Importing progress from a spreadsheet

Nozzit edited this page Oct 21, 2026 · 1 revision

Importing progress from a spreadsheet

Goal: put the progress that site staff fill in on a spreadsheet into the schedule in one go, without clicking every task yourself.

When you need this

A subcontractor or site manager does not have the app, but reports his state every week: how many percent done, when started, when finished. You send him a sheet with your tasks, he fills in three columns and sends it back. From that the app reads only three values per task: completion, actual start and actual finish. The rest of your schedule is left alone. What the app does with that progress is explained in Progress, status date and baseline.

Steps

1. Set the status date and calculate

Set the status date as described in Updating progress. The site manager fills in actual dates up to and including that day. If the schedule is out of date, the app recalculates it before the sheet is made.

2. Make the sheet

Choose Planning › Progress › Export progress sheet. The same button is on the Table and Report tabs. The app makes an Excel file and suggests the name (project name)-voortgang.xlsx; in the browser the file lands in your downloads. Prefer a CSV? Choose File › Export › Progress sheet (CSV). The Excel sheet is there too, as Progress sheet (Excel).

The sheet has eight columns. The column names stay in English, with a short instruction in the language of the app after them:

  • OPS Task ID, WBS and Name are only there to recognise the task. Leave them alone.
  • Start and Finish are the planned dates, for information. The app never writes them back.
  • Completion (%), Actual Start and Actual Finish are the ones you fill in.

The Excel sheet is protected, without a password: only the three fill-in columns can be edited. Excel checks that a percentage is between 0 and 100 and that an actual date is a date. A phase (summary task) is marked grey with — summary task: do not fill in.

3. Have it filled in

For each task the site manager fills in:

  • Completion (%): 0 up to and including 100. The app also reads decimals, with a comma or a point (for example 33,3 or 33.3). The instruction in the CSV still asks for whole numbers: a spreadsheet with a different regional setting can read 8,38 as 838.
  • Actual Start and Actual Finish: in Excel as a date in your own regional setting; in the CSV as dd-mm-yyyy or as yyyy-mm-dd.

Whatever stays empty changes nothing. So an empty cell does not clear existing progress either; that can only be done in the app. A task that has not started, he leaves completely empty.

4. Read the sheet in

  1. Choose Planning › Progress › Update progress from a spreadsheet (also on the Table and Report tabs), or File › Import › Update progress from a spreadsheet. The window Update progress from a spreadsheet opens.
  2. Click Choose file… and choose the filled-in .xlsx or .csv file.
  3. If the dates in a CSV are ambiguous, the app asks Day first or month first?, with the date from your file read in two ways. Click the date that is right.
  4. You now see a preview. At the top are four counters: Applied, Unchanged, Waiting for a link and Refused. Below that, per task, what changes, for example Completion: 0% → 100%.
  5. Check the preview and click Apply. The window shows Result, with the counters and the rows that were refused and why. Finish with Close.

You cannot skip the preview. The button Apply is disabled as long as there is nothing to apply.

5. Recalculate the schedule

Reading in does not recalculate by itself. Press Calculate (F5), for example through Planning › Schedule › Calculate, unless Calculate automatically is on.

Rows that do not simply fit

The app links every row to a task, first on OPS Task ID and otherwise on the WBS number.

Link is uncertain. If the app found the task only by WBS number, the row is under Link is uncertain, with Confirm and Change. The row is applied too if you do nothing; so check that the task is right. Confirm takes the row out of this list; it changes nothing about what is applied. Change lets you choose another task. With Clear link you remove a link you made yourself. Note: a sheet from another project with the same WBS numbers is linked after all, under Link is uncertain, and applied when you click Apply.

Waiting for a link. If the app found no task, or several with the same WBS number, the row is under Waiting for a link. At Choose a task… choose the right task; you search by WBS number or name. If you do not link it, the row is refused.

Pitfalls and what the app does

A row that does not fit is refused with a reason. The rest of the sheet just carries on. These are the main messages:

  • The actual date is after the status date. Set the status date later or correct the sheet.
  • This task is planned to start after the status date: fill in its actual start in the sheet first. The app does not invent a start; supply it in the sheet.
  • Percentage outside 0–100. Check the decimal separator: 8.38 can be read as 838 by a spreadsheet with a different locale.
  • Summary tasks cannot receive progress from a sheet. The progress of a phase follows from the tasks below it.
  • Actual finish is before actual start.
  • Unreadable date. and Unreadable percentage.
  • The entered values contradict each other. For example an actual finish with a percentage below 100.
  • No task found for this row. The sheet mentions a task ID and WBS number that do not occur in this project.
  • This WBS code occurs on multiple tasks — link the row by hand.
  • Another row already claimed this task. Two rows point to the same task.
  • Refused by the planner. Another refusal by the planning itself, without a message of its own.

If the whole file is refused, one of these messages appears in the window: This file has no “OPS Task ID” or “WBS” column to link rows to tasks., This file has none of the Completion, Actual Start or Actual Finish columns., This file is too large to read as a progress sheet. (more than 16 MB), This file has too many rows to read as a progress sheet. (more than 50,000 rows) or This file is password-protected and cannot be read. or This file could not be read as a progress sheet.

No status date. If there is no status date yet and the import applies progress, the app sets it to today and tells you. So set it yourself first.

Everything back in one go. The whole sheet is one step for Ctrl+Z.

Only what you fill in. A row with no difference from the schedule counts as Unchanged. A task without a row in the sheet stays as it was.

See also

Open Planner Studio

Tutorials

Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.

How-to guides

Explanation

Reference

Project

Clone this wiki locally