Using split view and the mini map
Goal: see two stretches of the timeline side by side, and move quickly through a long schedule.
You are discussing the start of the foundation and, at the same time, the handover nine months later. Without help you keep zooming in and out and lose track of where you were. With split view you see the same schedule twice, side by side, each with its own time window. With the mini-map you see the whole project period in one narrow strip, and you jump with a click to the part you are looking for.
- Choose the View tab. In the Presentation group are Presentation, Split view and Mini-map.
- Click Split view. The Gantt splits in two. Both windows start with the zoom and position of your current view.
The two windows share the task list, the rows and the vertical scroll. What each window has for itself is the time axis: zoom and horizontal position.
- Zoom and scroll in the window your mouse is over. With the default setting for Scroll & zoom (Zoom + drag) the mouse wheel zooms in that window, centered on your mouse. If your setting follows another mode, the wheel does in both windows what that mode says.
- With the default setting you scroll through the rows with Shift plus the mouse wheel. That applies to both windows at once.
- The buttons Zoom + and Zoom - and the time scale list (for example Quarter) only work on the left window. So you zoom the right window with the mouse wheel.
- Drag the bar between the two windows to the left or right to make them wider or narrower. They start at half.
Click Split view again. One window remains, with the view of the left window. A new split view starts again with the view of that moment.
- In the Presentation group, click Mini-map.
- Below the timeline a strip appears of the whole project period, with the tasks of your current view as thin dashes (so after a filter only the tasks that filter shows) and a frame around the part you see now.
- Click anywhere on the strip to put the frame there. The window centers on that spot. Or grab the frame and drag it.
The mini-map only moves the time window. The rows stay as they are.
If split view is on, each window gets its own strip, under its own part of the timeline. Each strip controls only the window above it.
The mini-map does nothing if the whole project is already in view. If you zoom out so far that the whole schedule fits, there is nothing to move to and clicking has no effect. Zoom in first.
The mini-map is only on the Gantt. On the Table, IFC and Report tabs and in the full resource panel (Resources, not Resource dock) there is no timeline, so no mini-map and no split view either. They are back as soon as you return to a view with the Gantt.
Split view belongs to the project, the mini-map does not. Split view applies to the open project: if you switch to another project and back, it is still there. The mini-map is one choice for all projects and stays on or off after a restart. Both are screen choices: they do not go into the project file, do not make the project "modified" and are not in Undo.
Split view and presentation. Both stay in view when you turn on presentation mode (see Presenting on a large screen). Because the ribbon is gone then, you can no longer turn them on or off in that mode. So set them up properly before you start.
- Presenting on a large screen: the Gantt full screen, without the ribbon.
- Creating and using a layout: the time scale can also be stored as part of a layout.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an MCP client
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the MCP link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- MCP tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project