Choosing the progress mode
Goal: decide how the app plans the remaining work of a task that has already started while its predecessor is still running: according to the relation (Retained Logic) or according to what actually happens (Progress Override).
On site, work often runs ahead of the logic. The painter already starts in the rooms that have been plastered, while the plasterer is still busy elsewhere. In the schedule that is, for example, a Finish-Start relation whose successor starts before the predecessor is finished. The app calls that out-of-sequence. If the status bar shows N out-of-sequence relation(s), you have such a case, and the progress mode decides how the app plans the remaining work of the successor. What the two modes do, with a worked example, is in Progress, status date and baseline.
- Update the progress and set the status date, as described in Updating progress.
- Go to Planning › Baselines & progress › Progress mode and open the list.
- Choose Retained Logic or Progress Override.
- Press Calculate (F5), for example through Planning › Schedule › Calculate. The choice makes the schedule out of date: the status bar reports Out of date — recalculate (F5). If Calculate automatically is on, the app does this itself.
How do you choose?
- Retained Logic is the default. The relation stays in force: the remaining work of the successor only starts once the predecessor is finished. Choose this if the order is really fixed, or if you want to plan cautiously.
- Progress Override lets reality win. The remaining work of the successor starts on the status date, without waiting for the predecessor. Choose this if the successor really keeps working and the finish date should not depend on a predecessor that is still running.
- Click the message N out-of-sequence relation(s) in the status bar. The Warnings panel opens, also reachable through Planning › Schedule › Warnings. Every relation is in it with the text Out of sequence: the successor's progress contradicts the relation, for example 4.2 Plastering → 4.5 Painting (FS).
- Look at the bar of the successor. Under Retained Logic it runs until after the finish of its predecessor. Under Progress Override it finishes earlier. In the example of the explanation that is Tuesday 27 July against Thursday 22 July.
No difference. The mode only has an effect on tasks that have already started while their predecessor is not yet finished. Without such a task nothing changes.
The message stays. Progress Override does not solve the out-of-sequence message. The mode decides how the app calculates; the contradiction between relation and progress remains. If the relation is no longer right, change it (Adding relations).
It belongs to the project. The choice is saved with the project file, applies to the whole project and can be undone with Ctrl+Z. A new project is on Retained Logic.
A P6 file. If you open a Primavera P6 file (.xer), the app takes the mode from the file. Besides Retained Logic and Progress Override, P6 also has Actual Dates. The app does not know that third mode; such a file calculates as Retained Logic. The import message counts that as 1 P6 scheduling setting used a safe fallback.
The calculation profile. In the Primavera P6 profile Progress Override also works backward, in the late dates and the free float of the predecessor (convention Progress Override ignores a started successor on the late side too). In the Open Planner Studio and Microsoft Project profiles that is not so. You find the conventions under Settings › Project › Project settings, in the block Calculation profile and options. In the example of the explanation that backward effect cannot be seen.
- Progress, status date and baseline: the difference between the two modes, with numbers.
- Updating progress: entering the progress the mode works on.
- Adding relations: changing a relation that is no longer right.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project