Managing resources
Goal: create, edit and delete resources (people, machines and material) in your project, so that you can assign them to tasks.
Before you put a bricklayer or a crane on a task, that person or machine has to exist as a resource. The resource records how much of it there is and on which days it works. With that the app works out whether you ask too much of it on one day. You edit a resource when the staffing changes, for example when a second bricklayer joins.
Two terms. Max units is the capacity per work day: 1 is one person or machine, 2 is two of them. An assignment is a resource on a task (see Assigning resources with a curve).
- Choose Resources › Manage › New resource. The resource panel takes over the workspace and an empty row appears at the bottom of the table. You can also open the panel with Resources › Manage › Resources and then choose New resource in project.
- Type the name, for example Bricklayer.
- Choose the Type: Labor (the default), Equipment, Material, Subcontractor or Crew.
- Fill in the other fields if needed. Everything has a default: Max units is 1 and Calendar is Project calendar. Rate/hour is empty. You can only fill in Unit for the type Material, for example m³.
- Press Enter or click outside the row. The resource is in the table. With Enter, an empty row opens below it straight away for the next one. Press Esc when you are done.
The row only becomes a resource once it has a name. With Esc, or by clicking away without a name, the app creates nothing. The order in which you fill things in does not matter: you may choose the type first and then type the name.
Edit the fields in the row. The app stores the name, the rate and the unit when you leave the field, and the other fields straight away.
- Max units is only accepted by the app if the value is greater than 0. With 0 or less the field gets a red border and jumps back to the previous value.
- Calendar decides on which days the resource works. Choose Project calendar or a calendar of its own. With + Resource calendar you create a new one, and the pencil (Edit…) opens the chosen calendar. If a task works on a day the resource is off according to its calendar, that day counts as overallocated. How to create a resource calendar is described in Setting up a resource calendar.
- Rate/hour and Total: Total is the loaded hours of that resource times the rate. A plasterer who is loaded for 32 hours with a rate of 50 per hour comes to 1,600.00. At the bottom of the table is the sum of all resources.
- Crew groups a resource under a resource of the type Crew. It is only a grouping: the app does not add up the capacity or the load of the members into the crew.
- The colored swatch on the left is the resource's color. It is display only and has no effect on the schedule.
Does your second bricklayer only arrive on 19 July? Click the arrow next to Max units. Under Time-phased capacity choose Add step. Each step has a date (From) and a number (Max units). From that date that number applies. Without steps the flat value always applies.
A new step starts with today's date and 1 unit. Change both, because otherwise a capacity of 1 applies from today.
- Click the bin in the row.
- If the resource has assignments, the app asks for confirmation, for example 'Bricklayer' has 4 assignment(s) — delete? Click the tick to delete or the cross to cancel. Without assignments the resource disappears at once.
The resource's assignments go with it. If a task has a task type other than Fixed duration and units, the app divides the work of the removed resource among the resources that remain. Depending on the task type, that changes their units or the task's duration. If the duration changes, the schedule is out of date.
You can undo creating, editing and deleting with Undo (Ctrl+Z).
Resources › Manage › Resource dock puts a compact overview in the right-hand column, next to Properties. There you see the name and color of each resource and a warning sign (Overallocated) next to a resource that is overallocated. You can only change Max units there. If you select one or more tasks, the overview shows only the resources of those tasks.
Only the type Material makes a difference for the calculation. Labor, Equipment, Subcontractor and Crew are treated the same. Material does not count towards a task's duration and is not leveled. In the histogram the All resources row does not count material either.
No name, no resource. An empty row disappears without a trace.
A new step in the capacity. If you forget to change the date and the number, the capacity is 1 from today.
Removing a resource you still need. If you remove it by accident, press Ctrl+Z straight away. The assignments come back too.
- Assigning resources with a curve: putting a resource on a task.
- Setting up a resource calendar: fixing the work days of one resource.
- Resolving overallocation: what to do when a resource has too much to do on a day.
- Resource panel: all fields and buttons of the resource panel.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project