Managing and sharing resource libraries
Goal: create and delete resource libraries, put calendars in them, and export or import a library, as a backup or to use it on another computer.
The library is not in your project files but in the app: in the desktop app in a file on this computer, in the browser in that browser's storage. It is not synchronized. If you clear the site data in the browser, the library is gone; so export it as a backup. If a colleague wants to work with the same crews and rates, you also hand the library over as a file. If your organization has several operating companies with their own crews, you make a separate library for each one. For a new project you choose which library it uses.
What a library is, you read in The resource library. You do not edit the resources themselves here but in the resource panel, see Using the resource library.
Choose File › Library. On the left is the list Resource libraries. On the right are the details of the library you click: name, the buttons, and the list Calendars. At the top it says that you manage resources in the Resources tab.
- Click the plus above the list (Add resource library). A library New resource library is added, and it is selected straight away.
- Type the new name in the name field at the top of the right-hand part and press Enter, or click outside the field. The app does not accept an empty name.
- Click Set as default to have this library preselected for new projects from now on. The default library has a star in the list.
- Under Calendars, click From project. A list opens with the calendars of your active project.
- Click the small arrow after the calendar you want to take over. Above the list it says Added. A calendar that is already linked to this library has already linked after its name.
- The calendar is now in the library's Calendars list. With the pencil (Edit) you change the name and save with the check mark. The trash can deletes the calendar immediately, without asking for confirmation. The copies in projects stay.
After Calendars there is a version number, for example v2. It goes up with every change to the library. A library calendar travels along to a project when you assign a resource that uses it. You attach it to a resource in Resources, Library view, in the column Calendar.
- Choose the library in the list.
- Click Export.
- In the desktop app and in Chrome and Edge you choose where the file goes. In other browsers it goes straight to your downloads folder and the app tells you so. The file is called
bibliotheek-followed by the name of the library, with the extension.ifc.
Below the buttons it says Exporting is also your backup: keep the file somewhere safe.
- Click Import. The window Import library opens for the library that you had selected in the list.
- Click Choose file… and pick the
.ifcfile of an export. If the file does not contain a library, it says This IFC file does not contain a resource library. - The app shows what is in it, for example 2 calendars, 5 resources (version 3).
- Choose what you want to do with it, see below.
- Click Add or Replace, or Cancel to stop.
You have two choices:
- Add as new resource library: the file becomes a separate library next to your existing ones. Below it says under which name, for example Will be added as “Mijn resourcebibliotheek (2)”. Nothing is lost and your active project stays linked to its own library.
- Replace an existing resource library: the entire content of the chosen library is replaced by the one from the file. It also says so: Importing replaces the ENTIRE pool of the selected resource library. If you have two or more libraries, you choose which one under Import into resource library. If your library is newer than the file, the app warns: Your local library is newer — importing may overwrite your changes.
The app proposes a choice itself. For a file that contained the default library, Add as new resource library is preselected. If the library from the file already exists on your computer and is not the default library, Replace an existing resource library is preselected, with exactly that library chosen. If in doubt, choose add: that overwrites nothing.
- Choose the library in the list and click Remove resource library. The button is grey for the last library, because there always remains one.
- Confirm with Delete. The question is Remove this resource library? If open projects are linked to it, it says This resource library is linked to 1 open project. Removing it will unlink that project. Continue? For more projects it says the same with the number, for example linked to 2 open projects.
The library is then gone, with all resources and calendars in it. The open projects that used it are unlinked: their resources stay as ordinary project resources. Export first if you want to keep the content.
A project file contains its own copies of the resources. If you also want to hand over the whole library, do the following. The export itself is also described in Exporting.
- Open a project that is linked to a library and choose File › Export.
- Tick Save library file alongside. The checkbox is only there for a linked project.
- Choose the card IFC and save the file. The app then also asks for a second file. It is named like the project with
-bibliotheekafter it, and contains the library.
The checkbox only works for the IFC export, not for the other export formats. Your colleague imports the second file as described above.
Two planners, two libraries. The app does not synchronize libraries between computers. The import window always shows a warning about it: Note: libraries are not synchronized between machines. If two planners work with the same resource library, the libraries may diverge. If your organization shares crews across operating companies, deliberately choose one shared pool.
Replacing overwrites everything. Everything you had in the chosen library is gone, and a library change falls outside Undo. Export first if you are unsure. Your projects keep their copies. The app updates copies that still exist in the new file. Copies that are no longer in it get the marking no longer in the library and keep working. If a copy differs, the window Link resource library opens (see Using the resource library).
Deleting a calendar from the list happens immediately. The app does not ask for confirmation, whereas deleting a resource does. That looks like a shortcoming. Library changes fall outside Undo.
- The resource library: how library and project relate to each other.
- Using the resource library: linking resources, assigning them and resolving deviations.
- Exporting: the export formats, including IFC with a library file.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project