Tracing a path
Goal: make the chain of tasks before or after a task visible, so you can see what puts a task on its date and what moves along if it runs late.
The roofing only starts in three weeks and you want to know which task decides that. Or the bricklayer runs a week late and you want to see which tasks after it move along. In a schedule with dozens of relations you cannot see that from the lines. With path tracing the app colours all predecessors (tasks that come before the chosen task, directly or through other tasks) and successors (tasks that come after it) and dims the rest.
- Select the task whose path you want to see, in the task list or on its bar in the Gantt. If you select several tasks, the app traces from the task you selected first.
- Choose Planning › Path tracing › Predecessors for everything that comes before the task, or Planning › Path tracing › Successors for everything that comes after it. Both buttons can be on at the same time. The same two buttons are on the Table tab, in the Path tracing group.
- If you want both directions in one go, right-click the task, in the Gantt or in the task list, and choose Trace path.
- Look at the result in the Gantt and in the task list. How to read it is explained below.
- You stop by clicking the active button again, by right-clicking a task and choosing Stop path tracing, or with Esc. Esc also clears the selection.
If you select another task while tracing, the path follows the new selection.
- Predecessors are gold, successors purple. In the Gantt the bars change colour, in the task list a stripe appears to the left of the row: solid for predecessors, dashed for successors. The chosen task has an outline.
- A darker colour, in the task list a thicker stripe with bold text, marks the chain of driving relations: the relations that really determine the dates. What that means is explained in Relations and lag.
- All tasks outside the path are dimmed. Relation lines that do not belong to the path are fainter and dotted.
No task selected. Without a selected task there is nothing to trace: the button is on, but nothing changes on screen. Select a task first.
No emphasis on the driving chain. The emphasis comes from the last calculation. If the schedule has not been calculated yet, or the calculation gives an error, the app tints all predecessors and successors equally strongly. Press Calculate (F5), for example through Home › Schedule › Calculate, and look at the path again. After a change the emphasis stays with the previous calculation as long as the status bar says Out of date — recalculate (F5).
A relation on a phase. Tracing follows the relations as you laid them. A relation from or to a phase (summary task) connects the phase itself. For the calculation it applies to every task in that phase, but the path does not carry on to the tasks inside it. If you trace a task inside a phase that is tied to another task by a relation on the phase itself, you therefore do not see that relation. In that case select the phase itself.
Only the chosen direction. If only Predecessors is on, you do not see what comes after the task, and the other way round.
- Relations and lag: why a relation is driving and how the app calculates a task's start date.
- Critical path and float: which chain decides the end of the project.
- Adding relations: adding a relation if you miss a connection in the path.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project