tasks without a resource come as the last band in the diagram, to see what nobody has yet.

Group by resource type — Default: off. Effect: a layer on top: first a band per resource type (labor, crew, subcontractor, equipment, material), within it per resource.

Show units/day and curve — Default: on. Effect: two columns after the task name with the units per day and the distribution curve of the resource of that band. If there is too little room for the timeline, the report leaves the columns out and says The Units/d and Curve columns were left out: …; more room comes from a larger paper size or landscape, a smaller font size or a narrower table.

Reporting period: — only the tasks that touch the period. Default: Project duration. Effect: the time axis runs exactly over the period. If there is nothing in the period it says No tasks in the reporting period — choose another period or Whole project. See Reporting period below.

Milestone overview

All milestones of the project in a table. No options of its own. The block Summary counts Milestones, Mandatory and Late. The columns are WBS, Name, Kind (Automatic, Start or Finish), Date, Constraint/deadline, Float, Mandatory and Status. The status is Late if the constraint is violated, the deadline is missed or the total float is negative; otherwise Critical if the milestone is critical according to the critical definition of the project; otherwise On schedule. Without milestones it says No milestones in this project. The PDF uses the paper and orientation you last chose for another report.

Variance

The current schedule next to the active baseline, for leaf tasks. No options of its own. The block Summary counts Tasks, Later and Earlier and shows Project end: +3 work days (the difference in work days between the baseline finish and the current finish). The columns are WBS, Name, Baseline start, Baseline finish, Current start, Current finish, Δ start (wd), Δ finish (wd) and Status. The status follows the finish: Later if the finish is later than in the baseline, Earlier if it is earlier, otherwise On schedule. New is a task that is not in the baseline, Dropped a task that is in the baseline but no longer in the schedule. Without an active baseline it says No active baseline — save a baseline or set one active. The PDF uses the paper and orientation you last chose for another report.

Look-ahead

What runs or starts in the period: the list for the weekly meeting. Options under Report options.

Reporting period: — the window of the report. Default: Next month. Effect: the report contains the uncompleted activities that touch the period, even if they span the whole period, plus overdue activities from before the reference day, as long as the end of the period is not before the reference day.

Near-critical ≤ (wd): — the threshold for Near-critical. Number from 0 to 60. Default: 5. Effect: a task with more than 0 and at most that many work days of total float counts as near-critical. At 0 only what the project's calculation option Mark near-critical marks counts.

The block Summary counts Activities, Overdue, In progress, Should have started, Starting, Critical and Near-critical. The status per row, always relative to the reference day: Overdue (not completed and the finish is before the reference day), Should have started (not started while the start was before the reference day), In progress, Starting (not yet started, starts in the window). The columns are WBS, Name, Start, Finish, Rem. (wd), Compl., TF (wd), Critical, Resources and Status.

Critical & near-critical

The activities that determine the project end and those that are nearly there. Option under Report options.

Near-critical ≤ (wd): — Default: 5. Number from 0 to 60. Effect and meaning as with the Look-ahead. The subtitle states the chosen threshold.

The report contains the uncompleted tasks that are critical (according to the solver and the critical definition of the project) or near-critical, sorted by float path, then by total float, then by start. The block Summary counts Critical, Near-critical, Critical chains and Leaf tasks. The columns are WBS, Name, Start, Finish, Rem. (wd), TF (wd), FF (wd), Path and Status. The column Path shows the float path if the calculation option Multiple float paths is on, otherwise a dash.

Progress report

Where the project stands on the status date. Options under Report options.

Reporting period: — Default: Last month. Effect: Completed in the past period counts within the period. Starting in the next period looks ahead from the status date, up to Look ahead until; with a Last period as far ahead as the period looks back.

Near-critical ≤ (wd): — Default: 5. As with the Look-ahead.

The block Summary shows Status date, Period, Look ahead until, Baseline finish, Forecast finish, Δ finish (wd), Planned (with (baseline) or (current schedule)), Actual, and the counts Complete, In progress, Not started, Overdue and Critical. Planned and actual are weighted by the duration of the tasks. Planned measures against the baseline if there is an active baseline, otherwise against the current schedule. The sections are Completed in the past period, In progress, Starting in the next period, Overdue and Open critical activities; a task can be in more than one section. Every section has the same columns: WBS, Name, Baseline finish, Forecast finish, Compl., Rem. (wd), TF (wd), Critical and Status. The status per row is Complete, In progress, Not started, Should have started or Should have finished.

