Creating and using a layout
Goal: switch between views of your schedule with one click, for example only the critical tasks, the tasks per crew or a different sort order.
In the site meeting the client wants to see only the critical tasks. Then the site manager wants to look per crew at who is needed when. Then you want the whole schedule again. Setting filters, groups and sort orders again and again is cumbersome. A layout stores such a view as a button in the ribbon.
A layout can store six things: the filter, the grouping, the sorting, the columns of the task table next to the Gantt, the time scale, and the relationship lines and overlays (baseline, progress line, status date line, resource accent, float band and bar colors). Only what you tick changes when you click the button. The rest of your view stays as it is.
You filter, group and sort with a layout. The separate buttons Filter…, Group… and Sort… now only exist behind a hidden setting (see the pitfalls).
- Choose the View tab. In the Layout group there is a button per layout. By default that is Resource diagram.
- Click it. Resource diagram groups the tasks per resource, sorts within each group on start and turns the relationship lines off. A task with two resources appears under both.
- Click again to turn the layout off. The view returns to what it was before your click.
Each click is one step for Undo (Ctrl+Z), both turning on and turning off.
- In the Layout group, click New layout. The New layout window opens.
- Type a Name and choose an Icon.
- Under What does this layout store? are the six parts with a checkbox. A new window starts with all parts ticked and filled with what is on your screen now. Untick everything the layout must not change. If you only want a filter, leave only Filter on. Take over the current view fills all parts again with your screen.
- Set up the parts.
- Click Save.
The layout is now a button in the ribbon, but it is not applied yet. Click the button to turn it on.
Under Filter you build rules. Click + rule, choose a Field, an Operator and a value. If you only want the critical tasks: field Critical, operator equals, value Yes. The fields include Task Name, Start, Finish, Total Float, Progress and Milestone, plus your own activity codes and fields and Resources. The operators depend on the kind of field: for text you can choose contains, for numbers and dates between.
Which operators you get depends on the kind of field:
- Text (Task Name, WBS): equals, not equals, contains, starts with and is empty.
- Number and date (Total Float, Start, Progress): equals, not equals, less than, less than or equal, greater than, greater than or equal, between and is empty. With between there are two fields: for a number with From and To as a hint, for a date without a hint (the first date is the start, the second the end).
- Yes/no (Critical, Milestone, Near Critical): equals and not equals, with the value Yes or No.
- Choice (Work category, an activity code): equals, not equals, is one of (with tick-box values) and is empty.
- Resources: is one of and is empty.
- In progress: only between, with two dates (from and to).
With the field In progress and the operator between and two dates you get all tasks that run at any moment in that period, such as everything active in June.
You combine several rules with the list at the top: All of the following (AND) shows tasks that meet all rules, Any of the following (OR) tasks that meet at least one rule. With + group you add a subgroup with its own rules.
The filter looks at the tasks themselves. The phases (summary tasks) such a task falls under stay visible in grey, so you see where the task belongs. If you also group, those grey phases disappear.
Under Group you add a field with + level. There are at most two grouping levels. Without grouping you see the WBS tree. Under Sort you add a field with + level and choose Ascending or Descending. With two levels the second decides when values on the first are equal.
In the window click Apply without saving. The ticked parts go onto the screen, but no button is added. That is handy for a filter you only need once. Ctrl+Z reverses it.
Right-click the layout button. You choose Edit…, Duplicate or Delete. Delete asks for confirmation first. A copy is called name (copy). A built-in layout, such as Resource diagram, you cannot edit or delete; you duplicate it to make your own version.
Layouts that do not store the same parts can be on together. If you have a layout that only stores the filter Critical equals Yes (call it, for example, Only critical) and you turn it on together with Resource diagram (grouping, sorting, relationship lines), you get the critical tasks per resource. If two layouts store the same part, for example both a filter, the second takes over and the first goes off. If you turn that second one off again, you return to the view from before your first click, not to the first layout.
You forget to untick parts. A layout that also stores the columns, time scale and overlays puts those back to the saved state at every click. Your zoom then jumps away while you only wanted a filter. Check in the window that only the intended parts are ticked.
An incomplete rule shows nothing. If you choose no value for a yes/no field (it still says —) or leave the dates of In progress empty, no task matches and the list stays empty. Complete the rule.
A manual change turns the layout off. If you yourself change a part the layout stores, for example Relationship lines while Resource diagram is on, that layout drops out and the other parts go back to the view from before the layout. Zooming turns off a layout that stores the time scale, and making a column wider turns off a layout that stores the columns. The rest of the view then stays as it is. The Resource diagram does not store the time scale, so zooming does not affect it.
Columns apply to the task table next to the Gantt. The Columns part stores the columns of the table to the left of the timeline. The table on the Table tab keeps its own columns. How you choose columns is in Adjusting table columns.
Indent and outdent are off. As long as a filter, grouping or sorting is on, the displayed order is not the order of the schedule. Indent and Outdent are then disabled with the tooltip Not available while filtering/grouping/sorting. Turn the layout off to adjust the structure again, as described in Adjusting the structure.
The status bar does not follow. Tasks: in the status bar shows the number of tasks of the whole project, even if a filter shows only part of them.
Layouts are on your device, not in the project. The app keeps your layouts and the columns for all your projects on this device. The overlays from a layout (baseline, progress line and the rest) apply to all your projects. The filter, grouping and sorting that are on right now belong to the open project, but do not go into the project file: after saving and reopening the view is clean again. They also do not make the project "modified".
The separate buttons are hidden. Columns…, Filter…, Group… and Sort… as separate buttons on the View tab are an old view. You bring them back with Show classic view buttons under Legacy features on the Advanced tab of the App settings window (⚙ in the title bar). Prefer layouts.
- Adjusting table columns: choosing, moving and pinning the columns themselves.
- Making and printing a report: putting the view on paper with Follow view.
- Adjusting the structure: why you cannot indent while filtering.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project