Days and hours
A task of 2 days and a task of 16 hours look the same, but the app calculates them differently. Why can you choose between days and hours? And what happens when a task in hours is tied to a task in days? In this article you read how the app counts days and hours, and where it rounds. The worked example shows the numbers.
A day task has a duration in whole work days, for example 5d. It occupies full work days. On the standard calendar it has a start and finish date without a time.
An hour task has a duration in working hours, for example 12h or 1h 30m. It has a start and a finish with a clock time, for example Tuesday 11:00.
The unit belongs to the task, not to the project. You can mix day tasks and hour tasks in one schedule. That is called mixed planning.
You use hours for work that does not fit in whole days: a crane you hire for twelve hours, a pour of six hours, a task that can only start after lunch. For everything else days are enough and clearer.
Hour planning is off by default. As long as it is, the app works in days. If a file does contain hour planning, such as tasks in hours, the app reports This file contains hour-based planning. Those tasks are still calculated, but you can only edit their duration once you turn hour planning on.
Every calendar has working-time blocks for each work day (called bands in the app). The standard calendar has 07:00 to 12:00 and 13:00 to 16:00. The gap is the break. The app derives those blocks from the calendar's Start (hour), End (hour) and break; you do not have to set anything for it. If you set blocks of your own per weekday, those take precedence.
The standard workday is the workday that occurs most often; its length is the sum of its blocks. So it is not an average: with Monday at 16 hours and Tuesday to Friday at 10 hours, the standard workday is 10 hours. If the work days differ in length, the most common daily total applies, and in a tie the highest. With four days of 8 hours and a Friday of 5 hours, the standard workday is therefore 8 hours. A calendar with its own hours per day (for example from Primavera P6) also calculates with this daily total, and the calendar window shows it. Its own value is kept for the export. If it differs, the calendar window shows an orange block below Standard workday. A task of 1870 hours on blocks of 10 hours therefore lasts 187 days, even if its own value is 8 hours per day.
The app counts working minutes from the start, through the working-time blocks. Breaks, evenings, weekends and holidays do not count. A task of 12 hours therefore does not fit in one work day of 8 hours: it runs on into the next day.
The app counts whole work days. The hours per day play no part. A task of 5 days finishes on the same day whether the calendar has 6 or 8 hours per day.
A day is the standard workday of the task's calendar. The app uses that in three places:
- For Duration display. Under Settings › Project › App settings, tab Appearance, you choose Automatic (native unit per task), Always days or Always hours. A task of 18 hours shows under Always days as
2.25d(18h): the native unit stays in brackets. - For a lag in hours after a day task (see Rounding).
- When you switch the unit of a task. The app then counts the days from the start of the task, each day with its own hours, and converts the duration immediately if the outcome is exact. Two days become
16h. On a calendar where Friday has 5 hours, 5 days from Monday become37h. Twelve hours cannot be turned into whole days on a calendar with days of 8 hours: the app then leaves the unit as it is.
The rules below apply to a Finish-Start relation on a calendar without working-time blocks of its own, such as the standard calendar.
- Hour → hour. The successor begins the moment the predecessor is finished, even if that is in the middle of a day.
- Hour → day. A day task never begins in the middle of a day. It begins on the first work day after the day on which the hour task finishes. The rest of that day stays unused and comes back as float of the hour task.
- Day → hour. A day task occupies its whole last day. The hour task begins on the first work day after it, at the start of the first working-time block.
The app rounds, or refuses, in four places:
- A day task after an hour task begins on the next work day. The hour task is, as it were, rounded up to whole days.
- A lag in hours counts in the lag calendar, by default that of the predecessor. If the predecessor is a day task on a calendar without working-time blocks of its own, such as the standard calendar, the app converts the lag to whole work days: the lag divided by the hours of the standard workday, rounded to a whole number; half a day rounds up. At 8 hours per day, 1 hour counts as 0 days, 4 hours as 1 day and 12 hours as 2 days. That also applies if the successor is an hour task. If the predecessor is an hour task, or its calendar has working-time blocks of its own, the lag counts exactly in working hours and the break does not count.