Schedule health

A check of the schedule itself for errors and unusual values, with the DCMA 14-point assessment at the top. Options under Report options.

High float > (wd): — Number from 1 to 365. Default: 44. Effect: an uncompleted task with more total float than this falls under High float.

Long duration > (wd): — Number from 1 to 365. Default: 44. Effect: an uncompleted task, not a milestone, with a longer duration falls under Long duration.

Lag > (wd): — Number from 0 to 365. Default: 10. Effect: a relation with more lag falls under Long lag. A negative lag (lead) is always reported.

Near-critical ≤ (wd): — Number from 0 to 60. Default: 5. Effect: determines the check Near-critical.

The section DCMA 14-point assessment comes first. It follows the fourteen checks of the US Defense Contract Management Agency, with the formulas and thresholds from their EVMS Program Analysis Pamphlet (DCMA-EA PAM 200.1, October 2012). Per point you see Count, Of (the total that was counted over), Value, Threshold, Result and Detail. The result is Pass, Flag or n/a; for n/a the reason is in the detail. A flag is not a failure: the pamphlet calls it a reason to look further. The thresholds under Report options do not apply to this section; it always uses the thresholds from the pamphlet.

It counts incomplete leaf tasks, without milestones and hammocks, and the relationships into such tasks. The note above the report gives both numbers. The fourteen points:

  • Logic: tasks without a predecessor or successor. Threshold: at most 5%.
  • Leads: relationships with a negative lag. Threshold: none.
  • Lags: relationships with a positive lag, however short. Threshold: at most 5%.
  • Relationship types: the share of FS relationships. Threshold: at least 90%.
  • Hard constraints: tasks with a mandatory constraint or an MSO, MFO, SNLT or FNLT. Threshold: at most 5%.
  • High float: tasks with more than 44 working days of total float. Threshold: at most 5%. Needs a calculation.
  • Negative float: tasks with a total float below 0. Threshold: none. Needs a calculation.
  • High duration: tasks longer than 44 working days. Counts the baseline duration if the task is in the active baseline, otherwise the current duration. Threshold: at most 5%.
  • Invalid dates: an actual start or actual finish after the status date, or a forecast start or forecast finish before the status date. Threshold: none. Needs a status date.
  • Resources: tasks without a resource. Threshold: none. Only if the project uses resources; otherwise n/a.
  • Missed tasks: of the tasks the baseline says should be finished on or before the status date, the share that finishes later or is forecast later. Threshold: at most 5%. Needs a status date and an active baseline.
  • Critical path test: the app extends a critical task by 100 working days and recalculates, on a copy, without changing the project. The test passes if the last task of the project then does not finish before that task. It tests the critical, incomplete task with the earliest start; the detail names the task and how many working days the finish moved. In the view Dates as recorded this test is n/a (not calculated): the test calculates, and the report then shows the dates from the source file. Press Calculate (F5) and the test runs again.
  • CPLI: (critical path length + float) / critical path length. The length counts the working days from the status date to the finish of the last task; the float is the difference with the baseline finish of that task, or the calculated float if the task is not in the baseline. Threshold: at least 0.95. Needs a status date.
  • BEI: the number of tasks complete on the status date, divided by the number the baseline says should be complete by then plus the tasks without a baseline. Threshold: at least 0.95. Needs a status date and an active baseline.

Two points differ from the pamphlet because the app does not have the concept: High duration counts every incomplete task, as the pamphlet limits it to the detail planning period (rolling wave), and Resources looks at assigned resources only, not at costs. The pamphlet gives no number for the critical path test; the 100 working days are the app's choice.

