Moving a project

Goal: shift the whole schedule to a new start date, and see beforehand what that does to the finish.

When you need this

The start of the work moves: the permit comes later, or you reuse the schedule of an earlier house for the next one. Moving every task one by one is a lot of work. With Move project you enter one new start date and the app shifts everything along.

The project finish does not always move by the same amount as the start. The calendar does not move along: holidays, construction break and winter stop sit on fixed dates. An example: with Home › File › New you create a project with Start Date 29-09-2026, Country on Netherlands and Construction holiday on None, and put a schedule of 30 work days in it that finishes on 9 November 2026. If you move it to 14 December 2026, 76 calendar days later, it finishes on 26 January 2027. That is 78 days later, because 25 December and 1 January are now days off within your schedule. The duration stays 30 work days. The preview in the window shows this before you change anything.

Steps

  1. Choose Planning › Schedule › Move project…. The button is disabled as long as the project has no start date.
  2. Under Current project start see where the project starts now, and under New project start choose the new date.
  3. If the project has baselines, the box Shift baselines too appears. Leave it off if you want to keep seeing the shift as variance (see the pitfalls).
  4. Click Calculate preview. The app calculates the shifted schedule in full, without changing anything in your project.
  5. Look at the preview (see below). If it is right, click Move.

In the preview you see:

  • the shift in calendar days (Shift: 76 calendar days later);
  • Project start and Project finish, from before to after;
  • a red warning if the calendar interferes, or the message that the project duration stays the same;
  • the number of shifted tasks and what else shifts along;
  • warnings you should read (see the pitfalls).

The app calculates the new schedule straight away, so you do not need to use Calculate (F5), and fits the view to the whole project. The whole thing is one step for Undo (Ctrl+Z).

The Move button only works after a preview without an error, and if the new date differs from the current one. If you change the date or the box, the preview disappears and you calculate again.

What shifts along, and what does not

What shifts: the start and finish of every task, the actual start and actual finish, the dates of constraints (also of a hard Mandatory pin, see Constraints and deadlines), deadlines, the status date, the anchors of external relations and the availability steps of resources. The project start and, if you have filled it in, the project end date shift too.

What does not shift:

  • the calendars, so holidays, construction break and winter stop;
  • baselines, unless you turn on Shift baselines too;
  • a filled-in custom field of the type Date.

Pitfalls and what the app does

The finish moves by a different number of days. If the preview sees that the finish moves by more or fewer calendar days than the start, or that the project duration in work days changes, it shows a red warning with the numbers. You can then still cancel.

Baselines stay in place. A baseline exists to measure variance. If you move the project with the box off, you see the shift as variance from the baseline. If you turn the box on, the baselines shift along with the schedule. Only their dates shift; the date on which the baseline was saved does not.

A running project. Actual dates shift along. In a project where you have already entered progress, that is not always what you want. The app warns: Check whether that is correct for a running project.

External relations. The anchor in your own project shifts along, the source project does not. Refresh the links after moving with Home › Tasks › Link ▾ › Refresh all external relations. See External relations to another project.

Holidays that do not reach far enough. A calendar with generated holidays covers a number of years. If the moved schedule runs past that, the app calculates that year without holidays. The preview warns about it, for example: The generated holidays of calendar “Bouwkalender NL” cover 2025–2029; the shifted schedule runs to 2030. Regenerate the holidays. Move the project first. Then open Planning › Calendar › Calendar: next to the holidays it now says Regenerate. Confirm with Apply and the app recalculates. The range of the new holidays follows the project dates, so regenerating before the move does not help.

The date is in the past. That is allowed, but the preview mentions it: The new start date is in the past.

Changing the project start in Project settings is something else. If you change the start date in Settings › Project › Project settings and choose Apply, the schedule does not move. Only tasks without a predecessor or constraint that would then lie before the new start shift to that date, and the app tells you how many. If you want to shift everything, use Move project….

See also

Open Planner Studio

Tutorials

Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.

How-to guides

Explanation

Reference

Project

Clone this wiki locally