Using the occupancy overview
Goal: see on which days two or more open projects together ask for more of a resource than the resource library has.
Your bricklaying crew is on the facades in one project and on the garages in another. Each project finds the crew neatly planned, because the histogram and the overallocation of a project only look at that one project. Only when you lay the projects side by side does it turn out that on the same days they together ask for more than you have bricklayers. The occupancy overview does that laying side by side for you.
The overview only counts resources that come from the resource library, in projects that are linked to the same library. How that calculates, you read in The resource library.
- Open the projects you want to compare, each in its own tab, see Working with several projects at once. The overview only sees projects that are open in this app.
- Link every project to the same library, and use the resource from the library in every project. Without a library link the resource panel does not show the overview. See Using the resource library.
- Calculate the projects with Calculate (F5), or turn on Calculate automatically. What the overview does with out-of-date projects is described under the pitfalls below.
- Go to one of the projects and choose Resources › Manage › Resources.
- At the top right, choose Occupancy. The overview belongs to the library of the project you are in. You cannot change anything in this panel: it is a read-only window.
Every resource from the library that is booked in at least one open project gets a row. Resources without a booking are not listed. The rows with the most double-booked days are at the top, then alphabetical.
- Documents says in how many projects the resource is booked, for example 2 documents.
- Period runs from the first to the last day with load, written as yyyy-mm-dd, for example 2027-06-07 – 2027-06-14.
- Peak / Capacity sets the highest daily load of all projects together against the capacity of the resource in the library, for example 4.0 / 3.0. If there is at least one double-booked day, it is shown in red.
- A red marker after the row, for example 3 days double-booked, counts the days on which the sum is greater than the capacity. If you hold the mouse over it, you see the dates.
- Click the small arrow before the name of a resource. The row opens up.
- At the top are the double-booked dates, the first five and then … and 3 more if there are more. Below that is, per project, the name with the period and the peak of that single project, for example Houses North 2027-06-07 – 2027-06-11 Peak: 2.0.
- Click the row itself to see a histogram at the bottom. Each project has its own color and the bars are stacked. The dashed line is the capacity of the library. If it changes over time, you see steps. Days that are double-booked get a red band behind the bars. Click the row once more to close the histogram again. Without a chosen row it says Select a resource to see the histogram.
The overview shows the problem, but does not resolve it. You have two options:
- Move a task in one of the projects, or give it fewer units per day. Then recalculate that project with F5.
- If someone really joins, raise Max units of the resource in the library. You do that in Resources › Manage › Resources, Library view.
Level… in the ribbon does not help here: it looks at the resources of the one project you are in, see Resource leveling.
The overview is empty. It says No library resources booked in the open documents. Then no open project has a resource from the library on a task.
You do not see the button Occupancy. The project you are in is not linked to a library.
A project does not count. It is not open in this app, it is linked to another library, or the resource in it is an own resource of that project. At the bottom of the overview it always says This overview only sees the documents opened in this app. A copy of a resource that has since been removed from the library does not count either.
A copy or variant counts in full. Every open project that is linked to the library counts, also if it is a copy or variant of another open project, for example a variant an MCP client made with planner_duplicate_document. Original and variant together can then show a double booking that in reality exists only once. The overview does not quietly filter on that: close the variant for a moment, or read around it.
A project is out of date. A project is out of date if you changed something in the schedule without recalculating. The overview then handles that project as follows:
- For a project that is not the active tab, the overview calculates in advance itself, without changing the project. Above the table it then says Changed documents have been calculated in advance for this overview; press F5 in the document, or turn on “Calculate automatically” to do this permanently. After the project it says Calculated in advance for this overview — the document itself still shows older dates until you press F5 there or turn on “Calculate automatically”. If Calculate automatically is on (Settings › Project › App settings, tab Planning), the app does really recalculate such projects as soon as you look at the overview, and the message disappears. If the active project is out of date too, the message from the next point is shown above the table instead.
- The overview does not calculate the project you are in yourself. If that project is out of date, it says A changed document has not been recalculated yet; it is included here with its last calculated figures. Press F5 in that document, or turn on “Calculate automatically”. and after the project Out of date: these are the last calculated figures — press F5 in this document. Watch out: last calculated figures is not quite right. The overview takes the old start dates, but already a changed duration or allocation. The figures can therefore differ from both the old and the new schedule, and from the bars in the Gantt. Only trust them after F5.
- If the overview cannot calculate a project, for example because of a loop in its relations, that project does not count. It is still listed, with Not counted: schedule not calculated — activate this document and press F5. and above the table At least one document has not been calculated and is not included in the occupancy.
The overview does not match what you expect. The capacity comes from the library (Max units of the library item, or its Time-phased capacity on that day), not from the Max units of the copy in the project. A sum equal to the capacity is not a conflict.
- The resource library: how the occupancy is counted, with a worked example.
- Using the resource library: linking projects and assigning resources.
- Resolving overallocation: overallocation within one project.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an MCP client
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the MCP link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- MCP tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project