The checks are in this order, with their severity. Error: Negative float, Missed deadline, Violated constraint and Inconsistent progress (actual start or finish after the status date, forecast start or forecast finish before the status date, 100% without an actual finish, actual finish but not 100%, progress without an actual start). Warning: No predecessor (open start) and No successor (open end) (not milestones), Long duration, Lead (negative lag), Hard constraint (a mandatory constraint or an MSO, MFO, SNLT or FNLT), Out-of-sequence progress and Missed task (against baseline). Info: Near-critical, High float, Long lag, Relationship other than FS and Without resource (only if the project uses resources). The report looks at leaf tasks that are not hammocks only. The block Summary counts DCMA flags, Errors, Warnings, Information, Leaf tasks and Relations; below the DCMA section are a section Overview (per check the severity and the count) and a section Findings (every task or relation). Without a calculation, the checks that need float are missing.

Resource loading

Per resource per week or month what is required against what is available. Options under Report options.

Reporting period: — Default: Project duration. Effect: every week or month that touches the period is included in full. That way a row shows the same number as the histogram.

Aggregation: — Choose from Weekly and Monthly. Default: Weekly. Effect: a row per calendar week (column Week of, with the Monday) or per calendar month (column Month).

Overloaded periods only — Default: off. Effect: on only shows the weeks or months with at least one overloaded day.

The columns are Resource, Type, Week of or Month, Required, Available, Variance (available minus required; negative is a shortage), Peak/day and Overloaded. Required is the sum of unit-days. Only weeks or months with demand are in it. The block Summary counts Resources, Weeks or Months, Overloaded weeks or Overloaded months and Overloaded resources.

Resource assignments

Per resource the activities it is attached to: what is this crew or crane doing? Options under Report options.

Reporting period: — Default: Project duration. Effect: with a period only assignments of activities that touch the period are included, plus overdue work from before the reference day. Project duration does not filter by date.

Include completed tasks — Default: off. Effect: on also includes the assignments of completed activities.

The rows are per resource, and within a resource by start. The block Summary counts Resources, Assignments and Tasks without a resource. The columns are Resource, Type, WBS, Name, Start, Finish, Rem. (wd), Units/day, Compl., Critical and Status. Resource and Type appear only on the first row of a resource. The status per row is the same as in the Progress report: Complete, In progress, Not started, Should have started or Should have finished.

WBS summary

The schedule rolled up per WBS element: the management overview. Options under Report options.

Level: — up to which level the WBS is shown. Choose from Full WBS and levels 1 through 8. Default: level 2. Effect: the subtitle says Up to level 2.

Show activities — Default: off. Effect: on also shows the leaf tasks themselves under each element.

The columns include WBS, Name, Start, Finish, Baseline start, Baseline finish, Duration (wd), Compl., Δ finish (wd), Min. TF, Act. (number of activities), Crit., Active and Done. Start and finish of a summary task come from the last calculation. Progress is duration-weighted over the leaf tasks. Min. TF and the counts concern the leaf tasks below. The block Summary counts WBS elements and Activities.

Reporting period

Four table reports and the Resource diagram work with a Reporting period:: Look-ahead, Progress report, Resource loading, Resource assignments and the Resource diagram. Each report remembers its own period. Below the drop-down are From and To, with the dates the choice produces.

Reference day. A period with Next or Last counts from the status date of the project, or from today if there is no status date. Then the table reports say No status date set — the report uses today (…). If you move the status date, the window moves along. Both days count.

Next week, Next 2 weeks, Next 4 weeks, Next 6 weeks, Next 8 weeks, Next 12 weeks — from the reference day, 7 days per week long. With status date Thursday 20 May, Next week runs from 20 through 26 May and Next 4 weeks from 20 May through 16 June.

Last week, Last 2 weeks, Last 4 weeks, Last 6 weeks, Last 8 weeks, Last 12 weeks — the same six, but counted back: 7 days per week long, through the reference day. Last 2 weeks runs from 7 through 20 May at 20 May.

Next month, Last month — a calendar month forward or back, up to a day before the same date in the other month. Next month runs through 19 June at 20 May; Last month runs from 21 April through 20 May.

Project duration — from the first start to the last finish of the schedule.

Custom — your own period. Effect: From and To become two date fields. They start with the dates of the choice you just had. The end date may not be before the start date (The end date is before the start date.) and both fields must be filled in (Fill in both dates.). If the input is not right, the report stays on the last valid period.

See also

Open Planner Studio

Tutorials

Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.

How-to guides

Explanation

Reference

Project

Clone this wiki locally