Right click menus
Which menus the right mouse button opens in the Gantt and in the task list, what each item does and which tasks it applies to. The items that also exist as a button or a shortcut are in The ribbon, tab by tab and Keyboard shortcuts.
There are four menus. Which one you get depends on where you click:
- On a task bar in the Gantt — the task menu, with Start relation from here at the top.
- On a task in the task list — the same task menu, without that one item at the top. This goes for the task list to the left of the Gantt and for the Table tab.
- On a group header in the task list — a small menu to expand and collapse groups. Group headers only appear when you group, for example with the Resource diagram layout.
- On empty space — in the Gantt next to or below the bars, and in the task list below the last task or on the grey New task row. The menu has New task, Add milestone and Paste; in the Gantt also Reset zoom and Fit to project. A new task or milestone goes to the bottom of the list. In the Gantt it starts on the date where you clicked; in the task list the name cell opens right away so you can type.
On the band of a group header in the Gantt, the right mouse button opens the menu for empty space; the group header itself has a menu only in the task list. A right-click in the timeline header does nothing. The column headers of the task list have their own menu, described in Adjusting table columns.
Which tasks does an item apply to? You click on one task, but the selection sets the scope. If the task you click on is part of the selection, the item applies to the whole selection. If it is not, it applies to that one task only. With a right-click on a bar in the Gantt or on a row in the task list, that task replaces the selection if it was not part of it. Every item that changes something is one step in Undo, also for a whole selection.
The items are in this order. A line between groups is a separator in the menu.
Start relation from here — only in the Gantt, on a bar. Turns on relation mode with this task selected; you then drag to the successor. See Adding relations.
Remove break and Remove all breaks — only in the Gantt, on a bar with interruptions. Remove break is only there if you click on a pause or the piece after it and the interruption is editable; it removes that one pause. Remove all breaks removes all of them, including interruptions from a source file that you cannot edit. See Splitting a task.
Edit... — opens the Edit task window for this task. See Task dialog and properties panel.
Insert above and Insert below — inserts one new task above the top task or below the bottom task of the scope, at the same level. It only works in the pure tree view, without filter, grouping or sorting; otherwise the app refuses with a message. See Adding tasks and milestones.
Add subtask — adds a new task as a subtask of the task you clicked on, at the bottom of its subtasks. For that one task only, not for the whole selection.
Add milestone — adds a milestone as a subtask of the task you clicked on. For that one task only.
Add relation — does the same as Start relation from here: turns on relation mode with this task selected. In the task list the item is disabled if the Gantt is not visible, with the tooltip Only available when the Gantt chart is visible.
Indent and Outdent — moves the tasks of the scope one level deeper or one level higher in the WBS. These two are only in the pure tree view. See Adjusting the structure.
Toggle milestone — turns the task into a milestone, or back. The new state follows from the task you clicked on and applies to the whole scope: if that one is a task, all tasks in the scope become milestones. A summary task and a task with assignments do not become a milestone; the rest of the scope does, and you get a message per reason.
Assign calendar ▸ — a submenu with Project calendar (the task then has no calendar of its own) and below it the available calendars. The current choice has a check mark. A task that is already on that calendar does not count and makes no extra Undo step. See Creating and assigning a calendar.
Progress ▸ — a submenu with 0%, 25%, 50%, 75% and 100%. The current value has a check mark. A summary task has no progress of its own: if there is one in the scope, its leaf tasks get the percentage. Without a status date the app sets it to today, with a message. A task that is planned to start only after the status date and has no actual start yet first leads to a question about the actual start; if you cancel it, nothing changes. See Updating progress.
Priority ▸ — a submenu with Low (100), Normal (500) and High (900), the leveling priority of the task. The current value has a check mark. See Resource leveling.
Trace path — shows the predecessors and successors of this task. If tracing is already on, the item is called Stop path tracing. See Tracing a path.
Collapse, Expand and Save branch as template — only for a summary task. Collapse and Expand are always both there, even if the task is already collapsed or expanded, and apply to the whole scope. Save branch as template saves the task with its subtasks and the relations between them as a WBS template. See Saving and inserting WBS templates.
Delete — deletes the tasks of the scope, with their subtasks. There is no confirmation; you get them back with Ctrl+Z, one step for the whole scope. See Selecting, deleting and undoing tasks.
This menu only exists in the task list, on a group header:
Collapse group or Expand group — collapses or expands only this group. The item shows what you can do.
Expand all and Collapse all — expands or collapses all groups at once.
You set up grouping with a layout, see Creating and using a layout.
- Dragging, panning and zooming in the Gantt: what dragging with the left and middle mouse buttons does.
- The ribbon, tab by tab: the buttons that have the same actions.
- Keyboard shortcuts: the keys that go with them.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an MCP client
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the MCP link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- MCP tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project