-
A duration in days is always a whole number. If you type
1.5d, the app reports Enter a whole number of days or hours, for example 2d or 12h. A duration in hours may be1.5h, or1h 30m. - Switching the unit only happens if the outcome is exact (see above).
The calendar is Monday to Friday from 07:00 to 12:00 and from 13:00 to 16:00: a standard workday of 8 hours. The project starts on Monday 7 June 2027.
Place crane lasts 12 hours. Monday has 8 working hours (5 until 12:00 and 3 after the break) and Tuesday the last 4 hours. The task runs from Monday 07:00 to Tuesday 8 June 11:00.
Adjust elements lasts 8 hours and follows with a Finish-Start relation. It begins right away on Tuesday at 11:00: that is 1 hour until the break and 3 hours after it. The last 4 hours are Wednesday from 07:00 to 11:00. The finish is Wednesday 9 June 11:00.
Finishing lasts 2 days and follows Adjust elements. A day task does not begin in the middle of a day, so it begins on Thursday 10 June and finishes on Friday 11 June.
If you leave out Adjust elements and tie Finishing directly to Place crane, Finishing begins on Wednesday 9 June and finishes on Thursday 10 June. The rest of Tuesday (4 working hours) cannot be used. You see those 4 hours again as the total float of Place crane: half a work day.
Reverse the order and it is simpler. Pour foundation lasts 2 days, from Monday 7 to Tuesday 8 June. Place crane now lasts 4 hours and follows. It begins on Wednesday 9 June at 07:00 and finishes at 11:00.
Between Place crane (12 hours) and Adjust elements (8 hours) you put a lag of 2 hours. Adjust elements then does not begin at 11:00 but on Tuesday at 14:00: 1 hour until the break, and 1 hour after it. The finish moves along to Wednesday 9 June 14:00.
After a day task a lag works differently. Pour foundation finishes on Tuesday 8 June. Without a lag Finishing begins on Wednesday 9 June. With a lag of 4 hours that is half a day, and the app rounds it up: Finishing begins on Thursday 10 June. With a lag of 1 hour the app rounds down, and Finishing simply begins on Wednesday.
Now Friday has only one block, from 07:00 to 12:00: 5 hours. The other days stay at 8 hours. The standard workday stays 8 hours, because that is the most common daily total. A week now has 37 working hours.
A task of 40 hours from Monday 7 June 07:00 uses Monday to Thursday (32 hours) and the Friday (5 hours). The last 3 hours fall on the Monday after, from 07:00 to 10:00. The finish is Monday 14 June 10:00. A task of 5 days would occupy 37 hours from Monday, and that is what the app proposes if you switch the unit of 5 days to hours.
In tutorial 4, on hour planning, you plan a crane job in hours yourself.
"8 hours is 1 day." Only if the calendar has days of 8 hours. On the calendar with the free Friday afternoon, 5 days is 37 hours, not 40.
"If I set more hours per day, my day task finishes sooner." No. A day task counts whole work days. The hours per day only change what a day is worth in hours, for example in the display and for a lag in hours. Only for a task with resources and the task type Fixed work or Fixed units does the duration change with it, because the work stays the same: 40 hours of work is 5 days at 8 hours per day and 7 days at 6 hours per day.
"A task of 8 hours lasts one day." Only if it starts at the beginning of the day. If it starts later, like Adjust elements on Tuesday at 11:00, it runs on into the next day.
A calendar with working-time blocks of its own behaves differently from the standard calendar. You get such a calendar by setting working times per weekday or by choosing a shift preset (2 shifts, 3 shifts, Night shift or 24/7). On such a calendar a lag in hours counts exactly in working hours, also after a day task.
Turning hour planning off removes nothing. Tasks in hours remain and are still calculated, but you cannot edit them until you turn hour planning on again.
- Turning on hour planning: the steps to plan a task in hours.
- Setting working times: adjusting the working-time blocks of a calendar.
- Calendars and working days: how the app counts work days and which calendar wins.
- Adding relations: the steps to add a relation or lag.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project