Setting up a resource calendar
Goal: record on which days a resource is available, so that the histogram, the overallocation and the leveling calculate with it.
The bricklaying crew works only Monday to Thursday. The crane is on another project in the first two weeks of August. A subcontractor has four fixed work days. Without a calendar of its own the app assumes the resource works on the days of the project calendar.
A resource calendar changes no task date at all. It only determines when the resource is available. If a task works on a day on which the resource does not work, the capacity that day is 0 and the day counts as overallocated. If you want the task itself to run on other days, give the task a calendar of its own (Creating and assigning a calendar). The difference is covered in Calendars and working days.
- Choose Resources › Manage › Resources. The resource panel opens. If the resource does not exist yet, create it with New resource in project.
- Find the resource's row. In the Calendar column the default is Project calendar: the resource then follows the project calendar.
- In that list, choose + Resource calendar. The Resource calendar window opens. It has the same fields as the calendar form: Name, Work days, the working times and the Holidays. The new calendar starts as a copy of the standard calendar and is called Resource calendar.
- Give the calendar a name that fits the resource, for example Crew Mon–Thu, and set the work days: click Friday off under Work days. You put holidays or downtime in the Holidays list with Add holiday.
- Click Apply. The calendar is now in the project's library and linked to the resource, in one step that you undo with Undo. With Cancel nothing has been created.
In the Calendar column, choose a calendar from the list. Project calendar removes the calendar of its own again. If you want to adjust the chosen calendar, click the pencil next to the list (Edit…). The Resource calendar window opens with the current calendar.
- If the status bar says Out of date — recalculate (F5), press Calculate (F5).
- Choose Resources › Histogram › Histogram and click the resource in the list to the left of the histogram. The days on which the resource does not work but is scheduled are red. If you hold the mouse over one, the bar reports, for example, Does not work this day per calendar "Crew Mon–Thu".
- Under Resources › Overallocation is the number of overallocated resources, and the status bar reports, for example, 1 resource(s) overallocated.
Only the days count, not the hours. A resource calendar determines on which days the resource works. How many units are available that day follows from the resource's Max units, not from the working times in the calendar.
Leveling does not always solve this. If there is no window in which every day of the task falls on a work day of the resource, shifting does not help. Choose Resources › Leveling › Level… and click Calculate. The task is then under Remaining conflicts, with the reason The resource does not work on all days this task needs — shifting cannot resolve this. Then assign the task to another resource, or give it a calendar of its own.
A shared calendar. The list shows all the project's calendars, so also the project calendar and the calendars of tasks. If you adjust such a calendar with the pencil, the schedule of the tasks that use it changes too, and the status bar reports Out of date — recalculate (F5). Rather make a calendar of its own for the resource.
Overallocation is not always the calendar. A resource that works every day can be overallocated too: the tooltip only mentions the calendar if the day is not a work day of the resource.
- Calendars and working days: why a resource calendar shifts no dates.
- Creating and assigning a calendar: the fields of the calendar form.
- Generating holidays and the construction holiday: putting holidays and downtime in the calendar.
- Calendar windows: all fields of the calendar windows.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project